BSP Division of Envirotech Corp. v. United States Environmental Protection Agency

471 F. Supp. 958
CourtDistrict Court, D. New Jersey
DecidedJune 11, 1979
DocketCiv. A. 78-2566
StatusPublished
Cited by3 cases

This text of 471 F. Supp. 958 (BSP Division of Envirotech Corp. v. United States Environmental Protection Agency) is published on Counsel Stack Legal Research, covering District Court, D. New Jersey primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
BSP Division of Envirotech Corp. v. United States Environmental Protection Agency, 471 F. Supp. 958 (D.N.J. 1979).

Opinion

OPINION

STERN, District Judge.

Plaintiff, BSP, a prospective supplier of part of an EPA-funded waste water treatment facility, brings suit under the Administrative Procedure Act, 5 U.S.C. § 701 et seq., to set aside a decision of the Environmental Protection Agency (EPA) dismissing BSP’s bid protest on procedural grounds. 1 BSP claimed in its bid protest that the contract specifications were anticompetitive because they called for equipment which was proprietary to BSP’s competitor Zimpro, Inc. 2 Rather than ruling on the merits of this claim, the EPA dismissed the bid protest as untimely and held further that BSP was estopped in its protest because it had earlier raised and then abandoned the same claim. We uphold the decision of the EPA and grant summary judgment in favor of the defendants.

The Federal Water Pollution Control Act, 33 U.S.C. § 1251 et seq. (FWPCA) provides for the cessation of ocean disposal of sewage sludge no later than December 31, 1981. 3 33 U.S.C. § 1412a(a). The Act further authorizes the EPA to award grants to any public agency to cover 75% of the cost of constructing waste treatment facilities which inter alia provide for alternative ways to dispose of sludge. 4 33 U.S.C. § 1281 et seq. On June 30, 1976, the EPA awarded the Passaic Valley Sewerage Commission (PVSC) 5 $290,841,697.00 or 75% of the total cost of constructing a secondary *960 waste water treatment facility on the Passaic River. 6

An essential part of this facility is the Thermal Sludge Conditioning System which is designed to treat sludge with heat and pressure. Pursuant to the FWPCA, see 33 U.S.C. § 1283(a), PVSC submitted specifications for this system for the EPA’s approval. The EPA expressed concern that the treatment process called for in the specifications was proprietary to Zimpro and therefore uncompetitive, and it ordered substantial revision of the specifications. (Adm.Rec. tab 2). In exchange, however, the specifications required that the supplier of the system have five years prior experiencé or, in lieu thereof, that it post an experience bond. The EPA approved the specifications on April 19, 1977. CCTW&M v. EPA, supra, at 71-74

BSP’s 1977 Protest and the CCTW&M Action

In July 1977, following the EPA’s approval of the contract specifications, BSP lodged a bid protest with PVSC, 7 arguing that the contract specifications, although revised, were still proprietary to Zimpro. Specifically, BSP argued that (1) the process contemplated by the specifications was patented by Zimpro, (2) the high-pressure pumps required by the specifications are manufactured and sold only by Zimpro, and (3) the experience requirement was drawn so that only Zimpro could qualify. (Adm.Rec. tab 4). In August 1977, BSP met with representatives of PVSC and the contract specifications were again revised. 8 Apparently, BSP was satisfied that the specifications were no longer proprietary for it immediately abandoned this claim. (Exh. P-R).

Thereafter, BSP still pressed its protest— but on other grounds. It focused solely upon the experience requirement and the bond alternative. BSP argued that only Zimpro possessed the requisite experience and that the bond alternative was so onerous that it was not in fact an alternative at all. BSP claimed that the combined effect of these requirements was to stifle competition to the benefit of Zimpro. (Exh. P-R; Adm.Rec. tab 10).

On September 2, 1977, PVSC denied BSP’s protest (Adm.Rec. tab 14), and BSP immediately sought review with the EPA. (Adm.Rec. tab 15). In the meantime, however, bids were submitted and, on September 9, 1977, PVSC opened them. Of the five bids — all of which named Zimpro as the supplier — the bid of CCTW&M was the lowest. 9 CCTW&M v. EPA, supra, at 73-74.

On December 10, 1977, the EPA issued a written decision, substantially agreeing with BSP that the experience requirement and bond alternative were anti-competitive. It ordered PVSC to revise the specifications and readvertise the contract. Id.

CCTW&M and Zimpro thereafter sought judicial review of the EPA’s decision. This Court found that the decision had a rational basis and awarded summary judgment to the EPA. See CCTW&M v. EPA, 452 F.Supp. 69 (D.N.J.1978).

The specifications were thereafter revised and bidding began anew.

BSP’s 1978 Protest and the Present Action

The revised specifications were readvertised on July 26,1978. Bids were submitted on August 30, 1978. They were as follows:

*961 PRIME CONTRACT SUPPLIER AMOUNT OF BID
Turner Construction Co. Zimpro, Inc. $79,162,000
Vicon Construction Co. Zimpro, Inc. 81,700,000
Terminal Construction Co. BSP 83,886,000

The contract was awarded to Turner Construction Co., the low bidder. (Exh. I, J).

During the pendency of the bidding, on August 22, 1978, BSP again lodged a protest with PVSC. Its protests this time were two-fold. (Adm.Rec. tab 33). First, it renewed the objection it had pressed, but then abandoned, in its 1977 protest; that the high-pressure pump called for in the specifications was proprietary to Zimpro. Second, it objected to “SP-13”, the specific warranty and bond requirements which replaced the experience bond. 10

Following PVSC’s denial of BSP’s protest, on August 28, 1978, BSP protested with the EPA. (Adm.Rec. tab 38). The Regional Administrator rendered his decision on October 5, 1978. (Exh. A). He ruled as follows.

First, with respect to BSP’s objections to the pump specifications, the Regional Administrator held that BSP was estopped by its withdrawal of this same objection during the 1977 protest:

It is . . . clear that BSP’s current protest is based upon the very same argument as that which underlay its protest of July 1, 1977 and which it withdrew in the course of pursuing its prior protest on other grounds. The [pump specification] was not changed in any way from August 1977 to August 1978. .

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
471 F. Supp. 958, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bsp-division-of-envirotech-corp-v-united-states-environmental-protection-njd-1979.