Busch v. Dyno Nobel, Inc.

40 F. App'x 947
CourtCourt of Appeals for the Sixth Circuit
DecidedJuly 18, 2002
DocketNo. 00-1808
StatusPublished
Cited by10 cases

This text of 40 F. App'x 947 (Busch v. Dyno Nobel, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Busch v. Dyno Nobel, Inc., 40 F. App'x 947 (6th Cir. 2002).

Opinion

DAUGHTREY, Circuit Judge.

This appeal arose from a series of dealings between plaintiff Noble Metal Merchants, Inc. (Noble Metal), an antifreeze recycling company, and defendant Dyno Nobel, Inc. (Dyno), an explosives manufacturer. The two parties entered into a joint venture to produce ethylene glycol, including the design and development of a plant to provide an economical manufacturing process. In the process of negotiation, the parties signed a letter of intent that set out the basic plan for the project but that expressly contemplated a later contract. However, a formal contract was never executed. After the new plant was built by the plaintiff to the defendant’s specifications, significant technical problems in the manufacturing process developed. The defendant then refused to continue working with the plaintiff, and the plaintiff filed this action, claiming breach of contract.

The case went to trial and the district court granted judgment as a matter of law to the defendant after the presentation of the plaintiffs case, finding that the original letter of intent was an unenforceable “agreement to agree” for the sale of goods. The plaintiff appeals that ruling, along with a variety of pretrial determinations made by the district court.

After examining the letter of intent and the additional evidence presented at trial, we conclude that the district court erred in granting judgment to the defendant as a [950]*950matter of law. The facts presented at trial were sufficient to create several genuine issues of fact for the jury — issues that might reasonably have led to recovery for the plaintiff. Additionally, we conclude that the trial court violated the mandate of Daubert by denying the plaintiff a hearing before excluding the testimony of its damages expert. See Daubert v. Merrell Dow Pharmaceuticals, 509 U.S. 579, 588, 113 S.Ct. 2786, 125 L.Ed.2d 469 (1993). Accordingly, we reverse the judgment of the district court and remand the case for further proceedings.

FACTUAL AND PROCEDURAL HISTORY

In 1993, when the dealings between the plaintiff and defendant began, Noble Metal was a small company located in Wixom, Michigan, in the business of selling scrap metal and recycling antifreeze. David Fincher, the Vice President of Special Projects for Dyno, contacted a representative of the Noble Metal, expressing an interest in purchasing ethylene glycol, a component of antifreeze. After a series of discussions, Fincher requested that Roger Busch, the owner and president of Noble Metal, talk to one of the defendant’s engineer.

Busch was soon thereafter contacted by Pierre Smith, a Dyno process engineer. Smith explained to Busch that the defendant was interested in distilling the plaintiffs recycled antifreeze in order to obtain ethylene glycol sufficiently pure to use for explosives manufacturing. Smith told Busch that Dyno wanted to purchase approximately five million pounds of ethylene glycol. Busch expressed excitement at the possibility of serving as the defendant’s source, but also voiced concern that producing such a large order would prevent him from adequately servicing his existing customers.

After receiving information about the plaintiffs plant, Smith created a preliminary design of a plant capable of producing ethylene glycol pure enough to meet the defendant’s needs. Smith predicted that the use of this process to manufacture ethylene glycol at the plaintiffs new facility could save the defendant up to ten cents per pound of ethylene glycol. Despite projected savings, several Dyno employees internally expressed opposition to the project. Walt Elston, the defendant’s executive vice president, briefly halted the project, but it was soon thereafter reinstated by Fincher.

Smith informed Busch that in order to make Noble Metals’s plant capable of producing the necessary purity he would need to install a 50-horsepower boiler. In March 1994, Busch was provided the opportunity to purchase an even larger capacity boiler at a discounted rate. He informed Smith of the boiler purchase, after which Smith altered the plant design to allow a larger output of refined ethylene glycol for the defendant’s use.

In June 1994, Smith completed the plant design. He was told by his supervisor, A1 Osborne, to hold off on plant construction until the project was approved by Dyno executives. On August 30, 1994, Smith presented the designs to Elston, Fincher, Osborne, and Gary Lindsay, Dyno’s chief executive officer. Elston and Fincher debated the viability of the project and, at the conclusion of the discussion, Lindsay “basically sided with Mr. Fincher” and directed Smith to go forward with the plant project.

Shortly thereafter, Fincher went to Wix-om to tour the plaintiffs plant. After-wards, he met with Busch, Rosen, and Frank Wolicki, the plaintiffs accountant, to discuss the viability of an agreement. Busch and Rosen testified that the parties [951]*951established the terms of their future relationship during that meeting. First, the plaintiff would supply its existing technology and front the cost of building a plant appropriate for the manufacture of ethylene glycol. In braiding the plant, the plaintiff would receive technical assistance, employee training, and some of the necessary equipment currently in the defendant’s possession. After the plant was complete, the plaintiff would provide ethylene glycol to the defendant, recovering the price of plant construction by charging a premium equal to the cost of plant production divided by the number of pounds to be provided on the ethylene glycol purchases in the first five years. In each of the first five years, the plaintiff would supply the defendant with ten million pounds of ethylene glycol, reserving the remainder of the plant’s output for existing customers. Rosen testified that the defendant “wanted as much as we could make, but we agreed to ten million.” The negotiated purchase price was plaintiffs costs plus 15 percent. After five years, the plant would belong entirely to the plaintiff, and the parties would decide each year whether to continue the relationship.

Busch told Fincher that in order to secure a loan for plant construction, he would need their agreement in writing. Fincher offered to have Dyno’s legal department prepare an appropriate contract. Busch suggested instead that the document be entitled a “letter of intent.” Busch testified that he preferred this label because he thought it would be a “two- or three-page document that kept everybody focused on what everybody was supposed to do.”

Busch received a draft of the letter of intent from the defendant in September. After reading it, he asked Fincher about the meaning of several provisions, including the wording of the introductory paragraph. Busch also suggested changes, but he did not consult a lawyer. Fincher sent Busch a signed final version of the letter of intent on September 26, 1994. On September 28, 1994, Busch sent Fincher two facsimile transmissions. Each fax included a cover sheet and a spreadsheet outlining the costs of producing ethylene glycol for the first two years. Busch testified that he sent the faxes to “confirm .. [his] understanding of how costs would be calculated.” Fincher did not respond to the faxes. On September 30, 1994, Busch signed the September 26th letter of intent on behalf of the plaintiff and faxed it to Fincher.

The language of the letter of intent signed by both parties contemplates a later document:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Alcala v. Verbruggen Palletizing Solutions, Inc.
531 P.3d 1085 (Idaho Supreme Court, 2023)
Julian Bivins v. Keith B. Stein
Eleventh Circuit, 2018
Gillis v. Wells Fargo Bank, N.A.
875 F. Supp. 2d 728 (E.D. Michigan, 2012)
In Re Plastech Engineered Products, Inc.
397 B.R. 828 (E.D. Michigan, 2008)
Johnson Controls, Inc. v. TRW Vehicle Safety Systems, Inc.
491 F. Supp. 2d 707 (E.D. Michigan, 2007)
Ford Motor Co. v. Kahne
379 F. Supp. 2d 857 (E.D. Michigan, 2005)
Mécanique C.N.C., Inc. v. Durr Environmental, Inc.
304 F. Supp. 2d 971 (S.D. Ohio, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
40 F. App'x 947, Counsel Stack Legal Research, https://law.counselstack.com/opinion/busch-v-dyno-nobel-inc-ca6-2002.