MEMORANDUM OPINION AND ORDER
SHADUR, District Judge.
S.A. Healy Company (“Healy”) has sued Metropolitan Sanitary District of Greater Chicago (“MSD”), its Purchasing Agent George Wahl (“Wahl”), United States Environmental Protection Agency (“EPA”), its Region Y Regional Administrator Valdas Adamkus (“Adamkus”) and Klein Construction Company (“Klein”) for judicial review of a February 6, 1984. determination made by Adamkus for EPA relating to an MSD construction project to be funded in principal part by the federal government. Healy, EPA and Klein (the successful bidder as a result of Adamkus’ determination) have moved for summary judgment under Fed.R.Civ.P. (“Rule”) 56. For the reasons stated in this memorandum opinion and order, Healy’s motion is denied and the Klein-EPA motions are granted.
Facts1
On May 4, 1983 MSD solicited bids on a contract for blower facilities at its Calumet Sewage Treatment Works. Healy, Klein and six others submitted bids. When the bids were opened June 7, Healy’s adjusted bid2 of $16,733,846 was the low bid with the possible exception of the following “alternate] bid” of $16,652,390 included on the last page of Klein’s bid3 *just below the signature lines:
Alt Bid Using Loutma Bid-If Acceptable
Voluntary Alternate Loutema Blowers
Contract bid price 14,000,000.—
Guaranteed max power 4 2,890
GMPC - 2500. = 390 HP
HP differential = 2,652,390.—
Contract bid price + bid adjustment 16,652,390.00
On August 23 Wahl (acting for MSD) rejected the various protests by Klein and other bidders, finding Healy’s bid “the low, responsive, responsible bid for MSD contract 77-289-2M.” It is highly significant for current purposes that in turning down the protests by two of the bidders other than Klein, Wahl specifically approved (1) the use of Lotema Corporation (“Lotema”) 5 equipment by Healy for its bid and (2) the guaranteed maximum power consumption level of 2890 horsepower at which Healy’s bid {and Klein’s alternate bid as well) specified the Lotema blowers would perform.
On September 1 Klein and the two other protesters appealed to EPA (on differing grounds) from MSD’s adverse determination. After full briefing and other written submissions, EPA’s Office of Regional Counsel issued a Report and Recommendation that was adopted by Adamkus February 6, 1984. Based on the Report and Recommendation Adamkus (acting for EPA):
[656]*656(1) affirmed MSD’s decision to dismiss the other protests but
(2) sustained Klein’s protest, designating it and not Healy the “low, responsive, responsible” bidder and returned the matter to MSD to award the contract to Klein.
This action followed.
Standard for Review
This action is brought under the judicial review section of the Administrative Procedure Act (“APA”), 5 U.S.C. § 706. MSD invites this Court to decide that its determination in Healy’s favor had a rational basis — but that would amount to an impermissible de novo review of EPA’s determination to the contrary. Instead the question for this Court is the quite different one whether EPA had a rational basis for deciding that MSD’s determination lacked a rational basis.
As our Court of Appeals said last year in Wisconsin Electric Power Co. v. Costle, 715 F.2d 323, 325 (7th Cir.1983) (quotation paraphrased to track the present case):
Our review of the [EPA] decisions is governed by the judicial review section of the APA, see 5 U.S.C. § 706.... [Therefore we can disturb the EPA’s decision only if the agency acted beyond the scope of its statutory authority, or in an arbitrary or capricious manner, or in violation of [MSD’s] procedural rights.
That decision cited to the seminal decision in Citizens To Preserve Overton Park v. Volpe, 401 U.S. 402, 415-17, 91 S.Ct. 814, 823-24, 28 L.Ed.2d 136 (1971), which made plain that in circumstances like those presented here the EPA decision is “entitled to a presumption of regularity” (id. at 415, 91 S.Ct. at 823), though it is to be subjected to a “thorough, probing, in-depth review” (id.). Under Overton Park that required review involves three steps, which in terms of this case are these:
1. . EPA must have acted within the scope of its authority.6
2. EPA’s decision must not be “arbitrary, capricious, an abuse of discretion or otherwise not in accordance with law ...” (id. at 416, 91 S.Ct. at 823). As the Court went on to say (id.) (citations omitted):
To make this finding the court must consider whether the decision was based on a consideration of the relevant factors and whether there has been a clear error of judgment ... Although this inquiry into the facts is to be searching and careful, the ultimate standard of review is a narrow one. The court is not empowered to substitute its judgment for that of the agency.
3. EPA must have followed the necessary procedural requirements.
This opinion will not conform to that sequence, dealing instead with the last Overton Park inquiry first. It does so because Healy’s argument in that respect— that Klein’s protest to EPA was not timely — is claimed to be jurisdictional. Were that really true, the issue would of course be one to be addressed at the threshold.
