Broadway Concrete Invests, L.L.C. v. Masonry Constracting Corp.

2022 Ohio 530, 185 N.E.3d 612
CourtOhio Court of Appeals
DecidedFebruary 24, 2022
Docket110420
StatusPublished

This text of 2022 Ohio 530 (Broadway Concrete Invests, L.L.C. v. Masonry Constracting Corp.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Broadway Concrete Invests, L.L.C. v. Masonry Constracting Corp., 2022 Ohio 530, 185 N.E.3d 612 (Ohio Ct. App. 2022).

Opinion

[Cite as Broadway Concrete Invests, L.L.C. v. Masonry Constracting Corp., 2022-Ohio-530.]

[Vacated opinion. Please see 2022-Ohio-19.]

COURT OF APPEALS OF OHIO

EIGHTH APPELLATE DISTRICT COUNTY OF CUYAHOGA

BROADWAY CONCRETE : INVESTMENTS, L.L.C., : Plaintiff-Appellee, : No. 110420 v.

MASONRY CONTRACTING CORP., : ET AL.,

Defendants-Appellants. :

JOURNAL ENTRY AND OPINION

JUDGMENT: AFFIRMED IN PART; REVERSED AND REMANDED IN PART RELEASED AND JOURNALIZED: February 24, 2022

Civil Appeal from the Cuyahoga County Court of Common Pleas Case No. CV-18-903809

Appearances:

Stark & Knoll Co., L.P.A., Michael L. Fortney, Alexandra N. Nienaber, and Richard P. Schroeter, Jr., for appellee.

The Law Offices of David M. Leneghan, David M. Leneghan, K. Scott Carter, and Catana Chrostowski, for appellants. ON RECONSIDERATION1

KATHLEEN ANN KEOUGH, P.J.:

Defendants-appellants, Masonry Contracting Corp. (“MCC”) and

Western Surety Company (“Western Surety”), appeal the trial court’s judgment,

rendered after a bench trial, that found in favor of plaintiff-appellee, Broadway

Concrete Investments L.L.C. d.b.a. Pompili Precast Concrete (“Pompili”) on Pompili’s

claims for breach of contract and violation of Ohio’s Prompt Payment Act and

awarded Pompili $82,388.51 in damages, plus $21,230.86 in interest and

$101,945.05 in attorney fees. For the reasons that follow, we affirm in part and

reverse and remand in part for further proceedings consistent with this opinion.

I. Background

This case arises out of the Nord Family Greenway construction

project on the Case Western Reserve University campus. The prime contractor for

the project was Gilbane Building Company. Gilbane subcontracted with Platform

Cements, Inc. d.b.a. Platform Contracting (“Platform”) for Platform to perform

excavation, site concrete, and hard cast (including precast concrete) for the project.

Platform subcontracted the precast concrete work to MCC, which in turn

subcontracted the supply of the precast concrete to Pompili by way of a purchase

order in the amount of $366,830.75 executed on October 26, 2016.

1 The original decision in this appeal, Broadway Concrete Investments, L.L.C. v. Masonry Contracting Corp., 8th Dist. Cuyahoga No. 110420, 2022-Ohio-19, released on January 6, 2022, is hereby vacated. This opinion, issued upon reconsideration, is the court’s journalized decision in this appeal. See App.R. 22(C); see also S.Ct.Prac.R. 7.01. The evidence at trial demonstrated that prior to receiving the

purchase order from MCC, Pompili submitted a written quote for the precast work

directly to Platform. A copy of Pompili’s quote, which included various contract

terms, was attached to the signed purchase order between MCC and Pompili, and a

handwritten note on the purchase order stated, “Note: see Broadway Concrete LLC

Terms & Conditions – Attached as Information Only.” Likewise, the written terms of

the purchase order stated, “Special Conditions: See attached Quotation #0209-001

for reference only.” Each page of the attached quotation from Pompili was marked

“INFORMATION ONLY.”

With respect to payment of Pompili’s invoices by MCC, the purchase

order required all invoices to be submitted to MCC by the 25th of the month “in order

for the invoices to be put on the appropriate draws. Receiving invoices after the 25th

will delay your payment.” The contract stated further that MCC “will issue checks

within 5 banking days after we receive payment.”

MCC submitted three pay applications to Platform in 2016: the first

in September, another in November, and the third in December. Pompili had not yet

submitted any invoices to MCC and accordingly, none of these pay applications

included any Pompili invoices. Matthew Birch, owner and president of MCC, testified

at trial that MCC’s first pay application to Platform, in the amount of $50,000, was

the result of an agreement with Platform that he would reduce his quote by $50,000

and Platform would give him an up front payment to help his start-up company.

