Brownhawk, L.P. v. Monterrey Homes, Inc.

Procedural entryThis page is a short order in Brownhawk, L.P. v. Monterrey Homes, Inc.. Read the opinion of the Court — 2010 Tex. App. LEXIS 8742
Court of Appeals of Texas·Decided October 27, 2010·No. 08-08-00190-CV·Published

Opinion

COURT OF APPEALS EIGHTH DISTRICT OF TEXAS EL PASO, TEXAS

BROWNHAWK, L.P., § No. 08-08-00190-CV Appellant, § Appeal from the v. § 448th Judicial District Court § MONTERREY HOMES, INC., of El Paso County, Texas § Appellee. (TC# 2007-4136) §

OPINION

Brownhawk, L.P. (“Brownhawk) appeals a breach of contract judgment in favor of

Monterrey Homes, Inc. (Monterrey”) in the amount of $225,000, plus pre-judgment interest and

attorney’s fees. In three issues, Brownhawk challenges the trial court’s findings of fact and

conclusions of law and its attorney’s fees award.

In September 2007, Brownhawk, a real estate developer, and Monterrey, a residential

construction company, entered into an agreement for Monterrey to purchase an unimproved tract

of land in El Paso County for development of the “Dos Palmas” subdivision. The parties signed

an earnest money contract for the property on September 21, 2006 (“the contract”). Monterrey

agreed to pay $2,250,000 for the property, and Brownhawk agreed to convey the property to

Monterrey including certain improvements which were to be completed by Brownhawk, in a

“good workman-like manner” on or before May 31, 2007. The improvements were specified as

follows: (1) Brownhawk would complete all earthwork and grading, as specified by the

subdivision plan; (2) install all sidewalks, streets with curbs, and gutters; and (3) install all utilities as appropriate for a residential subdivision.

The contract contained a general termination or “default” provision which provided each

party with the right to terminate the contract, seek specific performance, or seek other remedies

as provided by law, for breach by the other party. In a separate section, the contract also gave

Monterrey the right to terminate the contract and receive a full refund of the earnest money if

Brownhawk failed to complete the improvements by the date specified. The contract also

provided for the recovery of attorney’s fees for the prevailing party should a default lead to

litigation.

Final closing on the improved property was scheduled to take place “on or before 15 days

after completion of development.” Upon signing the agreement, Monterrey immediately

deposited $25,000 into an escrow account. Later, in accordance with the contract, Monterrey

deposited another $200,000 into escrow after the City of El Paso approved the preliminary

subdivision plat. Over the next few months, the parties negotiated numerous changes to the

configuration of the subdivision plat which required re-submission of the amended subdivision

plat for the city’s approval. The city approved the change, but required the parties to install a

“drainage flume” to accommodate the reduction.

With the newly approved subdivision plans approved, the parties signed an amendment to

the contract to further specify their responsibilities prior to closing. The amendment, signed

April 30, 2007, changed the property description to reference the updated subdivision plans

approved by the city, and made several changes to the closing provisions. First, the amendment

extended Brownhawk’s deadline for its initial construction obligations to May 30, 2007, with an

automatic forty-five day extension if Brownhawk was unable to meet the amended deadline. The

-2- amendment specified that closing would take place within fifteen days of “Completion of

Development” and further specified that “Completion of Development” would occur when

Brownhawk completed the following: (1) all earthwork and grading as required by the

Developer/Builder plan (attached to the amendment as Exhibit A); (2) all streets with curbs and

gutters and all sidewalks shown on the Developer/Builder Plan as “By Developer;” (3) all

utilities for a residential subdivision as specified by the Developer/Builder Plan; and (4) all “By

Developer” retaining walls according to the Developer/Builder Plan. Monterrey, in turn, took

responsibility for construction of all rock or retaining walls between lots, all rock or retaining

walls noted as “By Builder” on the Developer/Builder Plan, and construction of sidewalks along

Dos Palmas Drive, also specified as “By Builder.” Monterrey agreed it was responsible for

completing the “Builder’s Improvements” even if they were not completed by closing, and

further agreed that closing would not be delayed in any way by its failure to complete those

improvements. Finally, the amendment provides an additional termination provision for

Monterrey. In the event Brownhawk was unable to complete its improvements by the extended

completion date, Monterrey could terminate the contract by written notice to Brownhawk, or

negotiate another extension. If Monterrey chose to terminate the contract, it was entitled to a

refund of any remaining escrow funds, subject only to Monterrey’s decision to exercise its right

to purchase certain lots prior to closing (Monterrey’s “Early Purchase Right”). The amendment

does not specifically reference the drainage flume construction.

