Brenner v. Zaleski

174 So. 3d 76, 2014 La.App. 4 Cir. 1323, 2015 La. App. LEXIS 1129, 2015 WL 5597277
CourtLouisiana Court of Appeal
DecidedJune 3, 2015
DocketNo. 2014-CA-1323
StatusPublished
Cited by8 cases

This text of 174 So. 3d 76 (Brenner v. Zaleski) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brenner v. Zaleski, 174 So. 3d 76, 2014 La.App. 4 Cir. 1323, 2015 La. App. LEXIS 1129, 2015 WL 5597277 (La. Ct. App. 2015).

Opinion

EDWIN A. LOMBARD, Judge.

hThis suit arises from a construction contract dispute between the Appellants, condominium owner Michael Brenner and his mother, Jackie Brenner (“the Bren-ners”), and carpenter, Donald Zaleski. The Brenners seek review of First City Court’s August 18, 2014 judgment dismissing their breach of contract claims with prejudice. Finding that the First City Court made a legal error in determining that the contract at issue was not breached, we reverse. Additionally, this matter is remanded for a determination of damages.

Facts and Procedural History

The Brenners retained Mr. Zaleski to build a wooden loft1 in the ceiling of their condominium, which is located in New Orleans.2 The parties executed a contract on January 11, 2013. The contract did not contain a clause or wording relating to the termination of Mr. Zaleski’s services. Pursuant to the contract, Mr. Zaleski was to be paid $12,677.00, of which he was paid 50%, or $6,338.00, at the |2start of construction. The record reflects the Bren-ners increased the initial scope of Mr. Za-leski’s work, and an invoice update was later issued by him reflecting that he began to receive payments from the Bren-ners upon completion of certain tasks.

After Mr. Zaleski began building the loft,3 but prior to his completion of the project, the Brenners observed what they believed to be cosmetic flaws in his work. Ms. Brenner e-mailed Mr. Zaleski regarding the Brenners’ concerns, which she discussed with Mr. Zaleski the following day. Ms. Brenner alleges that Mr. Zaleski became aggressive during their conversation. Thereafter, the Brenners fired Mr. Zaleski on or about April 22, 2013. However, post-termination, they discovered a substantive defect: the loft subflooring installed by Mr. Zaleski was moving or flexing.

Subsequently, home inspector and civil engineer Friedrich Gurtler was hired by the Brenners to inspect Mr. Zaleski’s work, particularly the condition of the sub-flooring. Mr. Gurtler opined that Mr. Za-leski’s work was substandard and not structurally sound. He recommended the loft be reinforced with steel support columns, which the Brenners installed.

The Brenners4 filed suit against Mr. Zaleski in First City Court alleging he breached his contract as well as the implied warranty of good workmanship. Following a bench trial, the First City Court dismissed the Brenners’ lawsuit with prejudice. The Brenners timely appealed and raise two (2) assignments of error:

1. The First City Court erred in finding that Mr. Zaleski was premature[79]*79ly terminated in direct contravention of lathe existing law found in Vazquez v. Gairens, 26 So.2d 319 (La.App.Orleans 1946); and
2. The First City Court erred in determining that the timing and reasons for the termination of the contract should prevent recovery from damages clearly proven both in law and fact.

A trier of fact’s factual conclusions respecting a breach of contract claim are governed by the manifest error or clearly wrong standard of review. See Tarifa v. Riess, 02-1179, p. 10 (La.App. 4 Cir. 5/7/03), 856 So.2d 21, 27, as clarified on reh’g (9/3/03), writ denied, 03-2776 (La.12/19/03), 861 So.2d 574 and writ denied, 03-2755 (La.12/19/03), 861 So.2d 577. Where there is conflicting testimony, reasonable evaluations of credibility and inferences of fact should not be disturbed by the reviewing court. Rosell v. ESCO, 549 So.2d 840, 844 (La.1989). Where there are two permissible views of the evidence, the trier of fact’s choice between them cannot be manifestly erroneous or clearly wrong. Id. However, where one or more trial court legal errors interdict the fact-finding process, the manifest error standard is no longer applicable, and, if the record is otherwise complete, the appellate court should make its own independent de novo review of the record and determine a preponderance of the evidence. Evans v. Lungrin, 97-0541, 97-0577, pp. 6-7 (La.2/6/98), 708 So.2d 731, 735.

A contract is the law between the parties, and the parties will be held to full performance in good faith of the obligations flowing from the contract. Henderson v. Ayo, 11-1605, p. 5 (La.App. 4 Cir. 6/13/12), 96 So.3d 641, 645 (citing La. Civ.Code art.1983). It is implicit in every building contract that the contractor’s work be performed in a good, workmanlike manner, and free from defects in materials or work. Id. [Citations omitted.] See La. Civ.Code art. 2756.

| ¿The Brenners’ aver that their breach claim is based upon La. Civ.Code art. 2769, entitled Contractor’s liability for non-compliance with contract, which states:

If an undertaker fails to do the work he has contracted to do, or if he does not execute it in the manner and at the time he has agreed to do it, he shall be liable in damages for the losses that may ensue from his non-compliance with his contract.

Furthermore, they also contend that they had the right to terminate Mr. Zale-ski’s employment at any time pursuant to La. Civ.Code art. 2765, entitled Cancellation of contract by owner, which provides:

The proprietor has a right to cancel at pleasure the bargain he has made, even in case the work has already been commenced, by paying the undertaker for the expense and labor already incurred, and such damages as the nature of the case may require.

While the Brenners are correct in asserting that they had the right to terminate Mr. Zaleski at any time under La. Civ. Code art. 2765, our court has explained that claims under La. Civ.Code arts. 2765 and 2769 are distinct.

In Henderson, 11-1605, pp. 5-6, 96 So.3d at 645, we reasoned that pursuant to La. Civ.Code. art. 2765, Louisiana law recognizes the right of the owner of a construction project to terminate a contract to build after work has commenced on a project. It is the owner’s obligation, nevertheless, to pay the contractor for the work he or she completed. Id., 11-1605, p. 6, 96 So.3d at 645. We further clarified that La. Civ.Code art. 2769 applies where a contractor does not perform the work he or she has contracted to do:

[80]*80On the other hand, if the contractor fails to do the work he has contracted to perform, or does not execute in the manner agreed to he is liable in damages for losses that may ensue from his noncompliance with the contract.

J¿d.

The Brenners further rely upon Vazquez v. Gairens, 26 So.2d 319, 320 (La.App.Orleans 1946), wherein our predecessor court considered the application of both La. Civ. Code arts. 2765 and 2769:5

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
174 So. 3d 76, 2014 La.App. 4 Cir. 1323, 2015 La. App. LEXIS 1129, 2015 WL 5597277, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brenner-v-zaleski-lactapp-2015.