C & B Construction, Inc. v. Dashiell

172 A.3d 960, 234 Md. App. 424
CourtCourt of Special Appeals of Maryland
DecidedNovember 1, 2017
Docket1307/16
StatusPublished
Cited by1 cases

This text of 172 A.3d 960 (C & B Construction, Inc. v. Dashiell) is published on Counsel Stack Legal Research, covering Court of Special Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
C & B Construction, Inc. v. Dashiell, 172 A.3d 960, 234 Md. App. 424 (Md. Ct. App. 2017).

Opinion

Zarnoch, J.

This is a dispute over the nonpayment for construction work performed by subcontractor, appellant C&B Construction (“C & B”) for general contractor Temco Builders, Inc. (“Tem-co”). At the heart of this case is whether C&B may employ the Maryland Construction Trust Statute, Md. Code (1974, 2015 Repl. Vol.), Real Property Article (RP) §§ 9-201 et seq., to hold officers of Temco, appellees Vice President Jeffrey Dashiell (“Dashiell”) and President Edward J. Maguire (“Ma-guire”), personally liable for money owed to C & B by Temco. After C&B concluded its case at a bench trial in the Circuit Court for Wicomico County, Dashiell and Maguire filed a motion for judgment, which the circuit court granted based on its finding that RP § 9-204(a) 1 did not permit C & B to hold Dashiell and Maguire personally liable. The key issue we must address, therefore, is whether the applicability clause in § 9-204(a) required C & B to establish that its subcontracts were subject to either the Little Miller Act or the mechanics’ lien statute. If the Construction Trust statute does apply, C&B asks us to address whether the circuit court erred in granting judgment to Dashiell and Maguire, despite evidence showing that Temco had been paid by the owners in full or in large part based on Temco’s applications for payment.

BACKGROUND AND PROCEDURAL HISTORY

On six construction projects located across Maryland, C&B performed various drywall, ductwork, and other related construction work as part of a subcontract with Temco. According to C & B, for five of the six projects, C&B completed all of its obligations under the subcontract with Temco, and Temco was paid by the owners for all or the majority of the work performed by C & B. However, Temco failed to pay C & B for the work it performed. Additionally, on a sixth project, C&B alleged that Temco owed C & B for work for which Temco had received credit against a debt to another company, but failed to pay C&B. Neither party disputes that Temco failed to pay C & B for work performed under the subcontracts. According to C & B, rather than paying C & B for the work it performed, Dashiell and Maguire spent the money they received from the project owners by paying other subcontractors and Temco office expenses, or by repaying themselves for money they had put into the business.

On October 1, 2015, C&B filed a complaint in the Circuit Court for Wicomico County against Temco, as well as Dashiell and Maguire individually. For each of the six projects, C&B alleged breach of contract against Temco and sought to hold Dashiell and Maguire individually liable under the Maryland Construction Trust Statute. 2 C & B’s claims against Dashiell and Maguire included primarily three allegations: (1) “During the course of the Project, the owner paid Temco for labor and materials supplied to the Project by C&B” and “Temco held these monies in trust for C&B”; (2) “Defendants Maguire and Dashiell, as officers/managing agents for Temco, had direction over and control of the monies held in trust by Temco for the benefit of C&B”; and (3) “Defendants Maguire and Dashiell used and/or retained the monies held in trust for C&B for purposes other than to pay C&B for the materials and labor it supplied to the Project.” For the six projects for which C&B alleged it was not paid for work performed, C&B sought a total of $218,349.90. 3

On May 3, 2016, Temco entered into a consent judgment with C&B, agreeing to the entry of an award against it in the amount of $225,607.00. 4 C & B’s claims against Dashiell and Maguire, however, proceeded to trial on July 13, 2016. At the conclusion of C & B’s case, the Temco officers moved for judgment, asserting that the Construction Trust statute did not apply in this case, because the subcontracts were not subject to either the Little Miller Act or the mechanics’ lien statute. 5 After hearing argument, the Circuit Court Judge Donald C. Davis agreed with Dashiell and Maguire, noting:

[I]t seems to me really looking at the Statute and Section 9-204(a) ..., it applies to contracts under the Maryland Little Miller Act, and there is no contention that any of the contracts in this case would be subject to the Maryland Little Miller Act as well as properties subject to 9-102 of this Article which is the Mechanics Lien Statute.
And the only way to know whether the property is subject to 9-102 is for evidence to be provided that it is subject to 9-102, which I am just going to shorten it up and say that it’s either basically new construction or every building repaired, rebuilt or improved to the extent of 15 percent of its value.
And in this case, I have looked at the contracts, and there is nothing to indicate that the contracts are for any of the other exceptions. [... ]
There is no way for the Court to make any judgment as to whether or not that improvement is to the extent of 15 percent of the value of the project.
And as I said, there is no way for the Court to infer that[,] because there is no evidence that would permit a finding, a direct finding from the evidence. And it does seem to me that a basic proposition is that one cannot proceed under the Construction Trust Statute without first establishing that the ... contract for which that construction trust is sought to be imposed is one which would be lienable. So I think sort of the basic proposition is that Plaintiff must first establish that the property is I will say lienable under Section 9-102 as a predicate for anything under Section 9-201 [et seq.], and there is really no evidence in this case that would permit me to make that finding directly from the evidence or by any inference from the evidence that has been submitted.
So I don’t think—the question is a closer one as to whether or not there is adequate evidence of earmarking, but I don’t think I need to get to that point really, because I don’t believe that the evidence as submitted is sufficient for me to, even if I looked at it in the light most favorable to the Plaintiff, which I’m not required to do, but even if I did do that, I don’t think the evidence is sufficient.
So I’m going to grant the motion for judgment on behalf of Mr. Maguire and Mr. Dashiell.

On July 19, 2016, the circuit court issued a formal ruling in favor of Dashiell and Maguire. C&B filed a Motion for New Trial, which the circuit court denied without a hearing on August 16, 2016. C & B’s appeal to this Court followed.

DISCUSSION

Our focus here is on the proper interpretation of RP § 9-204. The Court of Appeals reiterated in Nesbit v. Gov’t Emps. Ins. Co.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

C & B Constr., Inc. v. Dashiell
190 A.3d 271 (Court of Appeals of Maryland, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
172 A.3d 960, 234 Md. App. 424, Counsel Stack Legal Research, https://law.counselstack.com/opinion/c-b-construction-inc-v-dashiell-mdctspecapp-2017.