Brox v. H.J. Stabile

Court of Appeals for the First Circuit·Decided March 28, 1994·No. 93-1970·Published

Opinion

USCA1 Opinion


March 25, 1994 NOT FOR PUBLICATION
NOT FOR PUBLICATION
UNITED STATES COURT OF APPEALS
FOR THE FIRST CIRCUIT
____________________

No. 93-1970

BROX INDUSTRIES, INC.,

Plaintiff, Appellee,

v.

H.J. STABILE & SONS, INC. ET AL.,

Defendants, Appellants.

____________________

APPEAL FROM THE UNITED STATES DISTRICT COURT

FOR THE DISTRICT OF NEW HAMPSHIRE

[Hon. Martin F. Loughlin, Senior U.S. District Judge]
__________________________

____________________

Before

Torruella, Circuit Judge,
_____________
Bownes, Senior Circuit Judge,
____________________
and Selya, Circuit Judge.
_____________

____________________

James E. Owers, with whom Sulloway & Hollis was on brief for
_______________ __________________
appellant Reliance Insurance Company and Morgan A. Hollis, with whom
________________
Gottesman & Hollis was on brief for appellant H.J. Stabile & Sons,
__________________
Inc.
Frank P. Spinella, Jr., with whom Hibbard & Spinella, P.A. was on
______________________ _________________________
brief for appellee.

____________________

____________________

BOWNES, Senior Circuit Judge. This diversity
BOWNES, Senior Circuit Judge.
_____________________

case requires us to rule on the timeliness of a notice of

claim under a payment bond. The district court, after an

evidentiary hearing, held that the notice was timely and

therefore granted judgment for plaintiff-appellee Brox

Industries in the amount of $178,155.86. We affirm.

I.
I.

BACKGROUND
BACKGROUND
__________

We set forth a summary of the pertinent facts found

by the district court. In June 1991 defendant-appellant H.J.

Stabile & Son, Inc. entered into a contract with Wal-Mart

Stores, Inc. to build a store in Seabrook, New Hampshire. In

July 1991 Stabile obtained a payment bond from co-defendant-

appellant Reliance Insurance Company. Reliance, of course,

is the real party in interest. Stabile subsequently

subcontracted with Atom Contracting Corp. to do work on the

Wal-Mart project. Atom then subcontracted with Brox to do

both on-site and off-site paving.

Under Stabile's contract with Wal-Mart all work was

to be completed on the project by December 3, 1991. By mid-

December Brox had not completed a substantial portion of the

paving work under its contract with Atom. On December 13

Stabile instructed Brox that it should cease operations on

the project due to the onset of winter. Because all of the

parties recognized that paving cannot be done properly in the

-2-
2

winter, they agreed that Brox would return the following

spring to complete the work. Stabile fully expected that

Brox would return to the work-site in the spring, and Brox

anticipated doing so. On December 23, 1991 Brox notified

Stabile that substantial work remained for the spring,

provided Stabile with an estimate of the remaining work, and

stated that the total amount of the paving work performed to

date was $201,106.50. Brox invoiced Atom for this work in

December 1991.

In February and March 1992, in response to concerns

of Wal-Mart about the quality of Brox's paving, Brox

conducted tests of its work. Also in March 1992, a Brox

employee filled in several potholes at the worksite in

preparation for returning to the project.

By March of 1992 Stabile had paid Atom all sums due

for work performed by Atom and its subcontractors, including

Brox. Atom, however, still owed Brox $178,155.86 for work

done through December 13, 1991. On March 18, 1992 Brox sent

a notice of claim for that amount to Reliance as surety for

Stabile. Nonetheless, Brox anticipated that it would finish

the paving work in the spring under its contract with Atom.

On May 14, 1992 Atom informed Stabile that it

intended to honor their contract, and that the State of New

Hampshire wanted two roads, which were contiguous to the

planned store, to be paved by June 1. On June 4 Stabile

-3-
3

agreed to the additional paving with a charge back to Atom.

Although the specifics are unclear, shortly thereafter

Stabile recognized that Atom would be unable to meet its

contractual obligations, and therefore it sought to engage a

new contractor to complete the paving work.

On June 11, after a brief bidding period, Stabile

and Brox entered into two contracts for the completion of the

paving at the project, one for on-site and one for off-site

work. On June 30 Stabile formally terminated its contract

with Atom. Brox finished the paving work at the project.

In August 1992 Brox commenced a diversity action in

the United States District Court for the District of New

Hampshire against Stabile and Reliance seeking payment under

the bond issued by Reliance as surety for Stabile. Under the

bond, a party not in direct privity with the principal, such

as Brox, must give notice of its claim to: the Principal,

the Surety, or the Owner, "within ninety (90) days after such

claimant did or performed the last of the work or labor, or

furnished the last of the materials for which said claim is

made." No claim is

Free access — add to your briefcase to read the full text and ask questions with AI

Brox v. H.J. Stabile, (1st Cir. 1994).

Brox v. H.J. Stabile (Brox v. H.J. Stabile) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

United States v. Thompson Construction Corp.
273 F.2d 873 (Second Circuit, 1959)
New England Metal Culvert Co. v. Williams Construction Co.
196 A.2d 713 (Supreme Court of New Hampshire, 1963)
Raitt v. National Grange Mutual Insurance
285 A.2d 799 (Supreme Court of New Hampshire, 1971)
American Fidelity Co. v. Cray
194 A.2d 763 (Supreme Court of New Hampshire, 1963)
Tolles-Bickford Lumber Co. v. Tilton School
94 A.2d 374 (Supreme Court of New Hampshire, 1953)