Timeliness
Here the combatants point to two different subsections of EPA’s regulation (40 CFR § 35.939), each emphasizing the word it says controls. Healy refers to Subsection (e)(1):
Any such request [for review of MDS’s determination] ... must be received by the Regional Administrator within 1 week after the complaining party [Klein] has received the grantee’s [MSD’s] determination of the protest.7
EPA and Klein rely on the permissive (not mandatory) language of Subsection (f)(7):
[657]*657A protest may be dismissed for failure to comply with procedural requirements of this section.
Healy’s argument that the requirement is jurisdictional — and that EPA is therefore without power to review MPL’s determination because Klein did not present its protest within the week — is empty. Both EPA and Klein adduce a number of instances in which EPA has exercised its discretion to review like protests submitted after the specified one-week period had expired.
Free access — add to your briefcase to read the full text and ask questions with AI
MEMORANDUM OPINION AND ORDER
SHADUR, District Judge.
S.A. Healy Company (“Healy”) has sued Metropolitan Sanitary District of Greater Chicago (“MSD”), its Purchasing Agent George Wahl (“Wahl”), United States Environmental Protection Agency (“EPA”), its Region Y Regional Administrator Valdas Adamkus (“Adamkus”) and Klein Construction Company (“Klein”) for judicial review of a February 6, 1984. determination made by Adamkus for EPA relating to an MSD construction project to be funded in principal part by the federal government. Healy, EPA and Klein (the successful bidder as a result of Adamkus’ determination) have moved for summary judgment under Fed.R.Civ.P. (“Rule”) 56. For the reasons stated in this memorandum opinion and order, Healy’s motion is denied and the Klein-EPA motions are granted.
Facts1
On May 4, 1983 MSD solicited bids on a contract for blower facilities at its Calumet Sewage Treatment Works. Healy, Klein and six others submitted bids. When the bids were opened June 7, Healy’s adjusted bid2 of $16,733,846 was the low bid with the possible exception of the following “alternate] bid” of $16,652,390 included on the last page of Klein’s bid3 *just below the signature lines:
Alt Bid Using Loutma Bid-If Acceptable
Voluntary Alternate Loutema Blowers
Contract bid price 14,000,000.—
Guaranteed max power 4 2,890
GMPC - 2500. = 390 HP
HP differential = 2,652,390.—
Contract bid price + bid adjustment 16,652,390.00
On August 23 Wahl (acting for MSD) rejected the various protests by Klein and other bidders, finding Healy’s bid “the low, responsive, responsible bid for MSD contract 77-289-2M.” It is highly significant for current purposes that in turning down the protests by two of the bidders other than Klein, Wahl specifically approved (1) the use of Lotema Corporation (“Lotema”) 5 equipment by Healy for its bid and (2) the guaranteed maximum power consumption level of 2890 horsepower at which Healy’s bid {and Klein’s alternate bid as well) specified the Lotema blowers would perform.
On September 1 Klein and the two other protesters appealed to EPA (on differing grounds) from MSD’s adverse determination. After full briefing and other written submissions, EPA’s Office of Regional Counsel issued a Report and Recommendation that was adopted by Adamkus February 6, 1984. Based on the Report and Recommendation Adamkus (acting for EPA):
[656]*656(1) affirmed MSD’s decision to dismiss the other protests but
(2) sustained Klein’s protest, designating it and not Healy the “low, responsive, responsible” bidder and returned the matter to MSD to award the contract to Klein.
This action followed.
Standard for Review
This action is brought under the judicial review section of the Administrative Procedure Act (“APA”), 5 U.S.C. § 706. MSD invites this Court to decide that its determination in Healy’s favor had a rational basis — but that would amount to an impermissible de novo review of EPA’s determination to the contrary. Instead the question for this Court is the quite different one whether EPA had a rational basis for deciding that MSD’s determination lacked a rational basis.
As our Court of Appeals said last year in Wisconsin Electric Power Co. v. Costle, 715 F.2d 323, 325 (7th Cir.1983) (quotation paraphrased to track the present case):
Our review of the [EPA] decisions is governed by the judicial review section of the APA, see 5 U.S.C. § 706.... [Therefore we can disturb the EPA’s decision only if the agency acted beyond the scope of its statutory authority, or in an arbitrary or capricious manner, or in violation of [MSD’s] procedural rights.
That decision cited to the seminal decision in Citizens To Preserve Overton Park v. Volpe, 401 U.S. 402, 415-17, 91 S.Ct. 814, 823-24, 28 L.Ed.2d 136 (1971), which made plain that in circumstances like those presented here the EPA decision is “entitled to a presumption of regularity” (id. at 415, 91 S.Ct. at 823), though it is to be subjected to a “thorough, probing, in-depth review” (id.). Under Overton Park that required review involves three steps, which in terms of this case are these:
1. . EPA must have acted within the scope of its authority.6
2. EPA’s decision must not be “arbitrary, capricious, an abuse of discretion or otherwise not in accordance with law ...” (id. at 416, 91 S.Ct. at 823). As the Court went on to say (id.) (citations omitted):
To make this finding the court must consider whether the decision was based on a consideration of the relevant factors and whether there has been a clear error of judgment ... Although this inquiry into the facts is to be searching and careful, the ultimate standard of review is a narrow one. The court is not empowered to substitute its judgment for that of the agency.
