Brawner Builders v. State Highway Admin.

258 A.3d 217, 476 Md. 15
Court of Appeals of Maryland·Decided August 25, 2021·No. 58/20·Published·Cited by 6 cases

Opinion

Brawner Builders, Inc., et al. v. Maryland State Highway Administration, No. 58, September Term, 2020, Opinion by Booth, J.

STATE FINANCE AND PROCUREMENT—PROCUREMENT CONTRACTS— FORMATION

The Court of Appeals held that certifying a supplier as a pre-approved source of materials for future projects did not constitute a procurement contract, as that term is defined in the State Finance and Procurement Article (“SF”) § 11-101. SF § 11-101(n) defines procurement as the process of buying or otherwise obtaining goods or services. Relying on this definition, the Court of Appeals reasoned that certifying a supplier as a pre- approved supplier of materials for future projects, without more, is not a procurement contract because the State is neither buying nor obtaining goods or services from the certified supplier.

STATE FINANCE AND PROCUREMENT—PROCUREMENT CONTRACTS— DISPUTE RESOLUTION—NOTICE OF CLAIM—TIMELINESS

SF § 15-219 provides that a contractor must file written notice of a claim against a procurement agency within 30 days after the basis for the claim is known or should have been known, and the support for the claim itself must be filed within 90 days after submission of the notice of claim. The Court of Appeals held that the Maryland State Board of Contract Appeals did not err in concluding a subcontractor failed to timely file a procurement contract claim even though such determination was made at the summary disposition stage because the undisputed facts showed notice of claim was not filed by the contractor within 30 days after the basis for the claim was known or should have been known.

Circuit Court for Baltimore City Case No.: 24-C-19-003208 Argued: June 4, 2021

IN THE COURT OF APPEALS

OF MARYLAND

No. 58

September Term, 2020

BRAWNER BUILDERS, INC., et al.

v.

MARYLAND STATE HIGHWAY

ADMINISTRATION

Barbera, C.J.

McDonald

Booth

Biran

Rodowsky, