Brown v. CONOCOPHILLIPS PIPELINE CO.

271 P.3d 1269, 47 Kan. App. 2d 26
CourtCourt of Appeals of Kansas
DecidedFebruary 28, 2012
Docket104,280
StatusPublished
Cited by11 cases

This text of 271 P.3d 1269 (Brown v. CONOCOPHILLIPS PIPELINE CO.) is published on Counsel Stack Legal Research, covering Court of Appeals of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brown v. CONOCOPHILLIPS PIPELINE CO., 271 P.3d 1269, 47 Kan. App. 2d 26 (kanctapp 2012).

Opinion

Brazil, J.:

This appeal concerns the fate of a large oak tree on the property of Lonzella Brown. The appellant, ConocoPliillips Pipeline Company (Conoco), owns an easement giving it the right to “lay, maintain, operate, inspect and remove” its high-pressure gasoline pipeline which runs through Brown’s property. The pipeline was laid in the 1960s, and since that time the tree has sprung up above the pipeline. In 2009, Conoco sought to cut down the tree on the basis that it interfered with its ability to maintain and inspect the pipeline. Brown eventually obtained a permanent injunction preventing Conoco from removing the tree unless an emergency arose. On appeal, Conoco argues that the court erred in finding that the tree did not constitute a material obstruction to their easement. We vacate the injunction and remand.

Conoco owns a 10" high-pressure gasoline pipeline which runs from Paola to Wyandotte County. The pipeline passes through Brown’s property in Wyandotte County. The pipeline was laid in 1963 by Conoco’s predecessor, Phillips Petroleum Company (Phillips). That same year, Phillips purchased an easement from the people who owned tire property at the time. The easement gen *29 erally describes the area on the property where the pipelines were to be laid but did not expressly specify the width, length, or location of Phillips’ rights for ingress and egress. The agreement merely stated that Phillips had the right to “lay, maintain, operate, inspect and remove” the two pipelines on the property. Otherwise, the landowners were vested with the right to “fully use and enjoy said premises except for the purposes hereinabove granted.” The easement was recorded with the Wyandotte County Register of Deeds in 1963. The pipeline has been used continuously since being constructed.

When Brown bought the property in 2000, the tree in question was already present. The tree is a 30-year-old pin oak and is 60' to 70' tall. Conoco began a tree-clearing project along the 53-mile route of the pipeline from Paola to Wyandotte County. Conoco removed a number of trees in the course of its tree-clearing project. In October 2009, Conoco informed Brown that it needed to remove the tree. Brown refused to allow Conoco to do so. Brown filed a petition for injunctive relief in Wyandotte County District Court seeking to enjoin Conoco from entering her land and cutting the tree down. Brown subsequently obtained a temporaiy restraining order against Conoco. Conoco counterclaimed breach of contract against Brown and for a declaratory judgment confirming its right to remove the tree.

The case proceeded to a hearing before the district court on February 9, 2010. Brown testified that she did not want to lose the tree because it is the only tree in her backyard, it shades her house and yard, and her granddaughter likes to play under it. She called a horticulturist, Phillip Hogan, as an expert, who testified that 80% or 90% of the tree’s roots were located within 3 feet of the surface. Hogan testified that tree roots take the path of least resistance, meaning that if they ran into the pipeline, they would go around it because soil is softer than the pipe. He testified that while the top of a tree moves with the wind, tree roots are stable and do not move. Hogan valued the tree at $12,000. However, in making this valuation, Hogan did not take the easement into consideration. He estimated that if the tree was cut down and a new one planted, *30 Brown would be over 90 years old before the replacement tree would reach the current tree’s size.

On cross-examination, Hogan admitted the tree’s roots could extend over and across the pipeline if the pipeline was located within the first 3 or 4 feet of the ground’s surface. He conceded that the pipeline could be damaged by the tree’s roots if the pipeline is located close to the surface within a few feet of the tree, much in the same way that tree roots can damage a house’s foundation if the house is too close to a tree. He also admitted he did not know the depth at which the pipeline had been buried nor did he know the pipeline’s location in relation to the tree. Finally, Hogan admitted he knows nothing about gas pipelines or the safety concerns related to pipelines and tree roots.

