Burton v. Weeks Marine Inc

CourtDistrict Court, W.D. Louisiana
DecidedDecember 12, 2023
Docket2:22-cv-01111
StatusUnknown

This text of Burton v. Weeks Marine Inc (Burton v. Weeks Marine Inc) is published on Counsel Stack Legal Research, covering District Court, W.D. Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Burton v. Weeks Marine Inc, (W.D. La. 2023).

Opinion

UNITED STATES DISTRICT COURT WESTERN DISTRICT OF LOUISIANA LAKE CHARLES DIVISION

ANTHONY BURTON CASE NO. 2:22-CV-01111

VERSUS JUDGE JAMES D. CAIN, JR.

WEEKS MARINE, INC. MAGISTRATE JUDGE KAY

MEMORANDUM RULING

Before the Court is a Motion for Summary Judgment [Doc. 15] filed by the Defendant, Weeks Marine, Inc. (“Weeks”), under Federal Rule of Civil Procedure 56. Plaintiff, Anthony Burton (“Burton”), opposes the motion. Doc. 19. I. BACKGROUND

This lawsuit arises from injuries suffered by Burton while employed as a rigger/pile driver working on a crane barge owned by Weeks. Burton filed suit against Weeks, alleging a claim of negligence under the Jones Act, 46 U.S.C. § 30104, and general maritime law. Doc. 1. Therein, Burton seeks recoupment of maintenance and cure as well as punitive damages on the grounds that Weeks has willfully and wantonly failed to pay sufficient maintenance and cure despite notice of the severity of his injuries and his continued treatment.1 Id. at ¶ 13. Burton also seeks damages for physical pain, mental

1 Plaintiff also sought punitive damages on the grounds that Weeks’s conduct was “grossly negligent and reckless” and “because of the vessel’s unseaworthiness following the United States Supreme Court’s ruling in Atlantic Sounding.” Doc. 1 at ¶ 14. This Court previously dismissed all claims for punitive damages arising from negligence and unseaworthiness. Doc. 8. anguish, disfigurement, loss of enjoyment of life, loss of earnings (past and future), and future medical expenses. Id. at ¶ 12.

Burton began his employment with Weeks as a rigger/pile driver on February 11, 2019. Doc. 15-3 at ¶ 1. From February 2019 through July 20, 2019, Burton worked at a Weeks facility in Portland, Texas, reclaiming land in a marshy area. Id. at ¶ 2. While there, Burton lived and worked onshore. Id. Burton was then transferred to a Weeks marine facility in Bourg, Louisiana, where he worked preparing barges to ship to other jobsites. Doc. 15-6, Burton Dep. at 77-78, 80-81. During that time Burton lived onshore at a local

hotel. Id. at 79. On September 16, 2019, Burton arrived to work in Cameron Parish, Louisiana, at the Weeks Venture Global job site, which was accessible by vehicle. Doc. 15-3 at ¶¶ 6-7. The scope of the work for the Venture Global project was to build a storm surge wall around a LNG facility. Id. at ¶ 7. There were six or eight crews, with four to six people in

each crew, all working on various parts of the surge wall project on land, spread out over a 400-acre area. Id. at ¶ 9. Burton’s initial role at the Venture Global job site was taking equipment off trucks and driving piles into the marsh. Id. at ¶ 12. On November 21, 2019, two months after Burton arrived at the site, the WEEKS 571 crane barge arrived. Id. at ¶ 11. Burton did not travel or arrive with the barge, as the

barge was unmanned during transportation. Id. at ¶ 13. The barge did not have its own self-propulsion. Id. at ¶ 14. The barge was moved from job to job by tugs with their own crews. Id. at ¶ 15. None of the construction crew slept on the barge, as the barge had no accommodations. Id. at ¶ 18. The crane barge was “spudded in” adjacent to the marine offload facility. Id. at ¶ 20. When spudded in place, the barge was less than 50 feet away from the dock, as the gangways were only a maximum of 50 feet long. Doc. 15-8, Wurster

