Brower Co. v. Garrison

468 P.2d 469, 2 Wash. App. 424, 1970 Wash. App. LEXIS 1144
CourtCourt of Appeals of Washington
DecidedApril 20, 1970
Docket272-40713-1
StatusPublished
Cited by15 cases

This text of 468 P.2d 469 (Brower Co. v. Garrison) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brower Co. v. Garrison, 468 P.2d 469, 2 Wash. App. 424, 1970 Wash. App. LEXIS 1144 (Wash. Ct. App. 1970).

Opinion

Swanson, J.

Henry W. Batts and wife, doing business as Batts Construction Co. (Batts), as general contractor, agreed to construct a truck sales and service building for Kenworth Northwest Sales & Service, Inc. (Kenworth). After construction of the facility was completed, The Brower Co., a subcontractor, brought a lien foreclosure action against Kenworth, the owner of the property, Batts, the general contractor, and other subcontractors, including United Plumbing & Heating, Inc. (United). United cross claimed to foreclose its lien claim for an alleged balance due on its subcontract. Kenworth then brought a separate action against Batts and its surety. It sought damages in excess of $425,000 claiming poor construction, real estate depreciation, and delayed performance damages. Batts counterclaimed seeking foreclosure of its lien claim of $81,209.01. These actions were consolidated for trial. The subcontractors’ lien claims were settled during the course of the trial, and none are appealed from. United is the only subcontractor involved in an issue on this appeal. Batts received a judgment against Kenworth for $81,209.01, less a setoff to Kenworth for damages for deficiencies in the construction of the building and for loss of profits caused by Batts’ failure to substantially complete the building within a reasonable time. The setoff totaled $79,811.50, thus netting Batts only $1,397.51. Batts has not appealed from that part of the judgment relating to deficiencies in construction but appeals from certain of the amounts allowed Kenworth as a setoff and the insufficiency of a setoff awarded Batts against United.

*426 Four separate areas of dispute are raised by the appeal and cross-appeal, as follows:

(1) The award of a setoff to Kenworth of approximately $14,000 against Batts for loss of profit caused by Batts’ delay in completing the building within a reasonable time.

(2) The award of a setoff to Batts of $2,900 against United, the amount being based upon the portion of the responsibility the trial court felt United had in causing the delay in the completion of the building. Batts claims the amount set off should have been $9,600.

(3) The award to Batts of a $1,500 attorneys’ fee. Respondent Kenworth cross-appeals and claims that Batts did not in fact receive a net judgment and, even if it did, the court abused its discretion in awarding an attorneys’ fee larger than the amount of the net judgment.

(4) The rejection of Batts’ claim for a 15 per cent markup on all change orders, including work performed by the subcontractors wherein a 15 per cent markup was included within their change order figure. This involves a claim of approximately $5,577.

To place these questions in their proper perspective necessitates a somewhat detailed account of the transaction.

Kenworth was incorporated when Kenworth Motor Truck Corporation announced it was going to separate the sales and service of trucks in the Seattle area from its manufacturing operation. Kenworth was awarded the distributorship and, in preparation for taking over this business operation, had certain plans and specifications prepared for the construction of a sales and service building. Kenworth issued a call for bids which were to be tendered on forms supplied by its architect. The instructions to bidders said that “consideration will be given to both the dollar amount and the completion time.” The bid form contained a clause reading, “The Undersigned, agrees if awarded the contract for the work, to substantially complete the work within............consecutive calendar days after notice to proceed is received.” The specifications issued to *427 prospective contractors provided, that the general conditions of the contract were to be controlled by The American Institute of Architects’ document A-201. 1 The architect also added supplementary conditions which were to control when in conflict with the general conditions. The appellant Batts submitted the winning bid and in it agreed to substantially complete the construction within 160 consecutive calendar days after receiving notice to proceed.

The owner-contractor agreement contained a specific article dealing with the time of completion, but no completion time was inserted. The article was left blank. The court found the contract did not provide for a fixed completion date. Finding 7. The trial court further determined, pursuant to the authority of Robinson v. Davis, 158 Wash. 556, 559, 291 P. 711 (1930), that where no time of performance is specifically agreed upon, a reasonable time for performance under the circumstances will be by the law presumed as intended by the parties to the contract. The court then stated in finding 9:

Under the circumstances which prevailed at the time of the execution of the Contract and taking into consideration all the evidence regarding the conditions and events which occurred during the performance of the contract, a reasonable time by which Batts should have substantially completed the facility was February 15,1967.

Thus, the initial question we must review is whether the construction contract contained an established completion date. Batts bases its argument that the contract did contain a fixed completion date on the terms of the accepted bid. It contends that the accepted bid which is described as a contract document in the contract itself must be a part of the contract. The contract’s supplementary condition article 1 (a) modifying the general conditions states:

“Contract Documents” consist of: (A) Accepted Bid, (B) General Conditions, (C) Supplementary General Conditions, (D) Agreement, (E) Specifications, and *428 (F) Drawings. Items (B) to (F) inclusive shall form the contract.

Batts argues that if the accepted bid is a contract document it must be part of the contract, and since the bid sets forth the specified number of days for completion, the court erred in disregarding that portion of the contract. In making this argument, Batts ignores the sequence of events. The accepted bid did, indeed, specify 160 days as the time within which the work was to be completed; however, the agreement contained a specific article dealing with time of completion:

Article 2. Time of Completion

The work to be performed under this Contract shall be commenced and completed as follows:

However, nothing was either typed or written below this heading. But the contract itself provides the answer to the intention of the parties, for the contract’s supplementary condition 1 (a), supra, indicates that the accepted bid, though a contract document, is not part of the contract. This is a clear indication that the parties intended that the accepted bid should merge into the contract and lose its separate existence apart from the agreement itself. The Supreme Court discussed the question of merger in Dix Steel Co. v. Miles Constr., Inc., 74 Wn.2d 114, 119, 443 P.2d 532 (1968):

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Burgess Vineyards, LLC v. Paul Beveridge, et ux dba
Court of Appeals of Washington, 2015
Watson v. Ingram
881 P.2d 247 (Washington Supreme Court, 1994)
Wallace Real Estate Investment Inc. v. Groves
881 P.2d 1010 (Washington Supreme Court, 1994)
Perini Corp. v. Greate Bay Hotel & Casino, Inc.
610 A.2d 364 (Supreme Court of New Jersey, 1992)
Aubrey v. Angel Enterprises, Inc.
717 P.2d 313 (Court of Appeals of Washington, 1986)
Walter Implement, Inc. v. Focht
709 P.2d 1215 (Court of Appeals of Washington, 1985)
Knight, Vale & Gregory v. McDaniel
680 P.2d 448 (Court of Appeals of Washington, 1984)
Stonebraker v. Zinn
286 S.E.2d 911 (West Virginia Supreme Court, 1982)
Northwest Acceptance Corp. v. Hesco Construction, Inc.
614 P.2d 1302 (Court of Appeals of Washington, 1980)
Coast Trading Co. v. Parmac, Inc.
587 P.2d 1071 (Court of Appeals of Washington, 1978)
S. L. Rowland Construction Co. v. Beall Pipe
540 P.2d 912 (Court of Appeals of Washington, 1975)
Mahoney v. Tingley
520 P.2d 628 (Court of Appeals of Washington, 1974)
Long v. T-H Trucking Co.
486 P.2d 300 (Court of Appeals of Washington, 1971)

Cite This Page — Counsel Stack

Bluebook (online)
468 P.2d 469, 2 Wash. App. 424, 1970 Wash. App. LEXIS 1144, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brower-co-v-garrison-washctapp-1970.