Birch testified that when he submitted his original bid to Platform, he met with Jason Klar, the owner of Platform, who told him that his bid was high. Birch told Jason that

he could reduce his bid if Platform paid him $50,000 to help start his newly formed

company. Birch testified that Jason agreed, paid him the agreed-upon $50,000, and

told him to invoice Platform.

Jeremy Kler, the project manager for Platform on the project, was

called as a witness by Pompili. Kler testified that Jason negotiated Platform’s contract

with MCC and agreed to pay MCC $50,000 up front for its first pay application. Kler

testified that he reviewed the pay application and approved it, even though none of

the billed items had been completed at that point. Kler likewise confirmed that

MCC’s initial quote to Platform was for $674,980, but the contract executed between

Platform and MCC was for $624,980. Platform paid MCC’s first pay application of

$50,000 on October 13, 2016 — the same day it executed its contract with MCC and

13 days before MCC and Pompili executed their subcontract.

Pompili submitted its first invoice in the amount of $3,500 to MCC

on January 31, 2017. MCC included Pompili’s invoice on its fourth pay application to

Platform on January 25, 2017.2 Platform paid MCC’s fourth pay application on May 4,

2017; MCC paid Pompili’s invoice on April 20, 2017, 14 days before it received payment

from Platform.

2Birch testified that he included money for Pompili in his fourth pay application before receiving Pompili’s invoice because he knew Pompili was working on shop drawings. Pompili submitted its second invoice in the amount of $20,000 on

April 20, 2017. MCC included Pompili’s invoice on its seventh pay application to

Platform on April 25, 2017. MCC received a partial payment of its total pay

application from Platform on June 17, 2017, and tendered the full amount of Pompili’s

invoice to Pompili on June 21, 2017.

Pompili’s third invoice, dated May 19, 2017, was for $30,000 and

included on MCC’s eighth pay application to Platform on May 25, 2017. MCC received

payment from Platform on August 1, 2017, and paid Pompili on August 3, 2017.

Pompili’s fourth invoice, dated June 29, 2017, in the amount of

$5,000, was included on MCC’s ninth pay application to Platform dated June 25,

2017. MCC paid Pompili on August 31, 2017, even though it did not receive payment

from Platform on this application until September 27, 2017.

Pompili’s fifth invoice, dated August 15, 2017, in the amount of

$70,000, was included on MCC’s 11th pay application submitted to Platform on

August 25, 2017. MCC paid Pompili on November 27, 2017, 17 days before it received

payment from Platform on December 4, 2017.

Pompili’s sixth invoice, dated September 18, 2017, for $36,500, was

included on MCC’s 12th pay application to Platform on September 25, 2017. MCC

paid Pompili on November 27, 2017, 17 days before receiving payment from Platform

on December 14, 2017.

On October 14, 2017, Pompili submitted its seventh invoice for

$110,000. MCC included the invoice on its 13th pay application to Platform. Platform rejected the application, however, and informed MCC the owner had decided it would

no longer pay for material that was stored off-site and would pay only for material

that was installed or on-site.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

A & J Plumbing, Inc. v. Huntington Natl. Bank
2014 Ohio 5707 (Ohio Court of Appeals, 2014)
Delta Fuels, Inc. v. Ohio Dept. of Transp.
2015 Ohio 5545 (Ohio Court of Appeals, 2015)
State v. Martin
485 N.E.2d 717 (Ohio Court of Appeals, 1983)
Wright v. State
591 N.E.2d 1279 (Ohio Court of Appeals, 1990)
Washington County Home v. Ohio Department of Health
896 N.E.2d 1011 (Ohio Court of Appeals, 2008)
City of Cleveland v. Jorski
53 N.E.2d 513 (Ohio Supreme Court, 1944)
Commercial Credit Co. v. Schreyer
166 N.E. 808 (Ohio Supreme Court, 1929)
Miller v. Cardinal Care Mgt., Inc.
2019 Ohio 2826 (Ohio Court of Appeals, 2019)
Broadway Concrete Invests., L.L.C. v. Masonry Contracting Corp.
2021 Ohio 1813 (Ohio Court of Appeals, 2021)
Broadway Concrete Invests., L.L.C. v. Masonry Contracting Corp.
2022 Ohio 19 (Ohio Court of Appeals, 2022)
Worldwide Asset Purchasing, L.L.C. v. Easterling
928 N.E.2d 1148 (Ohio Court of Appeals, 2009)
Seasons Coal Co. v. City of Cleveland
461 N.E.2d 1273 (Ohio Supreme Court, 1984)
Intercargo Insurance Co. v. Municipal Pipe Contractors, Inc.
2003 Ohio 7363 (Court of Common Pleas of Ohio, Franklin County, Civil Division, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
2022 Ohio 530, 185 N.E.3d 612, Counsel Stack Legal Research, https://law.counselstack.com/opinion/broadway-concrete-invests-llc-v-masonry-constracting-corp-ohioctapp-2022.