Brown v. First Federal Sav. & L. Ass'n of Great Falls

460 P.2d 97, 154 Mont. 79, 1969 Mont. LEXIS 347
CourtMontana Supreme Court
DecidedOctober 23, 1969
Docket11456
StatusPublished
Cited by16 cases

This text of 460 P.2d 97 (Brown v. First Federal Sav. & L. Ass'n of Great Falls) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brown v. First Federal Sav. & L. Ass'n of Great Falls, 460 P.2d 97, 154 Mont. 79, 1969 Mont. LEXIS 347 (Mo. 1969).

Opinion

MR. JUSTICE CASTLES

delivered the Opinion of the Court.

This is an action brought for the breach of a contract. The court made findings of fact and conclusions of law in favor of the respondent, the First Federal Savings & Loan Association of Great Falls. A motion by the appellants, Curtis L. and Helen M. Brown, for an amendment to the findings and conclusions was denied and this appeal followed.

The appellants had purchased some unimproved lots in Helena in 1957 and later obtained plans for a proposed home. After finding that a contractor named Seely was constructing homes in the area, the appellants entered into an oral agreement with him to build their residence for $17,495 less certain credits. There was a long waiting list for direct Veterans Administration loans at the time and the Browns found that Helena banks were not equipped to handle VA guaranteed loans. Upon the suggestion of an acquaintance, the appellants went to the respondent association in Great Falls. Due to a number of delays on the part of Seely, the loan was not approved by the respondent until July 7, 1958. Before this, on June 25, the Browns entered into a written agreement with Seely. There were additional delays and the various documents closing the loan were not sent to Helena until September 9, 1958.

The construction loan agreement called for a payment by the appellants to respondent of $4,028.50 and a mortgage loan by the respondent of $13,500. In addition, the Browns made an advance of $123.50 to the respondent for VA appraisal fees and title insurance premiums.

On August 13 the Veterans Administration issued its First Compliance Inspection Report showing satisfactory work through the first stage of construction. Under the loan agree *82 ment this report entitled Seely to a distribution of $2,600 upon receipt of other papers required by the respondent. On September 19, Seely delivered an affidavit to the respondent stating there were no unpaid bills other than a lumber bill of about $720. The respondent association transmitted the $2,600 to Seely on October 2, 1958 without requiring that waivers of priority of lien forms be signed and returned.

Thereafter the Browns experienced difficulty with Seely. The respondent received the VA’s Second Compliance Inspection Report after November 19, and on November 25, respondent wrote Seely that he would be entitled to a second disbursement when he sent in an affidavit listing all unpaid bills and when the lien waivers had been signed and returned. Around December 1, 1958 the appellants discovered that Seely was in financial trouble and Seely stated definitely the Browns would would not be in their home by Christmas as originally agreed upon. The appellants requested that the respondent make no more payments to Seely and the respondent asked the Browns to get a list of unpaid bills.

In the period before December 8, the Browns contemplated changing contractors. It was learned the original affidavit was in fact false, there being some $2,000 in unpaid bills as of September 19. Although demands were made neither the second affidavit nor the lien waiver forms were ever returned. The Browns ascertained that as of December 11, there were outstanding bills in the amount of $6,256.37.

On December 9, the respondent wrote Seely to have all bills paid and evidence of payment returned by December 12 and further, to do no more work on the project until so directed. No one in this action saw Seely again or in any way heard from him although both parties attempted to communicate with him.

Before December 16, the respondent requested the Browns to get an estimate on completion of the home from L. P. Barney, a Helena contractor. The Browns decided upon competitive bidding and informed the respondent. The president of respond *83 ent association, P. C. Bulen, came to Helena and met with the Browns, their attorney, and representatives from the three bidders. Following Mr. Bulen’s visit the Browns wrote respondent that their attorney was straightening things out for them and they had not yet selected a new contractor.

