Incor Group v. Polied Enviro. Rest. Ser., No. Cv01-0457219 (Mar. 28, 2002)

2002 Conn. Super. Ct. 3344-a
CourtConnecticut Superior Court
DecidedMarch 28, 2002
DocketNo. CV01-0457219
StatusUnpublished

This text of 2002 Conn. Super. Ct. 3344-a (Incor Group v. Polied Enviro. Rest. Ser., No. Cv01-0457219 (Mar. 28, 2002)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Incor Group v. Polied Enviro. Rest. Ser., No. Cv01-0457219 (Mar. 28, 2002), 2002 Conn. Super. Ct. 3344-a (Colo. Ct. App. 2002).

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.]

MEMORANDUM OF DECISION
This is an application for prejudgment remedy. The plaintiff is Incor Group, Inc. and the defendant is Polied Environmental Services, Inc. The controversy between the parties relates to the removal of asbestos on the U.S. Submarine Base in Groton, Connecticut. CT Page 3345

"General Statutes § 52-278d (a) permits a trial court to grant a prejudgment remedy if "the plaintiff has shown probable cause that . . . a judgment will be rendered . . . in the plaintiffs favor. . . ." We emphasize that a hearing on an application is not a full-scale trial on the merits of the plaintiffs' claims; Fischel v. TKPK, Ltd., 34 Conn. App. 22, 24, 640 A.2d 125 (1994); Hoke, Inc. v. Circuits, Inc., 26 Conn. App. 804, 805, 602 A.2d 1075 (1995); but rather concerns only whether and to what extent the plaintiff is entitled to have property of a defendant held in custody of the law pending final adjudication of the merits of the action. Tyler v. Schnabel, 34 Conn. App. 216, 220, 641 A.2d 388 (1994)." Bosco v. Arrowhead by The Lake, Inc., 53 Conn. App. 873, 874 (1999).

"General Statutes § 52-278d (a) provides that a trial court may issue a PJR if it determines that there is "probable cause to sustain the validity of [the plaintiffs] claim." It is firmly established that the trial court's hearing in probable cause is not intended to be a full scale trial on the merits of the plaintiffs claim. "The plaintiff does not have to establish that he will prevail, only that there is probable cause to sustain the validity of the claim. . . . The court's role in such a hearing is to determine probable success by weighing probabilities. . . ." (Internal quotation marks omitted.) Calfee v. Usman, 224 Conn. 29, 37, 616 A.2d 250 (1992). Probable cause for purposes of the PJR statutes is a flexible common sense standard that does not demand that a belief be correct or more likely true than false. Goodwin v. Pratt, 10 Conn. App. 618, 621, 524 A.2d 1168 (1987)." Fischel v. TKPK, Ltd., 34 Conn. App. 22, 24 (1994).

The plaintiffs claim for a prejudgment remedy is premised upon the court finding that: (1) the parties entered into an agreement as shown in Exhibit 2 coupled with Exhibit 3, and (2) that agreement was breached. The court finds these documents, Exhibits 2 and 3, did not comprise an agreement between the parties. The court finds that the plaintiff failed to sustain its burden of proof, to the standard of probable cause, regarding this issue. CT Page 3346

The court finds the following facts. On or about April 4, 2001, the plaintiff Incor Group, Inc. entered into a contract with USA Contractors for the removal of asbestos at Dolphin Gardens apartment buildings on the United States Navy Submarine Base in Groton, Connecticut. Incor was to remove asbestos from 383 units to ready them for demolition, for a contract price of $1,649,900.00.

Incor Group contracted with the defendant Polied Environmental to perform all of the work within the scope of the plaintiffs contract with USA Contractors. Discussions ensued regarding this work. On or about April 16, 2001, John Nericcio, Project Manager and Estimator for the plaintiff, sent a proposed contract to the defendant to perform the job for $1.43 million. Polied Environmental never signed the proposed contract. That proposed unsigned agreement would have required the defendant to remove all asbestos pursuant to specifications provided by Dewberry and Davis.

