Broadway Concrete Invests., L.L.C. v. Masonry Contracting Corp.

2022 Ohio 19
CourtOhio Court of Appeals
DecidedJanuary 6, 2022
Docket110420
StatusPublished
Cited by2 cases

This text of 2022 Ohio 19 (Broadway Concrete Invests., L.L.C. v. Masonry Contracting Corp.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Broadway Concrete Invests., L.L.C. v. Masonry Contracting Corp., 2022 Ohio 19 (Ohio Ct. App. 2022).

Opinion

[Cite as Broadway Concrete Invests., L.L.C. v. Masonry Contracting Corp., 2022-Ohio-19.]

COURT OF APPEALS OF OHIO

EIGHTH APPELLATE DISTRICT COUNTY OF CUYAHOGA

BROADWAY CONCRETE : INVESTMENTS, L.L.C., : Plaintiff-Appellee, No. 110420 : v. : MASONRY CONTRACTING CORP., ET AL., :

Defendants-Appellants. :

JOURNAL ENTRY AND OPINION

JUDGMENT: AFFIRMED IN PART; REVERSED AND REMANDED IN PART RELEASED AND JOURNALIZED: January 6, 2022

Civil Appeal from the Cuyahoga County Court of Common Pleas Case No. CV-18-903809

Appearances:

Stark & Knoll Co., L.P.A., Michael L. Fortney, Alexandra N. Nienaber, and Richard P. Schroeter, Jr., for appellee.

The Law Offices of David M. Leneghan, David M. Leneghan, K. Scott Carter, and Catana Chrostowski, for appellants. KATHLEEN ANN KEOUGH, P.J.:

Defendants-appellants, Mason Contracting Corp. (“MCC”) and

Western Surety Company (“Western Surety”), appeal the trial court’s judgment,

rendered after a bench trial, that found in favor of plaintiff-appellee, Broadway

Concrete Investments L.L.C. d.b.a. Pompili Precast Concrete (“Pompili”) on Pompili’s

claims for breach of contract and violation of Ohio’s Prompt Payment Act and

awarded Pompili $82,388.51 in damages, plus $21,230.86 in interest and

$101,945.05 in attorney fees. For the reasons that follow, we affirm in part and

reverse and remand in part for further proceedings consistent with this opinion.

I. Background

This case arises out of the Nord Family Greenway construction

project on the Case Western Reserve University campus. The prime contractor for

the project was Gilbane Building Company. Gilbane subcontracted with Platform

Cements, Inc. d.b.a. Platform Contracting (“Platform”) for Platform to perform

excavation, site concrete, and hard cast (including precast concrete) for the project.

Platform subcontracted the precast concrete work to MCC, which in turn

subcontracted the supply of the precast concrete to Pompili by way of a purchase

order in the amount of $366,830.75 executed on October 26, 2016.

The evidence at trial demonstrated that prior to receiving the

purchase order from MCC, Pompili submitted a written quote for the precast work

directly to Platform. A copy of Pompili’s quote, which included various contract

terms, was attached to the signed purchase order between MCC and Pompili, and a handwritten note on the purchase order stated, “Note: see Broadway Concrete LLC

Terms & Conditions – Attached as Information Only.” Likewise, the written terms of

the purchase order stated, “Special Conditions: See attached Quotation #0209-001

for reference only.” Each page of the attached quotation from Pompili was marked

“INFORMATION ONLY.”

With respect to payment of Pompili’s invoices by MCC, the purchase

order required all invoices to be submitted to MCC by the 25th of the month “in order

for the invoices to be put on the appropriate draws. Receiving invoices after the 25th

will delay your payment.” The contract stated further that MCC “will issue checks

within 5 banking days after we receive payment.”

MCC submitted three pay applications to Platform in 2016: the first

in September, another in November, and the third in December. Pompili had not yet

submitted any invoices to MCC and accordingly, none of these pay applications

included any Pompili invoices. Matthew Birch, owner and president of MCC, testified

at trial that MCC’s first pay application to Platform, in the amount of $50,000, was

the result of an agreement with Platform that he would reduce his quote by $50,000

and Platform would give him an up front payment to help his start-up company.

