Bridgeview Vineyards, Inc. v. State Land Board

154 P.3d 734, 211 Or. App. 251, 2007 Ore. App. LEXIS 374
CourtCourt of Appeals of Oregon
DecidedMarch 14, 2007
Docket99CV0132; A120754
StatusPublished
Cited by10 cases

This text of 154 P.3d 734 (Bridgeview Vineyards, Inc. v. State Land Board) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bridgeview Vineyards, Inc. v. State Land Board, 154 P.3d 734, 211 Or. App. 251, 2007 Ore. App. LEXIS 374 (Or. Ct. App. 2007).

Opinion

*254 BREWER, C. J.

This case involves the interpretation of Oregon’s fill and removal law, ORS 196.800 to 196.990. In January 1999, petitioner Bridgeview Vineyards 1 asked respondent Division of State Lands (DSL) for emergency authorization to place riprap in Sucker Creek, a nonnavigable stream located in Josephine County that is designated as salmonid habitat. After DSL denied the authorization, petitioner sought judicial review of DSL’s order in circuit court, alleging in its first claim for relief that its proposed activity fit within various exceptions to and exemptions from the fill and removal law’s permitting requirements. The circuit court agreed and granted petitioner’s motion for partial summary judgment on that claim. 2 ORCP 67 B. DSL appeals. For the reasons explained below, we reverse. 3

As will be discussed in more detail below, the fill and removal law generally requires that a permit be obtained from DSL before removing 50 cubic yards or more of material from, or before placing a like amount of material in, waters of this state. 4 If, however, salmon spawn in the waters at issue (that is, it is “salmonid habitat”), the permit requirements are more stringent: a permit is required before any quantity of material may be removed or used as fill.

The fill and removal law provides exemptions from the general permitting requirements and an exception to the more stringent requirements applicable to salmonid habitat. For state waters generally, the exemptions pertain to specific activities related primarily to forestry and farming, such as *255 road maintenance on farm lands and maintenance of riprap. ORS 196.905. An exception also applies to salmonid streams with more stringent permitting requirements. ORS 196.810(l)(e). But the more stringent permitting requirements for salmonid habitat also contain their own limitation. That limitation, set out in ORS 196.810(l)(b), provides that the more stringent permitting requirements do not apply to fill or removal “for activities customarily related to agriculture.”

It is those permitting requirements, limitations, exceptions, and exemptions that are at issue in this case. We turn to the undisputed pertinent facts that gave rise to the controversy before us.

I. FACTS AND PROCEDURAL HISTORY

Sucker Creek is a salmonid stream under the fill and removal law. Petitioner’s farm property lies along Sucker Creek and includes wetlands that have been converted to farm use. The property is zoned for exclusive farm use. Over the years, the property has been subject to erosion from Sucker Creek, resulting in the loss of several acres of meadows and trees as well as damage to a road that borders the creek.

In 1998, petitioner began removing gravel and rock from Sucker Creek to use as riprap along the bank to stop the erosion. That activity involved the removal of more than 50 cubic yards of material from Sucker Creek. The state halted petitioner’s activity, claiming that it violated the fill and removal law, and began criminal proceedings against Kerivan, petitioner’s president.

In 1999, and while the criminal proceedings were pending, petitioner sought emergency authorization from DSL to place riprap in Sucker Creek in order to shore up the stream bank. 5 Petitioner’s written request referred to earlier telephone conversations and stated, in part, “The emergency permit I’m asking for would allow us to put rip-rap in Sucker *256 Creek to extend the rip-rap installed after the 1964 flood * * *.” 6 (Emphasis added.) In denying the request, DSL indicated that it understood that petitioner’s “request was to immediately place riprap along the bankline of Sucker Creek to prevent further erosion of [petitioner’s] property.” DSL denied petitioner’s application, concluding that petitioner’s concerns about erosion had been ongoing for some time and did not satisfy the criteria for issuing an emergency authorization.

Petitioner sought review of DSL’s order in circuit court as an order in other than a contested case. ORS 183.484. 7 Its sixth amended petition for judicial review characterized its request for an emergency permit as one “to allow petitioners to protect their upland farmland by maintaining the Sucker Creek streambank, including streambank maintenance stabilization modifications that maintain the integrity of the existing bank.” Petitioner alleged that the “proposed erosion control work included the placing of less than 50 yards of rip-rap along the banks of Sucker Creek and outside the water. The proposed work also includes removal of material from an area outside the wet perimeter and not within the adjacent nonvegetated dry gravel bar.”

In its cross-motion for partial summary judgment on its first claim for relief, petitioner made two arguments in support of its assertion that DSL erred in denying its request. First, it argued that DSL incorrectly had concluded that no *257 emergency existed that justified granting the request. Second, it argued that no authorization or permit was required, because the fill and removal law did not apply to its proposed activity in any event. As to the latter argument, petitioner asserted first that its requested “erosion control” work involved an “activity customarily associated with agriculture,” which was excepted under ORS 196.810(l)(b), the exception to the more stringent salmonid creek permitting provision. Second, it contended that the “activity was exempt under the provisions of ORS 196.905,” which set out particular exemptions from the fill and removal permitting requirements.

During oral argument on petitioner’s summaryjudgment motion, petitioner purported to stipulate that “we removed more than 50 cubic yards” and that “we’ve already agreed to more than 50 yards was [involved in] this case.” There was no evidence that any such removal, or fill, for that matter, was proposed in the 1999 request. Instead, the only evidence in the record that petitioner removed or filled more than 50 cubic yards of material in Sucker Creek pertained to its 1998 activity.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of Portland v. Kessler
556 P.3d 648 (Court of Appeals of Oregon, 2024)
Bridgeview Vineyards, Inc. v. Oregon State Land Board
309 P.3d 1103 (Court of Appeals of Oregon, 2013)
Grogan v. Harvest Capital Co. (In re Grogan)
476 B.R. 270 (D. Oregon, 2012)
Gienger v. Department of State Lands
214 P.3d 75 (Court of Appeals of Oregon, 2009)
Filipetti v. Department of Fish & Wildlife
197 P.3d 535 (Court of Appeals of Oregon, 2008)
State v. Bordeaux
185 P.3d 524 (Court of Appeals of Oregon, 2008)
State v. Rodriguez
175 P.3d 471 (Court of Appeals of Oregon, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
154 P.3d 734, 211 Or. App. 251, 2007 Ore. App. LEXIS 374, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bridgeview-vineyards-inc-v-state-land-board-orctapp-2007.