Burke v. Union Pacific Resources Co.

138 S.W.3d 46, 2004 Tex. App. LEXIS 5061, 2004 WL 813289
CourtCourt of Appeals of Texas
DecidedJune 9, 2004
Docket06-02-00183-CV
StatusPublished
Cited by60 cases

This text of 138 S.W.3d 46 (Burke v. Union Pacific Resources Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Burke v. Union Pacific Resources Co., 138 S.W.3d 46, 2004 Tex. App. LEXIS 5061, 2004 WL 813289 (Tex. Ct. App. 2004).

Opinions

OPINION

Opinion by

Justice CARTER.

In the fall of 1997, Union Pacific Resources Company (UPRC) conducted a seismic survey consisting of most of Rusk County. After the survey had been con[54]*54ducted, Russell and Lori Burke noticed their recently drilled water well was producing an excessive amount of sand. The sand caused decreased weight gain on their feedlot cattle and caused over 1,000 of the cattle to die. After they were forced into bankruptcy, Russell and Lori Burke and Bob Anderson, the bankruptcy trustee (herein collectively “the Burkes”), sued UPRC and Palestine Water Well Service, Inc. (PWW). After a jury trial, the trial court rendered judgment against UPRC, awarding the Burkes $1.5 million and awarding PWW $200,000.00. The Burkes appeal the judgment of the trial court, and UPRC cross-appeals. We render a take-nothing judgment concerning PWW’s tortious interference claim and suggest a remittitur concerning the Burkes’ breach of contract claim.

The Burkes raise the following three issues on appeal:

1) Where the evidence shows that the water well was eventually repaired and some water service restored, was it error for the jury to find that the injury to the Burkes was permanent?

2) Where the expert only discovered that the seismic blasting damaged the well in December 2001, was it error for the jury to find that the Burkes should have discovered it on January 1,1998?

3) Where there was uncontroverted evidence concerning attorney’s fees, was it error for the jury to find that the Burkes were not entitled to recover attorney’s fees?

Union Pacific Resources Company, n/k/a Anadarko E & P Company, presents eleven issues on appeal. UPRC’s issues are as follows:

1)Did the Burkes prove their right to recover from UPRC on a breach of contract theory based on the testing permit (PX-17)?

2) Did the Burkes prove their right to recover from UPRC as purported third-party beneficiaries of the indemnity contract (PX-99) between UPRC and Schlum-berger?

3) Is there an adequate pleading by the Burkes to support recovery of consequential damages?

4) Is there sufficient evidence of the Burkes’ direct damages?

5) Is there sufficient evidence to support a total damage award of $1.5 million?

6) Is UPRC entitled to a credit for the Schlumberger settlement?

7) Does the two-year statute of limitations bar PWW’s claims for tortious interference?

8) Does the lack of a pleading prevent PWW from recovering for tortious interference with prospective relations?

9) Is there sufficient evidence to support either of PWW’s claims for tortious interference?

10) May PWW recover attorney’s fees or expert witness fees as tort damages?

11) Is there sufficient evidence of malice by UPRC toward PWW?

Facts

In the fall of 1997, the Burkes decided to open their own feedlot cattle preconditioning operation. Russell Burke was familiar with the business, having worked with his father for many years in a similar operation. Dr. Christopher Grotegut testified that he was familiar with Russell Burke and his father and that they had been in the business a long time. The Burkes purchased ninety-four acres in Laneville, Texas, and began to develop a preconditioning feedlot operation.

Most cattle ranchers in this region of Texas have small operations. Due to their [55]*55small size, it is not always profitable to precondition calves. A feedlot cattle preconditioning operation obtains calves from numerous operations and provides vaccinations and other care in a low stress environment until the calves’ immune systems are strong enough to fight diseases and stress on their own. It is essential to a preconditioning operation that quality water be made available to nurture the calves. Poor hydration will cause the cattle to have decreased appetites and result in reduced weight gain. Proper hydration will decrease the frequency and effect of diseases. Poor hydration will, however, prevent drugs from treating diseases as well as they should. The Burkes’ operation involved cattle that they owned outright, cattle that they partnered with others, and cattle that they fed for customers.