3. EPA must have followed the necessary procedural requirements.
This opinion will not conform to that sequence, dealing instead with the last Overton Park inquiry first. It does so because Healy’s argument in that respect— that Klein’s protest to EPA was not timely — is claimed to be jurisdictional. Were that really true, the issue would of course be one to be addressed at the threshold.
Timeliness
Here the combatants point to two different subsections of EPA’s regulation (40 CFR § 35.939), each emphasizing the word it says controls. Healy refers to Subsection (e)(1):
Any such request [for review of MDS’s determination] ... must be received by the Regional Administrator within 1 week after the complaining party [Klein] has received the grantee’s [MSD’s] determination of the protest.7
EPA and Klein rely on the permissive (not mandatory) language of Subsection (f)(7):
[657]*657A protest may be dismissed for failure to comply with procedural requirements of this section.
Healy’s argument that the requirement is jurisdictional — and that EPA is therefore without power to review MPL’s determination because Klein did not present its protest within the week — is empty. Both EPA and Klein adduce a number of instances in which EPA has exercised its discretion to review like protests submitted after the specified one-week period had expired. EPA thus applies the “may be dismissed” provision literally — surely a permissible reading. It is black letter law that, Udall v. Tallman, 380 U.S. 1, 16, 85 S.Ct. 792, 801, 13 L.Ed.2d 616 (1965):
When faced with a problem of statutory construction, this Court shows great deference to the interpretation given the statute by the officers or agency charged with its administration____ When the construction of an administrative regulation rather than a statute is in issue, deference is even more clearly in order.
Because EPA’s interpretation of its own regulations is unquestionably non-arbitrary, that really concludes the issue.
Moreover, even Healy recognizes (as it must) that EPA has a sua sponte power of review of just such questions under 40 CFR § 35.935-2. Healy urges that is irrelevant because EPA did not in fact purport to act sua sponte here. But what Healy fails to perceive is that EPA’s sua sponte power has a different cutting edge: It would be wholly anomalous to say EPA can act outside the one-week period sua sponte to correct a flaw in a contract award, but EPA is powerless to do so at the behest of a protester who has called the flaw to its attention. Thus the very existence of the sua sponte power tends to confirm the reasonableness of EPA’s reading that the one-week period for protests is not “jurisdictional” or “non-waivable,” but is rather a permissive (non-mandatory) ground for dismissal that it is not duty-bound to exercise.
Finally in this area, Healy seeks to rely on three District Court decisions, BSP Division of Envirotech Corp. v. United States, 471 F.Supp. 958 (D.N.J.1979); New Ikor, Inc. v. McGlennon, 446 F.Supp. 136 (D.Mass.1978); Maclean Construction Co. v. EPA, 432 F.Supp. 242 (W.D.Mich.1970). However they give Healy no real comfort:8
1. All three cases reconfirmed the “arbitrary and capricious” standard for review of EPA’s decisions, as stated in the APA and articulated in Overton Park.
2. Most significantly, all three simply upheld EPA’s decision to dismiss a protest as not being irrational.
Those decisions thus dealt with and upheld EPA’s exercise of its “may be dismissed” power — a far cry from supporting a reversal of EPA’s decision not to dismiss, as here.
There is thus no validity to Healy’s “jurisdictional” contention. This opinion can turn to the merits of EPA’s decision.
Klein's Alternate Bid
Under the circumstances of this case Klein’s alternate bid, though roughhewn, is as plain as plain can be. It was not, as Healy argues, either qualified or conditional or ambiguous. It clearly changed only one thing in the terms of the higher bid contained in the body of its proposal form: Lotema equipment was substituted for the other blowers contemplated in Klein’s costlier proposal. Having accepted Lotema equipment for purposes of the Healy bid9, MSD and Wahl could not rationally find them unacceptable as embraced by Klein’s alternate bid.
[658]*658What the preceding paragraph demonstrates is that this case would pass even the more stringent (and erroneous) criterion voiced by MSD — that its decision lacked a rational basis. A fortiori EPA’s decision passes muster under the proper standard: EPA surely had a rational basis for deciding MSD lacked a rational basis for its decision.
This opinion will not pause on the several other nit-picking, less-than-makeweight reasons stated by Wahl on MSD’s behalf, or advanced by MSD before EPA or this Court (see Healy Mem. 21-23 and R.Mem. 17). They are really not worth discussing, for to state them is to reveal their poverty. Suffice it to say this Court has considered each of them and has found EPA could rationally have found them — both individually and collectively — to be without rational support.10
Conclusion
There is no genuine issue of material fact, and EPA and Klein are entitled to a judgment as a matter of law. Healy’s motion for summary judgment (supported by MSD) is denied. This action is dismissed with prejudice, and MSD is ordered to comply with the Adamkus-EPA February 6, 1984 determination and to award the contract to Klein.