Bullock v. Tucker

822 S.E.2d 654, 262 N.C. App. 511
CourtCourt of Appeals of North Carolina
DecidedDecember 4, 2018
DocketCOA17-1429
StatusPublished
Cited by3 cases

This text of 822 S.E.2d 654 (Bullock v. Tucker) is published on Counsel Stack Legal Research, covering Court of Appeals of North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bullock v. Tucker, 822 S.E.2d 654, 262 N.C. App. 511 (N.C. Ct. App. 2018).

Opinion

ELMORE, Judge.

*656 *512 This action arose from the commercial lease of lakefront property at Tucker Lake in Johnston County that began 1 January 2012 and ended 31 December 2016. Lessors Trenton Glen Tucker, Allison C. Tucker, Hollie Tucker Winters, Brian Keith Winters, and Tucker Lake Recreations, Inc., as well as Sharlette Tucker, Glenwood Tucker, and Tim Richardson (collectively, "defendants"), appeal a trial court order that adopted a compulsory referee's report. In its report, the referee recommended that the lessees, Paula K. Bullock and Fynnmaster, LLC (collectively, "plaintiffs"), be awarded Rule 60(b) relief in the form of striking a provision in a 30 April 2014 order that amended the initial lease. That provision provided that "[u]pon termination of the lease, ... [p]laintiffs shall remove ... grain bin anchors" they had previously installed in Tucker Lake to support the cable system required to operate their commercial waterskiing enterprise. In its report, the referee found that defendants have thwarted plaintiffs' earnest efforts to remove the anchors since at least October 2016, and concluded that, at the time its report issued one day *513 before the lease expired, it was now impossible for plaintiffs to comply with this provision of the 30 April 2014 order. After a hearing on defendants' exception to the referee's report, the trial court adopted the report in its entirety. Defendants appeal.

On appeal, defendants contend the trial court's order adopting the referee's report should be reversed because (1) the trial court perfunctorily adopted the report without adequately reviewing the evidentiary sufficiency of the referee's findings; (2) certain findings were unsupported by the evidence and the findings did not support the conclusions; and (3) the Rule 60(b) relief recommended was improper because it (a) was premised on an erroneous conclusion that it was impossible for plaintiffs to perform the anchor-removal requirement of the 30 April 2014 order, and (b) inappropriately modified a material provision of a consent order. Defendants also contend that, even if the trial court did not reversibly err in these respects, (4) the case must be remanded for entry of a proper judgment because the trial court's order merely adopted the referee's report.

We hold that the trial court adequately reviewed defendants' exceptions to the referee's findings and did not err in adopting the report in its entirety. The challenged findings were supported by the evidence, the challenged conclusions were supported by the findings, the 30 April 2014 order amending the initial lease was not a valid consent order, and the Rule 60(b) relief recommended did not amount to an abuse of discretion. Accordingly, we affirm the trial court's order. However, we remand to the trial court with instructions to enter a judgment concordant with that adopted report.

I. Background

On 1 January 2012, plaintiffs entered into a five-year pro se commercial lease with defendants Trenton Glen Tucker, Allison C. Tucker, Hollie Tucker Winters, Brian Keith Winters, and Tucker Lake Recreations, Inc., to use a 48-acre parcel of lakefront property at Tucker Lake for plaintiffs' "operations of a water recreation operation including ... the construction and maintenance of underwater and above water cabling, docks buildings, and related facilities." Soon after, disputes concerning the parties' performances under the lease arose. Although the parties have been actively litigating since April 2012, we limit our discussion of the extensive procedural history to only that relevant to provide context and adjudicate the appeal.

On 3 April 2012, plaintiffs filed a verified complaint against defendants. Plaintiffs asserted claims of breach of contract, civil conspiracy, *514 tortious interference with contract, and unfair and deceptive trade practices ("UDTP"); sought declaratory judgments as to interpreting certain lease provisions; and sought a temporary restraining order ("TRO") and a preliminary injunction on the grounds that defendants have "frustrate[d their] efforts ... to construct a cable water skiing facility[.]" On 12 April 2012, defendants cross-moved for a TRO and preliminary injunction, seeking to enjoin plaintiffs from continuing construction. On 26 April 2012, the trial court entered a TRO that, inter alia , enjoined defendants from unreasonably interfering with plaintiffs' business *657 plans. Plaintiffs then proceeded with their plan of installing three large grain bin anchors in Tucker Lake to support the cable system required for their waterskiing enterprise.

On 4 June 2012, defendants filed their answer to the complaint, moved under Rule 12(b)(6) to dismiss plaintiffs' claims, and asserted eight affirmative defenses. Defendants also filed a third-party complaint against plaintiffs, and John Bemis, Jeff Roberts, and Jakub Pilecky (collectively, "third-party defendants"). Defendants, as third-party plaintiffs, asserted claims of breach of contract, fraud, trespass to real property, trespass to personal property, civil conspiracy, UDTP, summary ejectment, and assault. After further litigation, likely due to the number of claims and the parties' contentiousness, the trial court on 21 May 2013 entered an order appointing a compulsory referee to, inter alia , "resolve any disagreement among the parties relating to the performance of the lease agreement" and "serve until the trial of this action or until further order of the Court." Disputes about the lease and litigation continued.

In mid-January 2014, plaintiffs voluntarily dismissed six of their claims, moved for summary judgment on their three remaining claims seeking declaratory judgments on interpreting certain lease provisions, and moved for summary judgment on all of defendants' claims in their third-party complaint. After a bench trial scheduled for 21 January, the trial court permitted the parties to negotiate outside its presence to reach a resolution of their claims. After a full day of negotiation on 22 January, the parties announced in open court they had reached an agreement, which they requested the trial court adopt as a consent order. The trial court instructed the parties to draft a consent order and reconvene the next day for its entry. But after exchanging several drafts, the parties could not mutually agree to the language of the consent order.

In mid-February 2014, the parties filed cross-motions to enforce the settlement agreement they previously announced to the trial court on 22 January. After a hearing, at which both parties presented their proposed settlement agreements, the trial court entered an order on 30 April *515 2014 resolving the parties' claims and amending some provisions of the initial lease.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Culbreth v. Manning
Court of Appeals of North Carolina, 2021

Cite This Page — Counsel Stack

Bluebook (online)
822 S.E.2d 654, 262 N.C. App. 511, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bullock-v-tucker-ncctapp-2018.