After April 16, 2001, the defendant communicated with the plaintiff regarding certain issues pertaining to performing the job. Before signing any agreement, the defendant wanted in writing:

(1) Alternative Work Practices1 (AWP) to be permitted for the asbestos abatement,

(2) Permission to house its workers at the Sub Base during the work week, and

(3) Payment of $10,000 per week until full payment at the end of the agreement.

The defendant was under the supervision from the plaintiff, at the inception of the work, that alternative work practices had been approved for the asbestos abatement.

The defendant bid the job at $1.43 million based upon acceptance of AWPs for the job. The plaintiff was aware that AWPs were the basis for that bid.

The defendant proceeded to start work when requested by the plaintiff, without a signed contract, on May 16, 2001. Initially, the defendant had approximately 33 workers on the job. After one week of work, John Fitrzyk, principal of Polied, called the plaintiff for the first $10,000 payment. He was told it would be ready the next week. It was not. From May 16, 2001 to July 27, 2001, the defendant worked at the project site without any payment. CT Page 3347

Approximately three weeks into the job, the site was 85-90% prepped for asbestos removal with AWPs and the preabatement demolition was completed for these areas. At that time, a representative of the U.S. Navy (owner of the project site) appeared at the site and informed Fitrzyk that AWPs were not approved and, therefore, the additional site preparation would be needed. Fitrzyk complained to the plaintiffs representative; the result was a change order of $500 per unit for this additional work for the first 51 units.

On June 12, 2001, the plaintiff sent correspondence to USA Contractors that their contract would cost another $192,000 if the AWPs were not approved.

On July 17, 2001, Fitrzyk was told that his men and stored equipment in the buildings would have to be out of Navy Housing by 5:00 P.M. that date. This was apparently the result of concern that some of the men had utilized stoves for heat in an unusually cold summer.

As of July 17, 2001, the defendant had been paid nothing despite having made repeated requests and having received assurances of payment from the plaintiff, AWPs had not been approved and the defendant had no housing, outside of paying for motels for his workers (who largely lived in New York).

After two months on the job, the plaintiff informed the defendant that they needed certified payrolls in order to receive payment. This was a term of the original agreement proposed by the plaintiff, not signed by the defendant. Plaintiff was also required to have certified payrolls to be in compliance with its contract with USA Contractors. Defendant supplied certified payrolls for the first four weeks of work. Still no payment had been made. Defendant, consequently, has not certified any more of the payroll weeks.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bridgeport Pipe Engineering Co. v. DeMatteo Construction Co.
268 A.2d 391 (Supreme Court of Connecticut, 1970)
Calfee v. Usman
616 A.2d 250 (Supreme Court of Connecticut, 1992)
Goodwin v. Pratt
524 A.2d 1168 (Connecticut Appellate Court, 1987)
One Fawcett Place Ltd. Partnership v. Diamandis Communications, Inc.
589 A.2d 892 (Connecticut Appellate Court, 1991)
Hoke Inc. v. Circuits, Inc.
602 A.2d 1075 (Connecticut Appellate Court, 1992)
Fischel v. TKPK, Ltd.
640 A.2d 125 (Connecticut Appellate Court, 1994)
Tyler v. Schnabel
641 A.2d 388 (Connecticut Appellate Court, 1994)
State v. Crosby
641 A.2d 406 (Connecticut Appellate Court, 1994)
Bosco v. Arrowhead by Lake, Inc.
732 A.2d 205 (Connecticut Appellate Court, 1999)
Richter v. Danbury Hospital
759 A.2d 106 (Connecticut Appellate Court, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
2002 Conn. Super. Ct. 3344-a, Counsel Stack Legal Research, https://law.counselstack.com/opinion/incor-group-v-polied-enviro-rest-ser-no-cv01-0457219-mar-28-2002-connsuperct-2002.