Brown v. McKinnon Bridge Co., Inc.

732 F. Supp. 1479, 1989 U.S. Dist. LEXIS 16940, 1989 WL 200235
CourtDistrict Court, E.D. Tennessee
DecidedSeptember 6, 1989
DocketCIV-3-88-0367
StatusPublished
Cited by4 cases

This text of 732 F. Supp. 1479 (Brown v. McKinnon Bridge Co., Inc.) is published on Counsel Stack Legal Research, covering District Court, E.D. Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brown v. McKinnon Bridge Co., Inc., 732 F. Supp. 1479, 1989 U.S. Dist. LEXIS 16940, 1989 WL 200235 (E.D. Tenn. 1989).

Opinion

MEMORANDUM OPINION

JORDAN, District Judge.

This is an action by the plaintiff Michael R. Brown to recover for serious injuries he sustained while working for the defendant McKinnon Bridge Company, Inc. (McKin-non Bridge) during the construction of a bridge across the Tennessee river in Knox County, Tennessee. The plaintiff brought claims under the Jones Act, 46 U.S.C. § 688 et seq., the Longshoresmen and Harbor Workers’ Compensation Act, 33 U.S.C. §§ 901, et seq. (LHWCA), as well as the general maritime law against McKinnon Bridge and under the Tennessee Products Liability Act, T.C.A. §§ 29-28-101, et seq., against the defendant Vimco, Inc. (Vimco), a Pennsylvania corporation, which manu *1481 factured the bolts and ties used to secure forms for pouring concrete bridge piers. [Doc. 1.] Both defendants have filed cross-claims for indemnity or contribution. [Docs. 7 and 8.] In addition, McKinnon Bridge’s motion to assert a pendent counterclaim against the plaintiff to determine his workers’ compensation benefits under Tennessee law [Docs. 20, 20A] has been granted by this Court. [Doc. 43.] 1 Trial of this action is currently set for Monday, October 16, 1989.

Presently, several dispositive motions are pending before the Court. McKinnon Bridge has filed a motion for summary judgment on Yimco’s crosselaim. [Docs. 19, 19A.] 2 McKinnon Bridge has also filed a motion to dismiss the plaintiff’s claim under the LHWCA for lack of subject-matter jurisdiction. [Docs. 26, 26A, 53.] The plaintiff has filed his response, conceding that the Court does not have jurisdiction pursuant to the provisions of 33 U.S.C. § 919 because he did not first pursue an administrative claim; however, he continues to assert an original claim under § 905(b) of the LHWCA. [Docs. 32, 32A.] As part of his motion to withdraw his answer and to dismiss McKinnon Bridge’s workers’ compensation counterclaim [Docs. 33, 33A], the plaintiff states that should this Court determine that he is not a seaman under the Jones Act, he anticipates filing an administrative claim under the LHWCA. In regard to the claims under the Jones Act and general maritime law, cross-motions for partial summary judgment have been filed by the plaintiff [Docs. 29, 30, 31, 36, and 54] and McKinnon [Docs. 39, 39A, and 55]. The Court now addresses all dispositive motions except McKinnon Bridge’s motion for summary judgment on Vimco’s crossclaim and the plaintiff’s motion to withdraw his answer and to dismiss McKinnon Bridge’s counterclaim.

I. Facts

The material facts are essentially undisputed. The plaintiff was severely injured in the course and scope of his employment on July 22, 1987, when the forms used to pour concrete for a web wall on a bridge pier collapsed on top of him. The plaintiff first started working periodically for McKinnon Bridge in the early 1970’s and was hired as a laborer on various projects; he eventually became classified as a carpenter. [Brown deposition, at p. 16, lines 22-25 through p. 18, lines 1-22.] When McKinnon Bridge constructs a bridge across a body of water, it apparently maintains two crews that may be referred to as a land crew and a water crew. [Id., at p. 22, lines 5-15.] The water crew worked on piers in the water; [Id., at p. 23, lines 23-25 through p. 24, lines 1-12.]