Conoco called Michael Kemp, a claims consultant, and Todd Tullio, a regulatory compliance planning manager. Both Kemp and Tullio testified that the pipeline was located about 1 or 2 feet from the edge of the tree. Tullio was unsure of the precise depth at which the pipe had been buried in 1963 but estimated its present location was less than 36" under the ground’s surface. Tullio testified that the close proximity of the tree to the pipeline could damage the pipeline because the roots could rub the pipeline’s protective coating off, causing the pipe to corrode. Tullio explained that the pipeline moves when gasoline is being pumped through it and that the sustained friction between the pipeline and the roots could lead to the loss of the protective coating. The resulting corrosion of the pipeline could lead to a number of different problems, including large or small gasoline leaks, pipeline ruptures, environmental impacts, or possibly an explosion. He also presented pictures showing the effects tree roots can have on pipelines.

Tullio testified that if there were problems with the pipeline on Brown’s property, Conoco would be unable to excavate around the pipeline until die tree was cut down because of safety concerns and the inability to access the pipeline due to its close proximity to the tree. He estimated Conoco would be delayed from immediately accessing the pipeline by “at least a couple of days.”

He further testified that the tree also impeded Conoco’s ability to maintain the pipeline because it interfered with pipeline in *31 spections mandated by federal regulations. Federal guidelines require Conoco to aerially inspect its pipelines 26 times per year. Conoco contracts with an aerial company which navigates the pipeline’s route and looks for a variety of things, including dead vegetation, debris, people digging or planting vegetation, and tire like. If federal auditors detect shrubs or trees that prevent them from examining the pipelines, they can serve the pipeline company a notice of probable violation (NOPV), which gives the company 160 days to clear the right-of-way or face a fine. Tullio explained by way of example that Conoco had received a NOPV on a different pipeline in 2008. He testified that the efforts to remove Brown’s tree were motivated in part by Conoco’s desire to prevent it from receiving an NOPV. However, Conoco has not received an NOPV because of the tree at this time.

In addition to the aerial inspection done eveiy 2 weeks, Conoco also inspects its pipelines once every 5 years by using “smart pigs,” which are electronic devices that run through the pipelines to detect depth, wall thickness, dents, or other anomalies. The most recent smart-pig test of the Paola/Wyandotte County pipeline revealed 74 anomalies, which Conoco addresses by excavating down to the pipeline and repairing the problem. Conoco addresses problems in order of their seriousness, with all problems attended to within 1 year of their detection.

After the close of the hearing, the district court took the case under advisement. On March 16, 2010, the district court issued its decision in a memorandum opinion.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Drouhard v. City of Argonia
551 P.3d 156 (Court of Appeals of Kansas, 2024)
Beck v. City of Blue Rapids
Court of Appeals of Kansas, 2022
1400 Museum Park Condominium Ass'n v. Kenny Construction Co.
2021 IL App (1st) 192167 (Appellate Court of Illinois, 2021)
Legato v. City of Olathe
Court of Appeals of Kansas, 2021
Sewell and Lawson
Court of Appeals of Kansas, 2021
Roll v. Howard
480 P.3d 192 (Court of Appeals of Kansas, 2020)
Cent. Kan. Conservancy, Inc. v. Sides
443 P.3d 337 (Court of Appeals of Kansas, 2019)
Garn v. Higgins
Court of Appeals of Kansas, 2019
GBRB Properties, LLC v. Hill
Court of Appeals of Kansas, 2019
Digital Office Systems, Inc. v. Bleier
Court of Appeals of Kansas, 2018
Hunter Health Clinic v. Wichita State University
362 P.3d 10 (Court of Appeals of Kansas, 2015)
Garetson Brothers v. American Warrior, Inc.
347 P.3d 687 (Court of Appeals of Kansas, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
271 P.3d 1269, 47 Kan. App. 2d 26, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brown-v-conocophillips-pipeline-co-kanctapp-2012.