Butler Bros.-Hoff Co. v. Virginian Railway Co.

73 S.E. 441, 113 Va. 28, 1912 Va. LEXIS 5
Supreme Court of Virginia·Decided January 18, 1912·Published·Cited by 4 cases

Opinion

Buchanan, J.,

delivered the opinion of the court.

The principle controversy in this case is as to the amount of compensation which the appellant is entitled to receive for making a cut in the construction of the appellee’s line of road, under a, contract entered into between the appellant contractor and the railway company on the 9th of December, 1905, for the construction of about six and one-half miles of the latter’s roadbed. Upon that section of the road there is a cut known as “Terryville Cut.” It is about three thousand feet long and some eighty feet deep at. its summit. There is no material difference between the parties as to the number of yards of earth and stone removed in making the cut, but the principal controversy is over the classification oí the material removed.

[30]*30The contract or agreement between the parties is long, covering more than twenty pages of the printed record, and containing thirty-four sections.

Section 23 provides what compensation the contractor is to receive for its work, and, so far as is material to the work in the out, is as follows:

“The contractor agrees to receive as full compensation for all material used and labor performed in the work, and for the completing the same in all respects according to the aforesaid mentioned plans and specifications, and the requirements of the chief engineer under them, the prices enumerated below * * *
“Classified Excavation.
Earth, per cu. yard............................27 (cents)
Loose Rock, per cu. yard......................40 (cents)
Solid Rock, per cu. yard.......................85 (cents)
Excavation in Water, per cu. yard.............$3.00
# ifc ❖ #

In the general specifications for grading and masonry, which are expressly made a part of the agreement between the parties, all “Excavation” is designated as “classified” or “unclassified,” and what is meant by the terms “earth,” “loose rock,” “solid rock, ” and “excavation in water, ” is defined or divided as follows:

“(a) Earth includes clay, sand, gravel, loam, decomposed rock and slate, stones and boulders containing less than one (1) cubic foot, and all other materials, excepting those described below.
“(b) Loose Rock includes all boulders and detached masses of rock measuring over one (1) cubic foot in bulk and less than one (1) cubic yard; also all slate, shale, soft friable sand-stone and soap-stone, and other rock, which, in the judgment' of the engineer, may be removed without continuous blasting, although blasting may occasionally be resorted to.
“ (c) Solid Rock will include all rock found in ledges, or masses of more than one (1) cubic yard, which, in the judgment of the engineer, can only be removed by blasting. In rock excavations the “bottom” must in all cases be taken truly down to sub-grade; and, when so ordered by the engineer, ditches must be formed at foot of slopes.
[31]*31“ (d) Excavation in Water will apply to foundation pits under water, which, through no fault of the contractor, cannot, in the opinion of the engineer, be ditched or drained, but require pumping, and the deepening of channels in running water; it must cover all classes of material and must include drainage, bailing, pumping, and all materials and labor connected with such excavations; also the necessary benching and dressing of rock in foundations.
“Unclassified Excavation includes all classes of material, of every nature whatsoever, with the sole exception of ‘Excavation in Water, ’ as described above. ”

The contention of the appellant is that the excavation in “ Terry-ville Cut,” or a large portion of it, was “excavation in water,” as defined in the contract, and that it was entitled to pay therefor as such. The railway company insists that under the contract the work in “Terryville Cut” was not, nor was any part of it, “excavation in water” under the contract, and that, if it were, the appellant has waived and is estopped from setting up such claim.

The first question, therefore, to be considered is, what is meant by “excavation in water,” as used in the agreement and as defined in the specifications for grading.

The term “excavation in water,” as is clear from the language quoted above, does not apply to all excavation in water, but only to two kinds—viz.: (1st) “to foundation pits under water,” under certain circumstances, and (2d) to “the deepening of channels in running water.” It is not claimed by the appellant that its work in the cut was work in a foundation pit, but its contention is that it was work done in deepening a channel in running water.

That term, or the words thereof, if used in their primary or ordinary and popular sense, refer, as it seems to us, to work in making deeper the bed of a running stream, such as a creek or river, rather than to work in water in the construction of a railroad cut, which collects therein from seepage, wet weather, springs, or otherwise, during the progress of the work in opening or making the cut. At least it is not clear that the term was intended to include the latter kind of work. There is nothing in the agreement to show that the term or words were used in any other than in their ordinary and popular sense. This being so, viewing the language used in the most favorable light that it can be considered for the [32]*32appellant, the most that can be said is that the meaning of the term is not clear, but doubtful. ■

In construing a contract where there is a doubt as to its proper meaning, the court may look to the construction which the parties themselves have placed upon it in its execution in order to ascertain its meaning.

It appears that the work on the cut was commenced in April, 1906, and was completed in September, 1907. At no time during that whole period was the work done in the cut, or any part of it, treated or classified as “excavation in water” by the railway company or its engineers; nor was any claim made by the appellant to the railway company during that period that any part of the work in the cut was “excavation in water,” or that there was any error or mistake made in the monthly estimates (some seventeen or eighteen in number) in not so classifying any part of the work done in the cut.

By section 30 of the agreement between the parties it is provided: “So long as the work herein contracted for is prosecuted agreeably to the provisions of this contract, and with such progress as may be satisfactory to the chief engineer, the said chief engineer will, on or about the first day of every month, make an approximate estimate of the proportionate value of the work done thereon, and of acceptable material furnished and delivered upon the company's property at the site of the work, up to and inclusive of the last day of the previous month, based upon the price or prices herein-before specified; and the amount of said estimate certified to as being correct and in accordance with the terms of this contract, after deducting ten (10) per cent, and all previous payments, shall be due and payable to the contractor at the office of the treasurer of the company on or about the 20th day of the current month. ”

Free access — add to your briefcase to read the full text and ask questions with AI

Butler Bros.-Hoff Co. v. Virginian Railway Co., 73 S.E. 441, 113 Va. 28, 1912 Va. LEXIS 5 (Va. 1912).

73 S.E. 441 (Butler Bros.-Hoff Co. v. Virginian Railway Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Town of Ashland v. Newman
175 S.E. 724 (Supreme Court of Virginia, 1934)
People's Bank v. People's National Bank
139 S.E. 325 (Supreme Court of Virginia, 1927)
Chesapeake & Potomac Telephone Co. v. Wythe Mutual Telephone Co.
129 S.E. 389 (Supreme Court of Virginia, 1925)
Commonwealth ex rel. City of Portsmouth v. Portsmouth Gas Co.
112 S.E. 792 (Supreme Court of Virginia, 1922)