At the time of the accident, the plaintiff had been working on one of the piers in the water. [Id., at p. 25, lines 7-14.] The pier was constructed within a cofferdam placed around the site of the pier from which the water was pumped to create a dry hole in the river. [Id., at p. 42, lines 20-25 through p. 43, lines 1-3.] While the cofferdam was being put in place and the site prepared for construction, which took two-to-three weeks to complete, workers would construct the metal forms for pouring the concrete pier. Much of this work was done on barges in the river. [Gary Dick deposition, at p. 9, lines 16-22; James Beecham deposition, at p. 15, lines 5-14; Darrel J. Rogers deposition, at p. 7, lines 24-25 through p. 8, lines 1-5, 18-23; affidavit of Michael R. Brown.] The barges were anchored by various means and were used as construction platforms. [Brown deposition, at p. 34, lines 2-25 through p. 39, lines 1-15.]

Once the cofferdam was in place and sealed, laborers descended into the interior to construct the forms for pouring the pier. They had to ascend routinely to the barges for supplies and materials. [Id., at p. 43, lines 4-25 through p. 45, lines 1-3; Rogers deposition, at p. 8, lines 15-18 and at p. 10, *1482 lines 10-21.] The forms were bolted together, secured by cables, and then concrete was poured into them in progressive stages over the course of a day. [Brown deposition, at p. 45, lines 3-25 through p. 46, lines 1-22; p. 50, lines 14-23.] On this particular project, a web wall or retaining wall was constructed around the pier to connect it with another pier. [Id., at p. 52, lines 8-13.] The metal forms for the web wall were constructed in a similar manner as those for the piers. [Id., at p. 57, lines 20-25 through p. 58, lines 1-5.] During the assembly of the forms for one of these web walls, the form collapsed and resulted in injuries to the plaintiff. 3

In addition to the plaintiffs duties involving the construction of the cofferdam and working on the metal forms, he also vibrated air pockets out of the concrete as it was poured [Id., at p. 48, lines 22-25 through p. 50, lines 1-13], and flagged for the crane [Id., at p. 47, lines 22-25 through p. 48, lines 1-16]. The plaintiff was a member of the water crew at the time of the accident. [Affidavit of Michael R. Brown; Brown deposition, at p. 22, lines 18-24.] The plaintiffs duties sometimes required him to clean the barges and equipment on the barges, to assist in tying up the barges, to handle lines, to help to anchor the barges with spuds, and to tie the barges off when moved. [Dick deposition, at p. 7, lines 10-25 through p. 8, lines 1-18; Rogers deposition, at p. 7, lines 19-23.] The workers were transported to the barges by a tug or other type of boat. [Dick deposition, at p. 8, lines 19-22; Beecham deposition, at p. 14, lines 4-9.] The plaintiff would often eat the lunch he brought with him from home on a barge or on the tug boat. [Brown deposition, at p. 73, lines 12-18; Beecham deposition, at p. 14, lines 10-24.] He did not sleep on a barge, however, and went home every day. [Brown deposition, at p. 72, line 25 through p. 73, lines 1-5.] Although the tugs were equipped with living quarters, the barges had no crew quarters or kitchen facilities. [Id., at p. 73, lines 6-11.] Nevertheless, a substantial portion of the plaintiffs work was performed on several of the barges. [Affidavit of Michael R. Brown.]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Corman Marine Const. v. McGeady
Court of Special Appeals of Maryland, 2024
Polak v. Riverside Marine Construction, Inc.
22 F. Supp. 3d 109 (D. Massachusetts, 2014)
In Re Williams Marine Construction & Services, Inc.
350 F. Supp. 2d 975 (M.D. Florida, 2004)
Reecer v. McKinnon Bridge Co.
745 F. Supp. 485 (M.D. Tennessee, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
732 F. Supp. 1479, 1989 U.S. Dist. LEXIS 16940, 1989 WL 200235, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brown-v-mckinnon-bridge-co-inc-tned-1989.