Dep. at 63. Burton would sometimes accompany the WEEKS 571 as it was repositioned along the edge of the land at the marine offload facility, moving at most two to three hundred feet and never leaving the facility. Doc. 15-3. at ¶ 29. Burton’s assigned crew was using the crane as a stationary work platform at the Venture Global job site. Id. at ¶ 21. Burton worked on the WEEKS 571 while it was moored to the shore, connected by a gangplank, at dock level. Id. at ¶ 22. As a rigger, Burton

engaged in the work of transferring equipment from barges on the water onto the land. Id. at ¶ 23. While working on the stationary, spudded barge, moored at the marine offload facility, Burton’s crew loaded and unloaded materials from other barges that arrived at the offload facility, and would transfer the materials onto trucks on land at the site. Id. at ¶ 24. The WEEKS 571 was used to unload two types of materials from other material barges:

pipe piles and sheet piles. Id. at ¶ 25. The crane on the WEEKS 571 had a maximum radius of 170 feet and was moored directly adjacent to the marine offload facility so that trucks could approach close enough for the crane to reach. Id. at ¶ 28. Burton was injured on April 26, 2020, while working to extend the boom of the crane to add an additional section. Doc. 15-8, Wurster Dep. at 25, 43. As part of this

process, Burton and another crew member utilized a pry bar to move a spool, which was receiving wire cabling off the crane, that had become stuck in its frame. Id. at 33. Burton was injured when the tension on the pry bar gave way, and his fingers were caught between the spool and the pry bar. Doc. 15-6, Burton Dep. at 135. Weeks moves for summary judgment dismissal of Burton’s claims under Federal Rule of Civil Procedure 56, arguing that Burton is a longshoreman, not a seaman under the

Jones Act, and therefore, cannot avail himself of the available remedies and protections afforded by the Jones Act. Doc. 15-1. Burton opposes the motion, arguing that he qualifies as a seaman. Doc. 19-1. II. LAW AND ANALYSIS

A. Summary Judgment Standard Under Rule 56(a), “[t]he court shall grant summary judgment if the movant shows that there is no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law.” The moving party is initially responsible for identifying portions of pleadings and discovery that show the lack of a genuine issue of material fact. Tubacex, Inc. v. M/V Risan, 45 F.3d 951, 954 (5th Cir. 1995). He may meet his burden by pointing out “the absence of evidence supporting the nonmoving party's case.” Malacara v. Garber, 353 F.3d 393, 404 (5th Cir. 2003). The non-moving party is then required to go beyond the pleadings and show that there is a genuine issue of material fact for trial.

Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248 (1986). To this end, he must submit “significant probative evidence” in support of his claim. State Farm Life Ins. Co. v. Gutterman, 896 F.2d 116, 118 (5th Cir. 1990). “If the evidence is merely colorable, or is not significantly probative, summary judgment may be granted.” Anderson, 477 U.S. at 249 (citations omitted). A court may not make credibility determinations or weigh the evidence in ruling on a motion for summary judgment. Reeves v. Sanderson Plumbing Prods., Inc., 530 U.S.

133, 150 (2000). The court is also required to view all evidence in the light most favorable to the non-moving party and draw all reasonable inferences in that party's favor. Clift v. Clift, 210 F.3d 268, 270 (5th Cir. 2000). Under this standard, a genuine issue of material fact exists if a reasonable trier of fact could render a verdict for the nonmoving party. Brumfield v. Hollins, 551 F.3d 322, 326 (5th Cir. 2008).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tubacex, Inc. v. M/V Risan
45 F.3d 951 (Fifth Circuit, 1995)
Roberts v. Cardinal Services, Inc.
266 F.3d 368 (Fifth Circuit, 2001)
Malacara v. Garber
353 F.3d 393 (Fifth Circuit, 2003)
Brumfield v. Hollins
551 F.3d 322 (Fifth Circuit, 2008)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Chandris, Inc. v. Latsis
515 U.S. 347 (Supreme Court, 1995)
Harbor Tug & Barge Co. v. Papai
520 U.S. 548 (Supreme Court, 1997)
Stewart v. Dutra Construction Co.
543 U.S. 481 (Supreme Court, 2005)
Michael James Ardoin v. J. Ray McDermott & Co.
641 F.2d 277 (Fifth Circuit, 1981)
Lozman v. City of Riviera Beach
133 S. Ct. 735 (Supreme Court, 2013)
Reeves v. Sanderson Plumbing Products, Inc.
530 U.S. 133 (Supreme Court, 2000)
In Re of Two-J Ranch, Inc.
534 F. Supp. 2d 671 (W.D. Louisiana, 2008)
Larry Naquin, Sr. v. Elevating Boats, L.L.C.
744 F.3d 927 (Fifth Circuit, 2014)
Sanchez v. Smart Fabricators of TX
997 F.3d 564 (Fifth Circuit, 2021)
Endeavor Marine, Inc. v. Crane Operators, Inc.
234 F.3d 287 (Fifth Circuit, 2000)
Starks v. Advantage Staffing, LLC
202 F. Supp. 3d 607 (E.D. Louisiana, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
Burton v. Weeks Marine Inc, Counsel Stack Legal Research, https://law.counselstack.com/opinion/burton-v-weeks-marine-inc-lawd-2023.