Bridgeport Pipe Engineering Co. v. DeMatteo Construction Co.

268 A.2d 391, 159 Conn. 242, 1970 Conn. LEXIS 466
CourtSupreme Court of Connecticut
DecidedMarch 3, 1970
StatusPublished
Cited by97 cases

This text of 268 A.2d 391 (Bridgeport Pipe Engineering Co. v. DeMatteo Construction Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bridgeport Pipe Engineering Co. v. DeMatteo Construction Co., 268 A.2d 391, 159 Conn. 242, 1970 Conn. LEXIS 466 (Colo. 1970).

Opinion

Alcorn, J.

The plaintiff brought this action in three counts to recover amounts claimed to be due on an express contract or, in the alternative, on an implied contract to furnish labor and materials and on an implied contract for extras. The defendant filed special defenses asserting that the plaintiff had failed to perform properly and counterclaimed for damages for the alleged derelictions. The court ren *244 dered judgment for the plaintiff on the complaint and on the counterclaim, and the defendant has appealed.

In its brief the defendant has pursued assignments of error concerning two of the court’s findings of subordinate facts and five of the court’s conclusions of fact. All other assignments of error concerning the finding are therefore treated as abandoned. Horton v. Vickers, 142 Conn. 105, 107, 111 A.2d 675. Consideration of the assignments of error which are pursued discloses that the finding is not subject to correction.

The court found as follows: The plaintiff is a corporation engaged in the mechanical contracting business. The defendant corporation is a general construction contractor. During the week of March 17, 1965, the defendant became interested in bidding on a public housing project being undertaken by the West Haven Housing Authority. On March 24, 1965, a duly authorized representative of the plaintiff offered to furnish the labor and materials to do the plumbing, heating and ventilation work on the housing project, as called for by the plans and specifications, for $564,000. This offer was submitted to the defendant by telephone. The plaintiff’s offer was based on an estimate of the costs of labor and material plus $44,000 for overhead and profit. The figure of $44,000 approximated a special 8 percent charge for overhead and profit granted to the defendant instead of a charge of 10 percent for profit and 10 percent for overhead which the plaintiff would normally charge. The defendant submitted a bid to the West Haven Housing Authority as the general contractor for the proposed housing project on March 24,1965, and, on the same day, the defendant learned that it was the low bidder as *245 the general contractor on the project. Formal award of the contract was not made to the defendant, however, until the end of May, 1965. Between March 24 and the end of May, 1965, the presidents of the two corporations discussed the job, and the defendant’s president told the plaintiff’s president that the figure of $564,000 for the plaintiff’s work was too high. The plaintiff’s president refused to change the figure but told the defendant’s president that the plaintiff would do everything it possibly could to save him money if the job made money and that, if the costs of materials could be cut, the saving would be passed on to it. By letter to the defendant dated June 30,1965, the plaintiff confirmed its oral offer of $564,000. At some time prior to that date the defendant told the plaintiff to proceed with the work, and the plaintiff commenced the work in June, 1965. The plaintiff continued with the work for about two years, during which the defendant repeatedly requested a renegotiated price for the work but received none. When the plaintiff completed the work covered by its original offer, it had incurred costs of $486,649.86, which was $33,856.14 less than the estimated costs on which its offer had been based. There was no mutual change, modification or rescission of the contract price of $564,000, however. The plaintiff fully performed and completed its contract, and the defendant has paid the plaintiff $506,582.21 for the work done.

The plaintiff also did extra work not covered by the contract for which it billed the defendant. On one item the plaintiff charged for the cost of labor and materials plus 8 percent for overhead and 6 percent for profit, all of which the court found to be fair and reasonable. In each of nine other bills for extras, the plaintiff charged for the cost of labor *246 and materials plus 14.414 percent for overhead and 5 percent for profit, and the court has found each of these charges to be reasonable.

From these subordinate facts the court concluded that the plaintiff had offered, for $564,000, to furnish all labor and material necessary to complete the specified work under the plans and specifications and that the offer had been accepted by the defendant, thereby creating a contract; that the plaintiff had performed the work and furnished the material called for by the contract; that the defendant had paid the plaintiff $506,582.21; and that it owed the plaintiff a balance of $57,417.79 under the contract. The court also concluded that the plaintiff had furnished labor and material for a change order and other extra work to the reasonable value of $19,485.80, which included a charge of 14.414 percent for overhead and 5 percent for profit added to the cost for labor and materials. Judgment was accordingly rendered for the plaintiff to recover of the defendant $76,903.59.

