Brown v. Maryland Casualty Company

442 S.W.2d 187, 246 Ark. 1074, 1969 Ark. LEXIS 1347
CourtSupreme Court of Arkansas
DecidedMay 26, 1969
Docket5-4723
StatusPublished
Cited by9 cases

This text of 442 S.W.2d 187 (Brown v. Maryland Casualty Company) is published on Counsel Stack Legal Research, covering Supreme Court of Arkansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brown v. Maryland Casualty Company, 442 S.W.2d 187, 246 Ark. 1074, 1969 Ark. LEXIS 1347 (Ark. 1969).

Opinions

John A. Fogleman, Justice.

The Housing Authority of Pike County, Arkansas, contracted with Plez Lewis & Son, Inc., for the construction of a housing project according to plans and specifications prepared by architect Stanley Brown. After Plez Lewis defaulted, the housing authority called upon Maryland Casualty Company, surety on the contractor’s performance bond, to complete the contract. Maryland contracted with Con-Ark Builders, Lie., to complete the construction in accordance with the original plans. Apparently, it was contemplated that a change would b.e made in the plans and specifications as to foundations, because mention of this was made in the contract between Maryland and Con-Ark. After Con-Ark. took over, “Change Order Gf-2” was added requiring the installation of 124 piles, a minimum of ten feet in length or a total of 1,240 lineal feet. Con-Ark’s proposal to Maryland had contained an item of $6,500 for this work plus $4.75 per foot in excess of 1,240 feet. Con-Ark subcontracted this work to Piling & Repairs, Inc., for $5,084 plus $3.85 for each additional lineal foot. After the piling work started,' R. W. Laird, the architect’s representative on the job site, instructed Piling & Repairs’ workmen to drill the pilings deeper than the originally specified ten feet. Accordingly, this resulted in an additional 1,268 lineal feet of drilling over the original specification of 1,240 lineal feet.

Piling & Repairs, who had been paid by Con-Ark for a portion of the overrun, brought suit against Con-Ark for the balance due on the overrun. Con-Ark admitted the overrun and cross-complained against Maryland Casualty Company on Lhe premise that should Con-Ark be liable to Piling & Repairs, Con-Ark should have judgment against Maryland. Maryland then cross-claimed against the housing authority and Stanley Brown and R. W. Laird seeking judgment against them, jointly and severally, for any amount for which it was held liable.

At the trial it was stipulated that Stanley Brown was the housing authority’s agent and that Laird was Brown’s agent.

The trial court entered judgment for Piling & Repairs against Con-Ark as prayed, for Con-Ark against Maryland Casualty Company as prayed, and for Maryland against the housing authority, Stanley Brown and R. W. Laird, jointly and severally, for anything Maryland might be required to pay to satisfy the judgment in favor of Con-Ark. Brown and Laird filed notice of appeal. Con-Ark gave notice of appeal from the judgment in favor of Piling & Repairs. The appeal by the housing authority was designated as a cross-appeal in the sense used in Ark. Stat. Ann. § 27-2106 (Repl. 1962), Brown v. Maryland Casualty Co., 245 Ark. 70, 431 S.W. 2d 258. Maryland also appealed.

Maryland contends that it is not liable to Con-Ark unless and until it is paid for the extra work by the housing authority and its architect. tinder the terms of the contract between Con-Ark and Maryland allowance of the amount to be paid by the owner was a condition precedent to payment from Maryland to Con-Ark. The pertinent contract portions are as follows:

“7. Maryland agrees to pay the Contractor, as full compensation for all liability assumed hereunder, the sum of $109,500.00, subject to additions and deductions residting from change orders or extras issued by the Owner, to be paid as follows:— a. The sum of $101,729.83, being the balance of the Contract price remaining under tlie said Contract between Lewis and the Owner, out of the estimate and retained percentages to be received by Maryland from the Owner periodically, as provided for in the Contract, between Lewis and the Owner, for work performed by the Contractor, and to be paid to the Contractor within five (5) days after receipt thereof by Maryland, such payment to be in like amounts as Maryland receives from the Owner.
b. The additional sum of $7,770.17 * * *
c. Within five (5) days after receipt by Maryland from the owner of any payment to it for extra work ordered, including but not limited to contemplated change in foundations, on or after the effective date of this AGREEMENT and performed by the Contractor, Maryland mil make payment of an amount equal to the amount received by Maryland from the Owner for the aforesaid extra toork.
d. Within five (5) days after the Owner notified Maryland in writing that the Contract has been completed and accepted and the Owner has paid the final estimate and retained percentage to Maryland, then Maryland will pay to the Contractor the balance due under this AGREEMENT, if any. It is distinctly understood and agreed by the parties hereto that the payments provided for hereunder are to be made only after Maryland receives from the Owner the estimate payments, payments for extras and changes, and retainages to be paid to Maryland by the Owner and Lewis. It is further understood- and agreed that the payments shall, in no event, exceed the sum of $109,500.00, subject to any additions or deductions provided, for hereunder. . Any change or increase in the amount of this AGREEMENT hereinafter provided for shall he paid to the Contractor only in such amount as is allotved therefor by the Owner, anything in this AGREEMENT to the contrary notwithstanding.
It is understood that the payments provided for as above are to be made only after Maryland receives from the Owner the estimate payments, the payments for extras and changes, and retainages to be paid Maryland by the Owner under the terms of its Contract with Lewis, provided, however, that should the Owner withhold any estimate payment, payment for extras, or retainage for a period of twenty (20) days beyond the time it would normally be paid because of any reason not the fault of the Contractor, then Maryland shall nevertheless make payment to the Contractor for any such estimate, extra, or retainage earned by the Contractor and without awaiting payment from the Owner, as provided for in subparagraphs a, b, and c; provided further, however, that should the Owner withhold any payment herein referred to for a period of twenty (20) days beyond the time it would normally be paid, for reasons not the fault of the Contractor, then Maryland shall have the right to cancel this AGREEMENT upon notice to the Contractor. In the event of such cancellation, the Contractor shall be entitled to payment from Maryland for all amounts earned by the Contractor, including retain-age under this AGREEMENT, up to the date of cancellation.” (Emphasis ours.)

It is obvious that all parties knew that this was an undertaking to complete a job on which the original contractor had defaulted. Con-Ark was Maryland’s subcontractor for the completion of the work. There is no reason -why the parties could not contract for this work on any terms they agreed upon. There is no reason wl\y the terms of the contract which both parties agreed to should not be enforced.

In Blair v. United States, 147 F. 2d 840 (8th Cir. 1945), there was a contract between a contractor and a subcontractor which contained provision's very similar to those in this case. A fixed completion date in the contract between the government and Blair, the general contractor, had been extended.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Schmidt v. Stearman
253 S.W.3d 35 (Court of Appeals of Arkansas, 2007)
Pickell v. Guaranty National Life Insurance Co.
917 S.W.2d 439 (Court of Appeals of Texas, 1996)
Waldron Metal Recycling Co. v. Meuser
679 S.W.2d 217 (Court of Appeals of Arkansas, 1984)
Peek v. Meadors
500 S.W.2d 333 (Supreme Court of Arkansas, 1973)
Arnold v. All American Assurance Co.
499 S.W.2d 861 (Supreme Court of Arkansas, 1973)
Brown v. Maryland Casualty Company
442 S.W.2d 187 (Supreme Court of Arkansas, 1969)

Cite This Page — Counsel Stack

Bluebook (online)
442 S.W.2d 187, 246 Ark. 1074, 1969 Ark. LEXIS 1347, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brown-v-maryland-casualty-company-ark-1969.