CDI Engineering Group, Inc. v. Administrative Exchange, Inc.

222 S.W.3d 544, 2007 Tex. App. LEXIS 1877, 2007 WL 703565
CourtCourt of Appeals of Texas
DecidedMarch 8, 2007
Docket14-05-00621-CV
StatusPublished
Cited by16 cases

This text of 222 S.W.3d 544 (CDI Engineering Group, Inc. v. Administrative Exchange, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
CDI Engineering Group, Inc. v. Administrative Exchange, Inc., 222 S.W.3d 544, 2007 Tex. App. LEXIS 1877, 2007 WL 703565 (Tex. Ct. App. 2007).

Opinion

OPINION

CHARLES W. SEYMORE, Justice.

CDI Engineering Group, Inc. (CDI) appeals a judgment in favor of Administrative Exchange, Inc. (AEI) on the grounds that: (1) a letter memorializing an agreement between the parties is not an enforceable contract; (2) the trial court erred in submitting an incorrect question to the jury; (3) the evidence is legally and factually insufficient to support the jury’s determination that all conditions precedent to the agreement were met; and (4) the evidence is legally and factually insufficient to support the jury’s award of damages. Because we find the evidence legally insufficient to support the jury’s finding that all conditions precedent to the agreement *546 were met, we reverse and render judgment that AEI take nothing.

I. BACKGROUND

In early 2002, Lyondell Chemical Company and Equistar Chemicals, LP (Lyon-dell) proposed a vendor managed program to manage their temporary employees. Prior to the proposal of this program, Lyondell hired a large number of temporary employees through several different staffing companies. The purpose of the program, the genesis of which arose after the tragedy of September 11, 2001, precipitating Lyondell’s concern with background checks, was to consolidate the hiring of temporary employees with one company that could oversee any necessary subcontractors. Lyondell solicited bids from a number of temporary staffing companies to act as a general contractor for the program. Lyondell sought a staffing company that could provide both technical and nontechnical employees. 1 Both CDI and AEI submitted proposals. CDI had experience primarily providing technical employees; AEI specialized in nontechnical employees. Lyondell rejected AEI’s proposal because AEI is a regional, not a nationally based, company; CDI, which has a national presence, was included as one of four semi-finalists for the vendor managed program. Lyondell informed CDI that for CDI to win the contract it needed to team with a firm that provided nontechnical employees.

In March 2002, Philip Luna, vice president of CDI, contacted Dick Darroh, president of AEI, to discuss working together to win the Lyondell contract. The parties agreed that AEI would supply nontechnical employees to CDI for the purpose of obtaining the Lyondell vendor managed program. On April 1, 2002, the parties memorialized their agreement in a letter, with the following language pertinent to our inquiry:

This letter will serve to confirm CDI Engineering Group’s (CDI) intent to respond to Lyondell Chemical Company and Equistar Chemicals, LP, RFP No.2002-04. CDI would like to team with Administrative Exchange, Inc. (AEI) for the bidding and execution of this Managed System for Technical and Clerical Staff Augmentation Program.
[[Image here]]
CDI agrees to utilize AEI as exclusive supplier for those positions described as clerical and administrative non-professional and those described as human resources, accounting, laboratory, legal, tax and treasury. CDI will be responsible for the remaining technical and professional positions, and will utilize AEI as a preferred supplier for these positions as needed.

As part of the bidding process, on May 20, 2002, Lyondell met with CDI to discuss CDI’s proposal. At that time, Dave Gordon, director of corporate staffing for Lyondell, informed CDI that Lyondell viewed AEI as an obstacle to CDI’s bid. Lyondell employees informed CDI that they would permit AEI to manage the nontechnical positions in the contract as a subcontractor under CDI. Lyondell and CDI subsequently entered into a detailed contract under which CDI would manage all of Lyondell’s temporary employees. The contract expressly approved AEI, CDI Professional Services, and Today’s Staffing as subcontractors for CDI. There *547 was no clear provision in the contract that AEI would be the exclusive supplier and supervisor of nontechnical employees.

In August 2002, AEI learned that CDI was using other staffing companies to provide nontechnical employees to Lyondell. At a meeting on August 22, 2002, a representative of CDI told AEI that it would not be permitted to manage other nontechnical vendors. Moreover, AEI was informed that CDI intended to retain the forty current AEI employees and would recruit additional nontechnical employees from other staffing companies. AEI rejected CDI’s proposal as contravening the April 1, 2002 agreement. CDI responded that the agreement was contingent on Lyondell’s approval of AEI as an exclusive supplier. CDI contended that it was not bound by the agreement because Lyondell did not approve AEI as the exclusive supplier of nontechnical services. AEI subsequently sued CDI for breach of the April 1, 2002 agreement, fraud, and misappropriation of trade secrets. At trial, a jury found that the April 1, 2002 letter was an enforceable agreement, that all conditions precedent to the agreement had been met, that CDI breached the agreement, and that AEI suffered damages of $879,168.89. The jury found that CDI did not commit fraud or misappropriate trade secrets.

II. APPROVAL OF AEI AS AN EXCLUSIVE SUPPLIER WAS A CONDITION PRECEDENT TO THE CONTRACT

In its third issue, CDI contends the evidence is legally and factually insufficient to support the jury’s determination that all conditions precedent had been met for AEI to enforce the agreement 2 . Our consideration of this issue is controlled by Question No. 3, which was posited to the jury as follows:

Have all conditions precedent to AEI’s ability to enforce the agreement occurred?
Conditions precedent to an obligation to perform are acts or events that occur after the contract is made and that must occur before there is a right to immediate performance and before there can be a breach of contractual duty. You are instructed that Lyondell’s approval of AEI as the exclusive supplier of nontechnical services is a condition precedent to AEI’s ability to enforce the agreement.

A. The Standard of Review.

The test for legal sufficiency, “must always be whether the evidence at trial would enable reasonable and fair-minded people to reach the verdict under review.” City of Keller v. Wilson, 168 S.W.3d 802, 827 (Tex.2005). “[L]egal-suffi-ciency review in the proper light must credit favorable evidence if reasonable jurors could, and disregard contrary evidence unless reasonable jurors could not.” Id. Jurors cannot ignore undisputed testimony that is clear, positive, direct, otherwise credible, free from contradictions and inconsistencies, and could have been readily controverted. Id. at 820. Although the reviewing court must consider evidence in the light most favorable to the judgment, and indulge every reasonable inference that would support it, if the evidence permits only one inference, neither jurors nor the reviewing court may disregard it. Id. at 822. We sustain a legal sufficiency challenge when the record discloses one of

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cajun Constructors, Inc. v. Velasco Drainage District
380 S.W.3d 819 (Court of Appeals of Texas, 2012)
Rowan Companies, Inc. v. Wilmington Trust
305 S.W.3d 698 (Court of Appeals of Texas, 2010)
Mensa-Wilmot v. Smith International, Inc.
312 S.W.3d 771 (Court of Appeals of Texas, 2009)
Khorshid, Inc. v. Christian
257 S.W.3d 748 (Court of Appeals of Texas, 2008)
Landing Council of Co-Owners v. Durham
244 S.W.3d 462 (Court of Appeals of Texas, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
222 S.W.3d 544, 2007 Tex. App. LEXIS 1877, 2007 WL 703565, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cdi-engineering-group-inc-v-administrative-exchange-inc-texapp-2007.