Brox v. H.J. Stabile
Opinion
USCA1 Opinion
March 25, 1994 NOT FOR PUBLICATION
NOT FOR PUBLICATION
UNITED STATES COURT OF APPEALS
FOR THE FIRST CIRCUIT
____________________
No. 93-1970
BROX INDUSTRIES, INC.,
Plaintiff, Appellee,
v.
H.J. STABILE & SONS, INC. ET AL.,
Defendants, Appellants.
____________________
APPEAL FROM THE UNITED STATES DISTRICT COURT
FOR THE DISTRICT OF NEW HAMPSHIRE
[Hon. Martin F. Loughlin, Senior U.S. District Judge]
__________________________
____________________
Before
Torruella, Circuit Judge,
_____________
Bownes, Senior Circuit Judge,
____________________
and Selya, Circuit Judge.
_____________
____________________
James E. Owers, with whom Sulloway & Hollis was on brief for
_______________ __________________
appellant Reliance Insurance Company and Morgan A. Hollis, with whom
________________
Gottesman & Hollis was on brief for appellant H.J. Stabile & Sons,
__________________
Inc.
Frank P. Spinella, Jr., with whom Hibbard & Spinella, P.A. was on
______________________ _________________________
brief for appellee.
____________________
____________________
BOWNES, Senior Circuit Judge. This diversity
BOWNES, Senior Circuit Judge.
_____________________
case requires us to rule on the timeliness of a notice of
claim under a payment bond. The district court, after an
evidentiary hearing, held that the notice was timely and
therefore granted judgment for plaintiff-appellee Brox
Industries in the amount of $178,155.86. We affirm.
I.
I.
BACKGROUND
BACKGROUND
__________
We set forth a summary of the pertinent facts found
by the district court. In June 1991 defendant-appellant H.J.
Stabile & Son, Inc. entered into a contract with Wal-Mart
Stores, Inc. to build a store in Seabrook, New Hampshire. In
July 1991 Stabile obtained a payment bond from co-defendant-
appellant Reliance Insurance Company. Reliance, of course,
is the real party in interest. Stabile subsequently
subcontracted with Atom Contracting Corp. to do work on the
Wal-Mart project. Atom then subcontracted with Brox to do
both on-site and off-site paving.
Under Stabile's contract with Wal-Mart all work was
to be completed on the project by December 3, 1991. By mid-
December Brox had not completed a substantial portion of the
paving work under its contract with Atom. On December 13
Stabile instructed Brox that it should cease operations on
the project due to the onset of winter. Because all of the
parties recognized that paving cannot be done properly in the
-2-
2
winter, they agreed that Brox would return the following
spring to complete the work. Stabile fully expected that
Brox would return to the work-site in the spring, and Brox
anticipated doing so. On December 23, 1991 Brox notified
Stabile that substantial work remained for the spring,
provided Stabile with an estimate of the remaining work, and
stated that the total amount of the paving work performed to
date was $201,106.50. Brox invoiced Atom for this work in
December 1991.
In February and March 1992, in response to concerns
of Wal-Mart about the quality of Brox's paving, Brox
conducted tests of its work. Also in March 1992, a Brox
employee filled in several potholes at the worksite in
preparation for returning to the project.
By March of 1992 Stabile had paid Atom all sums due
for work performed by Atom and its subcontractors, including
Brox. Atom, however, still owed Brox $178,155.86 for work
done through December 13, 1991. On March 18, 1992 Brox sent
a notice of claim for that amount to Reliance as surety for
Stabile. Nonetheless, Brox anticipated that it would finish
the paving work in the spring under its contract with Atom.
On May 14, 1992 Atom informed Stabile that it
intended to honor their contract, and that the State of New
Hampshire wanted two roads, which were contiguous to the
planned store, to be paved by June 1. On June 4 Stabile
-3-
3
agreed to the additional paving with a charge back to Atom.
Although the specifics are unclear, shortly thereafter
Stabile recognized that Atom would be unable to meet its
contractual obligations, and therefore it sought to engage a
new contractor to complete the paving work.
On June 11, after a brief bidding period, Stabile
and Brox entered into two contracts for the completion of the
paving at the project, one for on-site and one for off-site
work. On June 30 Stabile formally terminated its contract
with Atom. Brox finished the paving work at the project.
In August 1992 Brox commenced a diversity action in
the United States District Court for the District of New
Hampshire against Stabile and Reliance seeking payment under
the bond issued by Reliance as surety for Stabile. Under the
bond, a party not in direct privity with the principal, such
as Brox, must give notice of its claim to: the Principal,
the Surety, or the Owner, "within ninety (90) days after such
claimant did or performed the last of the work or labor, or
furnished the last of the materials for which said claim is
made." No claim is
Free access — add to your briefcase to read the full text and ask questions with AI
Brox v. H.J. Stabile, (1st Cir. 1994).
Brox v. H.J. Stabile (Brox v. H.J. Stabile) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.
Related
United States v. Thompson Construction Corp.
273 F.2d 873 (Second Circuit, 1959)
United States Ex Rel. P. A. Bourquin & Co. v. Chester Const. Co.
104 F.2d 648 (Second Circuit, 1939)
New England Metal Culvert Co. v. Williams Construction Co.
196 A.2d 713 (Supreme Court of New Hampshire, 1963)
Raitt v. National Grange Mutual Insurance
285 A.2d 799 (Supreme Court of New Hampshire, 1971)
American Fidelity Co. v. Cray
194 A.2d 763 (Supreme Court of New Hampshire, 1963)
Tolles-Bickford Lumber Co. v. Tilton School
94 A.2d 374 (Supreme Court of New Hampshire, 1953)
United States ex rel. John D. Ahern Co. v. J. F. White Contracting Co.
649 F.2d 29 (First Circuit, 1981)