Brox v. H.J. Stabile

21 F.3d 419
CourtCourt of Appeals for the First Circuit
DecidedMarch 28, 1994
Docket93-1970
StatusUnpublished

This text of 21 F.3d 419 (Brox v. H.J. Stabile) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brox v. H.J. Stabile, 21 F.3d 419 (1st Cir. 1994).

Opinion

21 F.3d 419

NOTICE: First Circuit Local Rule 36.2(b)6 states unpublished opinions may be cited only in related cases.
BROX INDUSTRIES, INC., Plaintiff, Appellee,
v.
H.J. STABILE & SONS, INC. ET AL., Defendants, Appellants.

No. 93-1970

United States Court of Appeals,
First Circuit.

March 25, 1994

Appeal from the United States District Court for the District of New Hampshire [Hon. Martin F. Loughlin, Senior U.S. District Judge ]

James E. Owers, with whom Sulloway & Hollis was on brief for appellant Reliance Insurance Company and Morgan A. Hollis, with whom Gottesman & Hollis was on brief for appellant H.J. Stabile & Sons, Inc.

Frank P. Spinella, Jr., with whom Hibbard & Spinella, P.A. was on brief for appellee.

D.N.H.

AFFIRMED.

Before Torruella, Circuit Judge, Bownes, Senior Circuit Judge, and Selya, Circuit Judge.

BOWNES, Senior Circuit Judge.

This diversity case requires us to rule on the timeliness of a notice of claim under a payment bond. The district court, after an evidentiary hearing, held that the notice was timely and therefore granted judgment for plaintiff-appellee Brox Industries in the amount of $178,155.86. We affirm.

I.

BACKGROUND

We set forth a summary of the pertinent facts found by the district court. In June 1991 defendant-appellant H.J. Stabile & Son, Inc. entered into a contract with Wal-Mart Stores, Inc. to build a store in Seabrook, New Hampshire. In July 1991 Stabile obtained a payment bond from co-defendant-appellant Reliance Insurance Company. Reliance, of course, is the real party in interest. Stabile subsequently subcontracted with Atom Contracting Corp. to do work on the Wal-Mart project. Atom then subcontracted with Brox to do both on-site and off-site paving.

Under Stabile's contract with Wal-Mart all work was to be completed on the project by December 3, 1991. By mid-December Brox had not completed a substantial portion of the paving work under its contract with Atom. On December 13 Stabile instructed Brox that it should cease operations on the project due to the onset of winter. Because all of the parties recognized that paving cannot be done properly in the winter, they agreed that Brox would return the following spring to complete the work. Stabile fully expected that Brox would return to the work-site in the spring, and Brox anticipated doing so. On December 23, 1991 Brox notified Stabile that substantial work remained for the spring, provided Stabile with an estimate of the remaining work, and stated that the total amount of the paving work performed to date was $201,106.50. Brox invoiced Atom for this work in December 1991.

In February and March 1992, in response to concerns of Wal-Mart about the quality of Brox's paving, Brox conducted tests of its work. Also in March 1992, a Brox employee filled in several potholes at the worksite in preparation for returning to the project.

By March of 1992 Stabile had paid Atom all sums due for work performed by Atom and its subcontractors, including Brox. Atom, however, still owed Brox $178,155.86 for work done through December 13, 1991. On March 18, 1992 Brox sent a notice of claim for that amount to Reliance as surety for Stabile. Nonetheless, Brox anticipated that it would finish the paving work in the spring under its contract with Atom.

On May 14, 1992 Atom informed Stabile that it intended to honor their contract, and that the State of New Hampshire wanted two roads, which were contiguous to the planned store, to be paved by June 1. On June 4 Stabile agreed to the additional paving with a charge back to Atom. Although the specifics are unclear, shortly thereafter Stabile recognized that Atom would be unable to meet its contractual obligations, and therefore it sought to engage a new contractor to complete the paving work.

On June 11, after a brief bidding period, Stabile and Brox entered into two contracts for the completion of the paving at the project, one for on-site and one for off-site work. On June 30 Stabile formally terminated its contract with Atom. Brox finished the paving work at the project.

In August 1992 Brox commenced a diversity action in the United States District Court for the District of New Hampshire against Stabile and Reliance seeking payment under the bond issued by Reliance as surety for Stabile. Under the bond, a party not in direct privity with the principal, such as Brox, must give notice of its claim to: the Principal, the Surety, or the Owner, "within ninety (90) days after such claimant did or performed the last of the work or labor, or furnished the last of the materials for which said claim is made." No claim is made that Brox failed to give notice as required to the Principal, Surety or Owner.

The principal defense of Stabile and Reliance is that Brox's March 18, 1992 notice was untimely under the bond's requirements. Brox moved for summary judgment based on two alternative theories. It argued first that, assuming arguendo that its notice was untimely, Reliance must show prejudice from the tardiness in order to bar recovery under the bond. According to Brox, no prejudice could be shown. Alternatively, Brox maintained that its notice was timely under the bond.

The district court, in an opinion dated August 18, 1993, found that Brox's notice was timely. According to the district court, "[t]he crux of the case ... appears to be whether [Brox's] work [was] completed in December, 1991." Brox Industries, Inc. v. H.J. Stabile & Son, Inc., No. 92-426-L, slip op. at 6 (D.N.H. August 18, 1993). At the evidentiary hearing the court stated that "[i]f ... an agreement [about a winter hiatus] was made then clearly [Brox's] work under its subcontract with Atom was not completed on December 13, 1991 and [Brox's] failure to give notice within ninety days of that day would not bar recovery under the bond." Because the court eventually found that Brox still had substantial work to do on the contract as of December 13, and that the parties agreed to a winter hiatus of greater than ninety days, it held that Brox's notice was not untimely. Id. at 7.

In response to Brox's argument that work done at the project site in February and March 1992, i.e., quality tests and pothole repairs, reset the ninety-day notice period, the district court found that both the tests and the pothole repairs were remedial in nature and did not "advance the completion of the project." Id. at 5. Accordingly, under New Hampshire law, the district court found that the above work had no effect upon the ninety-day notice period. See Tolles-Bickford Co. v. School, 94 A.2d 374 (N.H. 1953). This conclusion and its predicate factual findings have not been appealed. The court entered judgment for Brox for the full amount of its claim, and defendants appealed.

II.

DISCUSSION

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Erie Railroad v. Tompkins
304 U.S. 64 (Supreme Court, 1938)
A. B. Cooley, D/b/a, Etc. v. Barten & Wood, Inc.
249 F.2d 912 (First Circuit, 1957)
United States v. Thompson Construction Corp.
273 F.2d 873 (Second Circuit, 1959)
New England Metal Culvert Co. v. Williams Construction Co.
196 A.2d 713 (Supreme Court of New Hampshire, 1963)
Raitt v. National Grange Mutual Insurance
285 A.2d 799 (Supreme Court of New Hampshire, 1971)
American Fidelity Co. v. Cray
194 A.2d 763 (Supreme Court of New Hampshire, 1963)
Tolles-Bickford Lumber Co. v. Tilton School
94 A.2d 374 (Supreme Court of New Hampshire, 1953)

Cite This Page — Counsel Stack

Bluebook (online)
21 F.3d 419, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brox-v-hj-stabile-ca1-1994.