The parties never closed on the property. On September 12, 2007, Brownhawk filed suit

against Monterrey for breach of contract, alleging that despite the completion of “virtually all” of

its own construction obligations, Monterrey failed to complete construction of the “By Builder”

-3- projects, and prevented Brownhawk from securing a final inspection from the City of El Paso.

Monterrey counter-claimed with its own breach of contract claim, alleging that Brownhawk

failed to meet the extended completion deadline provided by the contract amendment, and that it

had exercised its right to terminate the agreement by written notice sent to Brownhawk on

August 16, 2007.

The case was tried to the bench beginning on April 21, 2008. On April 30, 2008, at the

close of evidence, the trial court ruled in favor of Monterrey on its counterclaim and awarded

$225,000 plus interest and attorney’s fees. The trial court also awarded Monterrey $49,450 for

attorney’s fees, with additional contingent awards in the event of Brownhawk’s unsuccessful

appeals to this Court and the Texas Supreme Court. Following entry of the judgment, the court

entered findings of fact and conclusions of law.

The following findings are key to the disposition of this appeal:

5. Time was of the essence under the Contract.

6. [Pursuant to the Amendment] . . . Brownhawk was required to complete all the enumerated improvements no later than August 14, 2007 if the automatic extension was utilized. Time was again of the essence pursuant to the Contract Amendment.

. . .

8. [As of August 16, 2007] Brownhawk had not completed all the earth work and grading, nor had Brownhawk completed all the sidewalks, curbs and gutters.

10. [O]n August 14, 2007 the subdivision could not have passed final inspection and would not have been accepted by the City of El Paso.

-4- 13. In a letter dated August 16, 2007, Monterrey sent notice to Brownhawk electing to terminate the Contract. As part of the notice Monterrey demanded that Brownhawk release the escrowed amount of $225,000. . . . Brownhawk refused.

14. Brownhawk alleged that pursuant to revised plans that were filed with the City that Monterrey was supposed to construct a flume for drainage prior to the subdivision final inspection. Such revisions to the plan, however, were added after the plans to the Amendment were signed and without Monterrey’s permission or knowledge.

Free access — add to your briefcase to read the full text and ask questions with AI

Brownhawk, L.P. v. Monterrey Homes, Inc., (Tex. Ct. App. 2010).

Brownhawk, L.P. v. Monterrey Homes, Inc. (Brownhawk, L.P. v. Monterrey Homes, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Mustang Pipeline Co. v. Driver Pipeline Co.
134 S.W.3d 195 (Texas Supreme Court, 2004)
Abraxas Petroleum Corp. v. Hornburg
20 S.W.3d 741 (Court of Appeals of Texas, 2000)
Raw Hide Oil & Gas, Inc. v. Maxus Exploration Co.
766 S.W.2d 264 (Court of Appeals of Texas, 1988)
Anderson v. City of Seven Points
806 S.W.2d 791 (Texas Supreme Court, 1991)
Alford v. Johnston
224 S.W.3d 291 (Court of Appeals of Texas, 2005)
F-Star Socorro, L.P. v. City of El Paso
281 S.W.3d 103 (Court of Appeals of Texas, 2008)
Quick v. Plastic Solutions of Texas, Inc.
270 S.W.3d 173 (Court of Appeals of Texas, 2008)
Ragsdale v. Progressive Voters League
801 S.W.2d 880 (Texas Supreme Court, 1990)
Kimsey v. Kimsey
965 S.W.2d 690 (Court of Appeals of Texas, 1998)
O'NEIL v. MacK Trucks, Inc.
542 S.W.2d 112 (Texas Supreme Court, 1976)
Fasken Land & Minerals, Ltd. v. Occidental Permian Ltd.
225 S.W.3d 577 (Court of Appeals of Texas, 2005)
Ames v. Ames
776 S.W.2d 154 (Texas Supreme Court, 1989)
Manon v. Tejas Toyota, Inc.
162 S.W.3d 743 (Court of Appeals of Texas, 2005)
Marrs & Smith Partnership v. D.K. Boyd Oil & Gas Co.
223 S.W.3d 1 (Court of Appeals of Texas, 2005)
Tate v. Tate
55 S.W.3d 1 (Court of Appeals of Texas, 2000)