Birch testified that when he submitted his original bid to Platform, he met with Jason

Klar, the owner of Platform, who told him that his bid was high. Birch told Jason that

he could reduce his bid if Platform paid him $50,000 to help start his newly formed

company. Birch testified that Jason agreed, paid him the agreed-upon $50,000, and

told him to invoice Platform. Jeremy Kler, the project manager for Platform on the project, was

called as a witness by Pompili. Kler testified that Jason negotiated Platform’s contract

with MCC and agreed to pay MCC $50,000 up front for its first pay application. Kler

testified that he reviewed the pay application and approved it, even though none of

the billed items had been completed at that point. Kler likewise confirmed that

MCC’s initial quote to Platform was for $674,980, but the contract executed between

Platform and MCC was for $624,980. Platform paid MCC’s first pay application of

$50,000 on October 13, 2016 — the same day it executed its contract with MCC and

13 days before MCC and Pompili executed their subcontract.

Pompili submitted its first invoice in the amount of $3,500 to MCC

on January 31, 2017. MCC included Pompili’s invoice on its fourth pay application to

Platform on January 25, 2017.1 Platform paid MCC’s fourth pay application on May 4,

2017; MCC paid Pompili’s invoice on April 20, 2017, 14 days before it received payment

from Platform.

Pompili submitted its second invoice in the amount of $20,000 on

April 20, 2017. MCC included Pompili’s invoice on its seventh pay application to

Platform on April 25, 2017. MCC received a partial payment of its total pay

application from Platform on June 17, 2017, and tendered the full amount of Pompili’s

invoice to Pompili on June 21, 2017.

1 Birch testified that he included money for Pompili in his fourth pay application before receiving Pompili’s invoice because he knew Pompili was working on shop drawings. Pompili’s third invoice, dated May 19, 2017, was for $30,000 and

included on MCC’s eighth pay application to Platform on May 25, 2017. MCC received

payment from Platform on August 1, 2017, and paid Pompili on August 3, 2017.

Pompili’s fourth invoice, dated June 29, 2017, in the amount of

$5,000, was included on MCC’s ninth pay application to Platform dated June 25,

2017. MCC paid Pompili on August 31, 2017, even though it did not receive payment

from Platform on this application until September 27, 2017.

Pompili’s fifth invoice, dated August 15, 2017, in the amount of

$70,000, was included on MCC’s 11th pay application submitted to Platform on

August 25, 2017. MCC paid Pompili on November 27, 2017, 17 days before it received

payment from Platform on December 4, 2017.

Pompili’s sixth invoice, dated September 18, 2017, for $36,500, was

included on MCC’s 12th pay application to Platform on September 25, 2017. MCC

paid Pompili on November 27, 2017, 17 days before receiving payment from Platform

on December 14, 2017.

On October 14, 2017, Pompili submitted its seventh invoice for

$110,000. MCC included the invoice on its 13th pay application to Platform. Platform

rejected the application, however, and informed MCC the owner had decided it would

no longer pay for material that was stored off-site and would pay only for material

that was installed or on-site. Platform advised Birch to revise his pay application.

Birch conducted an on-site survey and concluded that Pompili’s invoices were

overstated as compared to what material was on-site or installed. Platform agreed with Birch’s conclusion. Birch then revised Pompili’s invoice downward to reflects its

overbilling and submitted a revised 13th pay application to Platform. Platform paid

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Broadway Concrete Invests, L.L.C. v. Masonry Constracting Corp.
2022 Ohio 530 (Ohio Court of Appeals, 2022)
Gissentaner v. Buckeye Sauce Corp.
2022 Ohio 468 (Ohio Court of Appeals, 2022)

Cite This Page — Counsel Stack

Bluebook (online)
2022 Ohio 19, Counsel Stack Legal Research, https://law.counselstack.com/opinion/broadway-concrete-invests-llc-v-masonry-contracting-corp-ohioctapp-2022.