It is elementary that to create a contract there must be an unequivocal acceptance of an offer. In the case of a bilateral contract, the acceptance of the offer need not be express but may be shown by any words or acts which indicate the offeree’s assent to the proposed bargain. W. G. Maltby, Inc. v. Associated Realty Co., 114 Conn. 283, 288, 158 A. 548; Frederick Raff Co. v. Murphy, 110 Conn. 234, 239, 147 A. 709. The acceptance of the offer must, however, be explicit, full and unconditional. Woodbridge Ice Co. v. Semon Ice Cream Corporation, 81 Conn. 479, 487, 71 A. 577. And the burden rested on the plaintiff to prove a meeting of the minds to establish its version of the claimed contract. Lucier v. Norfolk, 99 Conn. 686, 699, 122 A. 711.

*247 The plaintiff’s claim is that it made an offer to do the prescribed work for the fixed sum of $564,000 and that the offer was accepted. The court has not found that there was an express acceptance of the offer. In addition to the facts already recited, the court has found, however, that Gene DeMatteo is president of the defendant and that the offer which was submitted to him on the plaintiff’s behalf was computed and transmitted by F. Arthur DeLucia. The court also has found that the plaintiff undertook to do the work “pursuant to the terms of DeLucia’s understanding with DeMatteo of March 24, 1965.” This finding, which is not attacked by the defendant, lacks clarity because of the uncertainty as to the meaning which the court ascribed to the word “understanding”. One of its accepted meanings is “a mutual agreement not formally entered into but in some degree binding on each side.” Webster, Third New International Dictionary. “We therefore resort to the memorandum of decision to interpret the finding.” Kriedel v. Krampitz, 137 Conn. 532, 535, 79 A.2d 181; Rogers v. Kinnie, 134 Conn. 58, 61, 54 A.2d 487; Van Tassel v. Spring Perch Co., 113 Conn.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Reale v. Match Group, LLC
D. Connecticut, 2022
Errato v. American Express Co.
D. Connecticut, 2019
Computer Reporting Services, LLC v. Lovejoy & Associates, LLC
145 A.3d 266 (Connecticut Appellate Court, 2016)
Loiselle v. Browning & Browning Real Estate, LLC
83 A.3d 608 (Connecticut Appellate Court, 2013)
Shetucket Plumbing Supply Inc. v. S.C.S. Agency, Inc.
570 F. Supp. 2d 282 (D. Connecticut, 2008)
Knauss v. Ultimate Nutrition, Inc.
514 F. Supp. 2d 241 (D. Connecticut, 2007)
Alstom Power, Inc. v. Balcke-Durr, Inc.
849 A.2d 804 (Supreme Court of Connecticut, 2004)
Hipsky v. Allstate Insurance
304 F. Supp. 2d 284 (D. Connecticut, 2004)
Greenfield v. Lawrence Memorial Hospital, No. 560884 (Aug. 26, 2002)
2002 Conn. Super. Ct. 10822 (Connecticut Superior Court, 2002)
Tulip Construction, Inc. v. Dilorenzo, No. Cv00-0083389 (Aug. 14, 2002)
2002 Conn. Super. Ct. 10204 (Connecticut Superior Court, 2002)
Incor Group v. Polied Enviro. Rest. Ser., No. Cv01-0457219 (Mar. 28, 2002)
2002 Conn. Super. Ct. 3344-a (Connecticut Superior Court, 2002)
Co-Options v. News America Mktg., No. X01 Cv 00 0163095 S (Feb. 27, 2002)
2002 Conn. Super. Ct. 2238 (Connecticut Superior Court, 2002)
Coventry v. Hastings, No. Cv-98-0066824 (Feb. 7, 2002)
2002 Conn. Super. Ct. 1572 (Connecticut Superior Court, 2002)
Nile Company, LLC v. Capuano, No. Cv 00 0083319s (Oct. 24, 2001)
2001 Conn. Super. Ct. 14617 (Connecticut Superior Court, 2001)
Colliers Dow Condon v. Schwartz, No. Cv 00-0594954 (Sep. 14, 2001)
2001 Conn. Super. Ct. 13458-e (Connecticut Superior Court, 2001)
Cheverie v. Ashcraft & Gerel
783 A.2d 474 (Connecticut Appellate Court, 2001)
Skc Palm Holdings v. Gottlieb Family, No. Cv 98 0078029 (Feb. 13, 2001)
2001 Conn. Super. Ct. 2213 (Connecticut Superior Court, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
268 A.2d 391, 159 Conn. 242, 1970 Conn. LEXIS 466, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bridgeport-pipe-engineering-co-v-dematteo-construction-co-conn-1970.