Brownhawk, L.P. v. Monterrey Homes, Inc.

327 S.W.3d 342, 2010 Tex. App. LEXIS 8742, 2010 WL 4231524
CourtCourt of Appeals of Texas
DecidedOctober 27, 2010
Docket08-08-00190-CV
StatusPublished
Cited by7 cases

This text of 327 S.W.3d 342 (Brownhawk, L.P. v. Monterrey Homes, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brownhawk, L.P. v. Monterrey Homes, Inc., 327 S.W.3d 342, 2010 Tex. App. LEXIS 8742, 2010 WL 4231524 (Tex. Ct. App. 2010).

Opinion

OPINION

DAVID WELLINGTON CHEW, Chief Justice.

Brownhawk, L.P. (“Brownhawk) appeals a breach of contract judgment in favor of Monterrey Homes, Inc. (Monterrey”) in the amount of $225,000, plus pre-judgment interest and attorney’s fees. In three issues, Brownhawk challenges the trial court’s findings of fact and conclusions of law and its attorney’s fees award.

In September 2007, Brownhawk, a real estate developer, and Monterrey, a residential construction company, entered into an agreement for Monterrey to purchase an unimproved tract of land in El Paso County for development of the “Dos Pal-mas” subdivision. The parties signed an earnest money contract for the property on September 21, 2006 (“the contract”). Monterrey agreed to pay $2,250,000 for the property, and Brownhawk agreed to convey the property to Monterrey including certain improvements which were to be completed by Brownhawk, in a “good workman-like manner” on or before May 31, 2007. The improvements were specified as follows: (1) Brownhawk would complete all earthwork and grading, as specified by the subdivision plan; (2) install all sidewalks, streets with curbs, and gutters; and (8) install all utilities as appropriate for a residential subdivision.

The contract contained a general termination or “default” provision which provided each party with the right to terminate the contract, seek specific performance, or seek other remedies as provided by law, for breach by the other party. In a separate section, the contract also gave Monterrey the right to terminate the contract and receive a full refund of the earnest money if Brownhawk failed to complete the improvements by the date specified. The contract also provided for the recovery of attorney’s fees for the prevailing party should a default lead to litigation.

Final closing on the improved property was scheduled to take place “on or before 15 days after completion of development.” Upon signing the agreement, Monterrey immediately deposited $25,000 into an escrow account. Later, in accordance with the contract, Monterrey deposited another $200,000 into escrow after the City of El Paso approved the preliminary subdivision plat. Over the next few months, the parties negotiated numerous changes to the configuration of the subdivision plat which required re-submission of the amended subdivision plat for the city’s approval. The city approved the change, but required the parties to install a “drainage flume” to accommodate the reduction.

With the newly approved subdivision plans approved, the parties signed an amendment to the contract to further specify their responsibilities prior to closing. The amendment, signed April 30, 2007, changed the property description to reference the updated subdivision plans approved by the city, and made several changes to the closing provisions. First, the amendment extended Brownhawk’s deadline for its initial construction obligations to May 30, 2007, with an automatic *344 forty-five day extension if Brownhawk was unable to meet the amended deadline. The amendment specified that closing would take place within fifteen days of “Completion of Development” and further specified that “Completion of Development” would occur when Brownhawk completed the following: (1) all earthwork and grading as required by the Developer/Builder plan (attached to the amendment as Exhibit A); (2) all streets with curbs and gutters and all sidewalks shown on the Developer/Builder Plan as “By Developer;” (3) all utilities for a residential subdivision as specified by the Developer/Builder Plan; and (4) all “By Developer” retaining walls according to the Developer/Builder Plan. Monterrey, in turn, took responsibility for construction of all rock or retaining walls between lots, all rock or retaining walls noted as “By Builder” on the Developer/Builder Plan, and construction of sidewalks along Dos Pal-mas Drive, also specified as “By Builder.” Monterrey agreed it was responsible for completing the “Builder’s Improvements” even if they were not completed by closing, and further agreed that closing would not be delayed in any way by its failure to complete those improvements. Finally, the amendment provides an additional termination provision for Monterrey. In the event Brownhawk was unable to complete its improvements by the extended completion date, Monterrey could terminate the contract by written notice to Brownhawk, or negotiate another extension. If Monterrey chose to terminate the contract, it was entitled to a refund of any remaining escrow funds, subject only to Monterrey’s decision to exercise its right to purchase certain lots prior to closing (Monterrey’s “Early Purchase Right”). The amendment does not specifically reference the drainage flume construction.

The parties never closed on the property. On September 12, 2007, Brownhawk filed suit against Monterrey for breach of contract, alleging that despite the completion of “virtually all” of its own construction obligations, Monterrey failed to complete construction of the “By Builder” projects, and prevented Brownhawk from securing a final inspection from the City of El Paso. Monterrey counter-claimed with its own breach of contract claim, alleging that Brownhawk failed to meet the extended completion deadline provided by the contract amendment, and that it had exercised its right to terminate the agreement by written notice sent to Brown-hawk on August 16, 2007.

The case was tried to the bench beginning on April 21, 2008. On April 80, 2008, at the close of evidence, the trial court ruled in favor of Monterrey on its counterclaim and awarded $225,000 plus interest and attorney’s fees. The trial court also awarded Monterrey $49,450 for attorney’s fees, with additional contingent awards in the event of Brownhawk’s unsuccessful appeals to this Court and the Texas Supreme Court. Following entry of the judgment, the court entered findings of fact and conclusions of law.

The following findings are key to the disposition of this appeal:

5. Time was of the essence under the Contract.
6. [Pursuant to the Amendment] ... Brownhawk was required to complete all the enumerated improvements no later than August 14, 2007 if the automatic extension was utilized. Time was again of the essence pursuant to the Contract Amendment.
[[Image here]]
8. [As of August 16, 2007] Brownhawk had not completed all the earth work *345 and grading, nor had Brownhawk completed all the sidewalks, curbs and gutters.
[[Image here]]
10. [0]n August 14, 2007 the subdivision could not have passed final inspection and would not have been accepted by the City of El Paso.
[[Image here]]
13. In a letter dated August 16, 2007, Monterrey sent notice to Brown-hawk electing to terminate the Contract. As part of the notice Monterrey demanded that Brown-hawk release the escrowed amount of $225,000.... Brownhawk refused.
14. Brownhawk alleged that pursuant to revised plans that were filed with the City that Monterrey was supposed to construct a flume for drainage prior to the subdivision final inspection.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
327 S.W.3d 342, 2010 Tex. App. LEXIS 8742, 2010 WL 4231524, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brownhawk-lp-v-monterrey-homes-inc-texapp-2010.