The respondent and the appellants agreed that the first mortgage payment due on January 1, 1959 would be extended and the Browns need only make payment upon the principal. Mrs. Brown sent a check for $16.99, principal payment on January 2, but the second payment due February 1, 1959 was not paid. The Browns, upon their request, received a balance sheet from the respondent during this period.

A letter was also sent by the respondent to the Browns suggesting the possibility of a conventional loan, but no reply was received. On December 26, Mr. Bulen again came to Helena and saw Mr. Brown and his attorney but obtained no information relating to financing the project, retaining or terminating Seely, or employing a new contractor.

On February 5, 1959 the respondent wrote to the Browns sending the mortgage, a release of mortgage, various other papers and a check for $1,988.93. The check was presented and paid and the release of the mortgage was recorded. Some four and a half years later this action was commenced.

The issues presented for review are: (1) Whether the respondent breached the contract; (2) Whether the respondent had the right to cancel the contract and (3) Whether the respondent breached a fiduciary obligation giving rise to a cause of action.

The appellants assert the respondent breached the construction loan agreement in four ways: (a) by not requiring lien waivers before the first disbursement; (b) by not exercising due care in the disbursement; .(c) by not maintaining sufficient funds for the completion of the contract; and (d) by canceling the contract.

First of all, the original agreement between the Browns and Seely does not require any sort of lien waivers. The construction *84 loan agreement, in setting out the disbursement schedule, provides :

‘ ‘ Course of Construction disbursements are to be made in the following amounts at the times noted, upon furnishing of Waivers of Priority of Lien Rights and Final Lien Waivers as required by lender.”

The appellants contend that the waivers of priority were a condition to payment and the phrase “as required by the lender” refers to the type of waivers to be furnished so that an ambiguity is created; and therefore, this ambiguity should be resolved against the respondent. When a matter in a contract is left to the determination of one party alone, that party’s determination is conclusive if he acts in good faith. McCrimmon v. Murray, 43 Mont. 457, 469, 117 P. 73; Waite v. Shoemaker & Co., 50 Mont. 264, 287, 146 P. 736. Furthermore, any dispute as to the meaning of the phrase was resolved by the district court’s finding that the matter of requiring waivers of priority is left to the respondent’s discretion and is not a condition to payment.

On July 1, the respondent wrote the appellants that the waivers of priority would not be required until the second disbursement; when the papers were sent for signature the respondent asked that the waivers be signed before the first disbursement; but on September 18 the respondent again told the appellants that the waivers need not be signed until a later time.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Estate of Strever v. Cline
924 P.2d 666 (Montana Supreme Court, 1996)
Arrow Const. Co., Inc. v. Camp
827 P.2d 378 (Wyoming Supreme Court, 1992)
Federal Land Bank of Spokane v. Snider
808 P.2d 475 (Montana Supreme Court, 1991)
Billings Clinic v. Peat Marwick Main & Co.
797 P.2d 899 (Montana Supreme Court, 1990)
Cheney v. Jemmett
693 P.2d 1031 (Idaho Supreme Court, 1984)
Bronken's Good Time Co. v. J. W. Brown & Associates
661 P.2d 861 (Montana Supreme Court, 1983)
E. F. Matelich Construction Co. v. Goodfellow Bros.
645 P.2d 391 (Montana Supreme Court, 1982)
Town Pump, Inc. v. Diteman
622 P.2d 212 (Montana Supreme Court, 1981)
Marvin v. Hargrave
618 P.2d 339 (Montana Supreme Court, 1980)
Smith v. Zepp
567 P.2d 923 (Montana Supreme Court, 1977)
STC, INC. v. City of Billings
543 P.2d 374 (Montana Supreme Court, 1975)
Phalen v. Rilley
496 P.2d 295 (Montana Supreme Court, 1971)

Cite This Page — Counsel Stack

Bluebook (online)
460 P.2d 97, 154 Mont. 79, 1969 Mont. LEXIS 347, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brown-v-first-federal-sav-l-assn-of-great-falls-mont-1969.