In order to obtain an adequate water supply, the Burkes contracted with PWW to drill a water irrigation well. PWW and the Burkes selected a location for the well based on PWW’s knowledge of the Lane-ville area and its sand formations. PWW started drilling the well on November 17, 1997, and completed the well on November 21, 1997. While PWW was in the process of drilling the well, it noticed some seismic testing operations approaching the area.

On September 22,1997, the Burkes gave permission for seismic testing of their ninety-four acres. Seismic testing is a method of exploring for hydrocarbons under the ground. Schlumberger Technology Corporation (Schlumberger) performed the seismic testing on behalf of UPRC, which involved thirty-six square miles and lasted several months. Seismic testing involves drilling a shot hole, placing charges in the hole, and collecting readings of the waves created by the detonation of the explosives.

Due to his previous oil field experience, Jere Pritchett, an employee of PWW, became concerned about the effect of the seismic testing on the well. Pritchett stopped the drilling of the well and informed the seismic crew about the well. Some of the seismic crew came to the well site and discussed the situation with Pritchett. The Burkes did not want to stop drilling the well because they had to get the feedlot operating in order to make payments on their obligations. Schlum-berger agreed to move their explosive charges away from the well so as not to damage it.

Schlumberger obtained an agreement from UPRC to pay for any damage to the well caused by the seismic testing. Bennie Bates, the field project manager, signed the agreement on behalf of UPRC. John Gibson, the project manager, testified he authorized Bates to execute the agreement.

When PWW finished the well, it produced clean water without any sand. The Burkes did not install a pump until January 1998. After the well had been drilled, but before the pump was installed, Schlumberger performed the blasting. After the blasting, the Burkes and Pritchett noticed the well pad had been “uplifted” three to four inches above the ground. When the pump was activated, there was sand in the water. The well eventually began producing parts of the gravel pack intended to filter out the sand. This indicated that the gravel pack and screen had been broken. The sand production became so bad that the 900-gallon holding tank and automatic watering troughs would fill with sand. Sometimes the watering troughs needed to be cleaned out fifteen to twenty times a day. The Burkes installed two sand separators in an attempt to filter out the sand. Initially, Burke and PWW were unable to determine the cause of the problem.

[56]*56Eventually, the parties discovered that the seismic crews had detonated charges closer to the well than discussed earlier and had increased the magnitude of the charges. Three of the charges had been detonated in violation of the safe distance guidelines that UPRC had developed for another project.

The cattle being raised by the Burkes had abnormally high rates of pneumonia and mortality. The cattle gained less weight than expected.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Walmart, Inc. v. Fintiv, Inc.
Court of Appeals of Texas, 2021
MCMC Auto Ltd. v. Sidecars, Inc.
Court of Appeals of Texas, 2018
Nelson v. Vernco Constr., Inc.
566 S.W.3d 716 (Court of Appeals of Texas, 2018)
Freeman v. Harleton Oil & Gas, Inc.
528 S.W.3d 708 (Court of Appeals of Texas, 2017)
Elness Swenson Graham Architects, Inc. v. RLJ II-C Austin Air, LP
520 S.W.3d 145 (Court of Appeals of Texas, 2017)
Huff Energy Fund, L.P. v. Longview Energy Co.
482 S.W.3d 184 (Court of Appeals of Texas, 2015)
Aaron Thompson v. State
Court of Appeals of Texas, 2014
Danny Ray Cline v. Guaranty Bond Bank
404 S.W.3d 139 (Court of Appeals of Texas, 2013)
DeGroot v. DeGroot
369 S.W.3d 918 (Court of Appeals of Texas, 2012)
Jeffrey C. Green v. State
Court of Appeals of Texas, 2012

Cite This Page — Counsel Stack

Bluebook (online)
138 S.W.3d 46, 2004 Tex. App. LEXIS 5061, 2004 WL 813289, Counsel Stack Legal Research, https://law.counselstack.com/opinion/burke-v-union-pacific-resources-co-texapp-2004.