Butler v. Baber

512 So. 2d 653
CourtLouisiana Court of Appeal
DecidedNovember 13, 1987
DocketCA-4569
StatusPublished
Cited by2 cases

This text of 512 So. 2d 653 (Butler v. Baber) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Butler v. Baber, 512 So. 2d 653 (La. Ct. App. 1987).

Opinion

512 So.2d 653 (1987)

George J. BUTLER, et al.
v.
Winston C. BABER, et al.

No. CA-4569.

Court of Appeal of Louisiana, Fourth Circuit.

August 28, 1987.
Writ Granted November 13, 1987.

*654 Alvin A. LeBlanc, Jr., Kenner, for plaintiff.

J. Walter Ward, Jr., Christovich & Kearney, New Orleans, for defendants, Winston C. Baber, d/b/a Progress Petroleum Co., and Highlands Ins. Co.

Jesse S. Guillot, New Orleans, for defendants, Robert P. Waldron, Individually, and Robert P. Waldron, Inc.

Before GARRISON, BARRY and CIACCIO, JJ.

CIACCIO, Judge.

George Butler, George Butler, Inc., and Leo Bianchini[1] appeal a judgment which denied recovery for alleged damage to oysters and water bottoms on their leases in Plaquemines Parish.

Plaintiffs sued Winston Baber d/b/a Progress Petroleum Company and his insurer Highlands Insurance Company, after Progress dredged a canal through Wilkinson Canal (a portion of Bayou Dupont) and the marsh into Wilkinson Bay. Included as defendants were Robert Waldron, Robert Waldron, Inc., the consultant hired to determine alternate routes for the canal, Southern Louisiana Contractors (SOLOCO), the dredger, and J. Ray McDermott & Company, hired to backfill and dam the canal. SOLOCO and McDermott compromised and were dismissed along with their third party demands.

Plaintiffs primarily argue that the trial court erred by concluding that they did not carry their burden of proof, and in failing to consider strict liability under La.C.C. Art. 667. Defendants/appellees reply (as in their answers below) that Leo Bianchini's claim had prescribed and that George Butler has no right of action.[2] The defendants also contend that the judgment is not clearly wrong.

I

At issue are a number of oyster leases in Wilkinson Bay: nos. 18515, 19386, 19387, 20057, 20058, 20135, 20136, 20569, 21936, 21937, 21942, 21943, 21986, 23386, 20247, 21984, 21989, 21990 and 23688. Bianchini and Butler had jointly owned 20247 and 21984, Butler owned 21989 and 21990, and the others were sold by Bianchini to Butler *655 on August 26, 1977, and recorded on August 31, 1977. An Act of Correction was executed on November 6, 1979, and the transfer was registered with Wildlife and Fisheries on November 13, 1979.

With the exception of No. 18515, the leases were sold by Mr. and Mrs. Butler to Oysters Champagne, Inc. (whose president was Dr. Hugh Champagne)[3] on December 7, 1979. In an Act of Correction dated November 29, 1982, the Butlers reserved their right to any cause of action arising from Progress's drilling and dredging operations in the Wilkinson Bay area. In June, 1983, George J. Butler, Jr., Inc. assigned any judgment in this suit to Delta Bank and Trust Company.

Baber obtained state mineral lease no. 7502 for Tract No. 14692 which covered the Wilkinson Bay area. The lease provides: "[I]n conducting all operations under this Lease requiring dredging, filling, or local navigation in order to explore, develop or exploit shallow-water areas, Lessee shall comply with the applicable requirements of the appropriate Louisiana state agency charged with the environmental management of said area."

It further states that after completion of operations "the affected water bottoms shall, to the extent reasonably possible of accomplishment, be returned or restored to a condition as nearly equivalent to that which existed before said operations were conducted and/or structures were constructed." The language notes that the mineral lease is in an oyster restricted area and all operations were to be in strict conformity with regulations.

Baber obtained canal right of way servitudes from two land owners, and those documents state his intention to "sweep out" the Wilkinson Canal and/or Bayou Dupont to a depth of eight feet and to then dredge across the land area. The right of way was for a 70 feet width with the right to deposit the spoil on the adjacent area. The documents declare a fill dam would be deposited across the west end of the canal adjacent to Wilkinson Canal and at the east end at the entrance to Wilkinson Bay. The soil dam was to be above the marsh to compensate for settlement. The fill was to be "carried not only the seventy (70') foot width of the original canal, but also an additional twenty (20') feet back from the existing banks at each side of the said canal."

Baber obtained a Damage Release from Butler for $8,000 which waived damages that had or may occur to oyster lease no. 20135 insofar as the damages may result from operations, including dredging related to Progress's proposed lease 7502, well no. 1 in the Bay. The release was limited to the area "500 feet wide from center of canal and slip...."

Progress obtained a permit from the Army Corps of Engineers to "dredge and maintain channels and a canal" in Wilkinson Canal, Wilkinson Bay and the adjacent wetlands central to a point about 8.0 miles southerly from Myrtle Grove, Louisiana. The permit contained a special condition: "That no dredged material is to be placed in the oyster planting area or in the small area of natural oyster within lease No. 20135 as identified in letter from Mr. Robert Waldron dated 28 February 1978 to Progress Petroleum Company." Sheet 1 of the attached survey declared: "NO SPOIL TO BE PLACED IN WILK. CANAL. SPOIL PLACED IN WILK. BAY WILL NOT DECREASE WATER DEPTH BY MORE THAN 0.5 FT." Sheet 1A noted: "Spoil to be placed on land."

The permit survey allowed a total of 157,072 cubic yards of material to be swept along the route. The permit and survey marked the route recommended by Robert Waldron, Baber's geological consultant, who had selected three alternatives. The route from Wilkinson Canal/Bayou Dupont cut across the marsh to the north and east and went to the well location in Wilkinson Bay. The original permit positioned the *656 well immediately north of an oyster planting area on Butler's Lease No. 20135. The Corps of Engineers required that it be moved. The amended location (okayed by Waldron) placed the well 600 feet north and 200 feet east of the original site. In a letter dated April 13, 1978, Waldron stated the change would remove the drilling operation from the oyster area "allowing the canal and well slip dredging to be performed with no fear of depositing spoil within the shell fish planting."

Baber hired SOLOCO to dredge the 70 foot wide canal through Wilkinson Bayou and the marshland into Wilkinson Bay. SOLOCO's dredge superintendent testified the dredge went off Wilkinson Canal at a 90 degree angle, headed east toward the bay, and made a couple of turns to skirt the edge of ponds (except one pond which was cut through). SOLOCO used a 4 cubic yard dredge which made a 45 foot path along the left side, turned around, then cut the additional width on the way back. The spoil was placed on the left side going toward the bay and on the right on the way back. The dredging ended in June, 1978, and the canal was kept open for months during the drilling operations.

The well was dry, so McDermott was hired to plug the western and eastern ends of the canal. Unlike SOLOCO, McDermott used a full-sized dredge. The spoil bank was backfilled. McDermott's dredge captain testified the dams were placed two feet above the marsh level. There was considerable testimony by experts, plaintiff and defendant, that the dams had washed away and could be crossed.

II

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Butler v. Baber
514 So. 2d 448 (Supreme Court of Louisiana, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
512 So. 2d 653, Counsel Stack Legal Research, https://law.counselstack.com/opinion/butler-v-baber-lactapp-1987.