Burkholder v. Wykle

268 F. Supp. 2d 835, 2002 U.S. Dist. LEXIS 4850, 2002 WL 32123914
CourtDistrict Court, N.D. Ohio
DecidedFebruary 22, 2002
Docket1:01CV1165
StatusPublished
Cited by3 cases

This text of 268 F. Supp. 2d 835 (Burkholder v. Wykle) is published on Counsel Stack Legal Research, covering District Court, N.D. Ohio primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Burkholder v. Wykle, 268 F. Supp. 2d 835, 2002 U.S. Dist. LEXIS 4850, 2002 WL 32123914 (N.D. Ohio 2002).

Opinion

MEMORANDUM OF OPINION

MANOS, District Judge.

On May 14, 2001, Donald and Marilyn Burkholder, plaintiffs, initiated the above-captioned case against Kenneth R. Wykle, 1 Administrator of the Federal Highway Administration (“FHWA”), and Gordon Proctor, Director of the Ohio Department of Transportation (“ODOT”), defendants. Specifically, the plaintiffs allege numerous violations of the National Environmental Policy Act, 42 U.S.C. § 4321, et seq. (“NEPA”), the National Federal Aid Highway Act, 23 U.S.C. § 100, et seq. (“Highway Act”), and the Administrative Procedure Act, 5 U.S.C. § 701, et seq. (“APA”), and seek to enjoin the state and federal agencies from completing the expansion and relocation of U.S. Route 30 until such time as an Environmental Impact Statement (“EIS”) can be completed.

As the claims arise under the above-stated laws of the United States, jurisdiction is properly predicated upon 28 U.S.C. § 1331.

On November 2, 2001, both parties filed cross motions for summary judgment (Docket Nos. 21 and 23). 2 On August 27, 2001, the administrative record was filed with this Court (Docket No. 13) and, on October 25, 2001, November 5, 2001, and December 10, 2001, the parties supplemented the record (Docket Nos. 19 and 24) and identified specific relevant portions therein (Docket No. 38). 3 The Court finds that the issues have been fully briefed by the parties and that an evidentiary hearing on the matter is unnecessary.

For the following reasons, the plaintiffs’ motion for summary judgment is DENIED and the defendants’ motion for summary judgment is GRANTED.

I. FACTS

The facts are largely undisputed. U.S. Route 30 (“US 30”) is part of the Lincoln *838 Highway, the first transcontinental highway in the United States, and extends from Atlantic City, New Jersey to Astoria, Oregon (EA p. 1; AR004862). In Ohio, U.S. 30 spans 242.1 miles, the entire width of the state (Id.). At the present time, approximately 54 percent of the highway in Ohio exists as a four-lane, divided highway, while the remaining 46 percent, divided into seven discrete segments, consists of a “2-lane or multi-lane undivided rural highway.” (Id.). The Ohio Department of Transportation has identified U.S. 30 as a “Macro Corridor” and desires to upgrade the remaining seven segments so that a four-lane, divided highway will then span the entire state (Id.; AR004859; Access Ohio).

The instant controversy concerns the upgrade of one such segment and the proposed relocation of approximately 16.31 miles of the highway between the cities of Bueyrus and Ontario, Ohio (“the project area”). At present, the road is a two lane, undivided highway, but is abutted, at both its eastern and western termini, by modern four-lane, limited access freeways. 4 ODOT has examined the possibility of improving this section of road, with varying degrees of interest, since the 1970s when the roads on either end of the project area were improved. (Plaintiffs’ Motion for Summary Judgment, p. 24; EA p. i). By the 1990s, however, ODOT had determined that the existing two-lane highway was insufficient to accommodate present and future traffic, and began to consider the instant upgrade in earnest. (AR013019). 5

On June 7, 1993, the state retained the firm of McCoy/Fok & Associates, Inc. (“McCoy/Fok”) to prepare a preliminary study of the project and its associated environmental, economic, social, and cultural impacts. (AR003678). 6 McCoy/Fok then began the task of reviewing the relevant literature (AR004137), coordinating their efforts with those of other governmental agencies (EA p. 62; EA Table 16; EA Appendix E), and conducting appropriate ecological investigation. (AR001558).

On November 4, 1993 and January 26, 1995, ODOT conducted public hearings wherein public input was sought and comments were recorded. (AR003634; AR003664; AR017221; AR018511). While the information presented at the 1993 meeting was more generalized, at the 1995 meeting, ODOT informed the residents that four alternative routes had been developed for U.S. 30, and that a “no build” alternative was being considered as well. (AR003634). On December 10, 1996, purportedly based upon “environmental issues, comments received from citizens attending the public meeting and responses received after the meeting”, ODOT issued a press release, which indicated that a “preferred route” had been selected. (AR012636). On April 22, 1999, ODOT convened a third public meeting to discuss this decision. (AR012457).

*839 After seven years of preparation, on November 27, 2000, ODOT issued an Environmental Assessment, prepared by MeCoy/Fok, and submitted the document to FHWA, the project’s financier 7 for the return of either a Finding of No Significant Impact, which would permit the project to go forward without further environmental review, or instructions to prepare a more detañed Environmental Impact Statement. 8 On January 25, 2001, the environmental document was presented to the public at a formal hearing and comments were again sought regarding the adequacy of the document, the process by which it had been prepared, and the ultimate conclusion that no significant environmental impacts were created by adopting the preferred route. (AR024150).

On April 12, 2001, based on the EA, the FHWA authorized the construction of the 16.31 müe relocation of U.S. 30 by issuing a Finding of No Significant Impact, and obviated the preparation of an Environmental Impact Statement (AR024239).

Unfortunately, the identified “preferred alternative” discussed above passes through property presently occupied by the plaintiffs’ home. Not surprisingly, the plaintiffs herein object to both this determination and the process by which it was reached.

II. STANDARD OF REVIEW

When examining the propriety of a federal agency’s action upon a motion for summary judgment, a reviewing Court must base its decision upon both the summary judgment standard of review, and the analysis required by the Administrative Procedures Act, 5 U.S.C. § 701, et seq. This being so, the Court wül briefly examine both standards.

A. SummaRY Judgment

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
268 F. Supp. 2d 835, 2002 U.S. Dist. LEXIS 4850, 2002 WL 32123914, Counsel Stack Legal Research, https://law.counselstack.com/opinion/burkholder-v-wykle-ohnd-2002.