Brubacher Excavating, Inc. v. Commerce Bank/Harrisburg, N.A.

995 A.2d 362, 2010 Pa. Super. 67, 2010 Pa. Super. LEXIS 334, 2010 WL 1643275
CourtSuperior Court of Pennsylvania
DecidedApril 23, 2010
Docket96 MDA 2009
StatusPublished
Cited by3 cases

This text of 995 A.2d 362 (Brubacher Excavating, Inc. v. Commerce Bank/Harrisburg, N.A.) is published on Counsel Stack Legal Research, covering Superior Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brubacher Excavating, Inc. v. Commerce Bank/Harrisburg, N.A., 995 A.2d 362, 2010 Pa. Super. 67, 2010 Pa. Super. LEXIS 334, 2010 WL 1643275 (Pa. Ct. App. 2010).

Opinion

*363 OPINION BY

SHOGAN, J.:

¶ 1 Commerce Bank/Harrisburg, N.A. (“Appellant”) appeals from the order entering summary judgment in favor of Bru-bacher Excavating, Inc. (“Appellee”). Because we hold that the trial court erred in awarding prejudgment interest, we vacate and remand for modification of the judgment consistent with this Opinion.

¶ 2 The trial court set forth the relevant factual and procedural background of this case as follows:

I. Background
The facts of this case are undisputed. 1 This action arises out of the construction of a branch bank of Commerce Bank/Harrisburg, N.A. (“[Appellant]”), located at 1461 Manheim Pike, Lancaster, Pennsylvania (the “Property”). Manheim Equities is the owner-in-fee of the Property, and [Appellant] is the tenant. Manheim Equities, as lessor, assigned its interest in the lease to Liberty Bank.
On September 6, 2006, [Appellant] entered into a written contract with Premier Construction, Inc. (“Premier”) to construct the branch bank. Prior to permission or authority being given by Manheim Equities or [Appellant] to Premier for the commencement of work on the project, [Appellant] caused to be filed in the Prothonotary’s Office of the Court of Common Pleas of Lancaster County on October 3, 2006, a Stipulation Against Liens which was dated September 29, 2006. The Stipulation Against Liens was filed to Docket No. CI-06-09679 and was in conformance with all requirements of the Mechanics’ Lien Law then in effect. Accordingly, as of October 3, 2006, this Stipulation could have been reviewed by any and all subcontractors and sub-subcontractors who were to perform work on the Property.
On November 3, 2006, Premier entered into a subcontract with McElroy Contractors, LLC (“McElroy”), whereby McElroy was to perform certain site work at the Property for an estimated $116,815.00. McElroy in turn subcontracted a portion of its work to Brubacher Excavating, Inc. (“[Appellee]”), on or about April 27, 2007, to perform asphalt paving on the project at a bid price of $45,689.00.
■ [Appellee] completed asphalt paving on the Property on or about May 21, 2007, and invoiced McElroy in the amount of $42,976.45, which represented the cost of labor and materials. 2 McEl-roy has not paid any amount to [Appel-lee] for its work on the project. McEl-roy was required to pay [Appellee] within 30 days of its invoice dated May 21, 2007, or by June 20, 2007. Premier has paid McElroy for all amounts due and owing under its subcontract with McElroy except for $20,224.31 that it is still retaining from McElroy.
On or about August 27, 2007, [Appel-lee] notified [Appellant] and Premier in writing that it intended to file a mechanics[’] lien on the project. [Appellee] filed its mechanics[’] lien claim on October 19, 2007, and subsequently filed a complaint in action upon the mechanics[’] lien claim on November 14, 2007. [Appellant] filed preliminary objections on December 4, 2007, which were overruled by Order of this [c]ourt dated February 4, 2008. [Appellant] then filed an answer with new matter on February *364 21, 2008, to which [Appellee] filed a reply on February 26, 2008.
A petition to discharge the mechanics[’] lien on deposit of security pursuant to 49 P.S. § 1510 was filed by [Appellant] on April 14, 2008. A rule was entered upon [Appellee] on April 28, 2008, to show cause why [Appellant] was not entitled to the relief requested in its petition. Ultimately, an order was entered on July 10, 2008, granting the petition to discharge and directing the Prothonotary, upon [Appellant’s] depositing of the surety bond attached to the petition as Exhibit “A,” to discharge [Appellee’s] mechanics^] lien claim filed in the Office of the Prothonotary. The Bond to Discharge Existing Lien was filed on July 11, 2008.
Meanwhile, the case was certified as ready for trial and a pretrial conference was held on June 5, 2008, during which the parties agreed that a trial was unnecessary and that this matter could be disposed of on cross-motions for summary judgment. The parties further agreed to enter into stipulations of fact prior to the filing of the cross-motions for summary judgment by the parties. [Appellant’s] motion and brief in support thereof were filed on July 25, 2008. [Appellee] filed its cross-motion for summary judgment and brief in opposition to [Appellant’s] motion for summary judgment and in support of its motion for summary judgment on September 5, 2008. Reply briefs were filed by [Appellant] and [Appellee] on October 2, 2008, and October 8, 2008, respectively.

Trial Court Opinion on Cross Motions for Summary Judgment, 12/22/08, at 1-4.

¶ 3 In its Order entered on the same date, the trial court granted summary judgment in favor of Appellee Brubacher Excavating, Inc., and entered judgment in the amount of $42,976.45, together with pre-judgment interest at the statutory rate of 6% from June 20, 2007 to the date judgment was entered. Trial Court Order, 12/22/08.

¶ 4 Appellant then filed the instant appeal, which presents the following questions for our review:

1. Whether the amendments to the Pennsylvania Mechanics’ Lien Law, 49 P.S. § 1101 et seg., which became effective after [Ajppellant Commerce Bank/Harrisburg N.A. entered into a construction contract with the general contactor, can be properly and legally interpreted so as to retroactively create a right to a mechanic’s lien by a sub-subcontractor when no such right existed at the time Commerce entered into the construction contract?
2. Whether the amendments to the Pennsylvania Mechanics’ Lien Law, 49 P.S. § 1101 et seq., retroactively voided a stipulation against liens that was filed by Commerce prior to the effective date of the amendments?
3. Whether a properly filed stipulation against liens[,] which placed all potential claimants, including Brubacher, on notice that the property was subject to a stipulation against liens, was limited in its effect because it contained a description of a portion of the work to be performed?
4. Whether a contractor may recover interest as part of a mechanics’ lien claim when the Mechanics’ Lien Law provides proper claimants with a statutory right to assert a lien to secure payment for the value of labor and materials only?

Appellant’s Brief at 4.

¶ 5 In reviewing the grant of a motion for summary judgment, we use the following standard and scope of review:

*365 We view the record in the light most favorable to the nonmoving party, and all doubts as to the existence of a genuine issue of material fact must be resolved against the moving party. Only where there is no genuine issue as to any material fact and it is clear that the moving party is entitled to a judgment as a matter of law will summary judgment be entered.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rodriguez, M. v. Kravco Simon Co.
111 A.3d 1191 (Superior Court of Pennsylvania, 2015)
Hogg Construction, Inc. v. Yorktowne Medical Centre, L.P.
78 A.3d 1152 (Superior Court of Pennsylvania, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
995 A.2d 362, 2010 Pa. Super. 67, 2010 Pa. Super. LEXIS 334, 2010 WL 1643275, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brubacher-excavating-inc-v-commerce-bankharrisburg-na-pasuperct-2010.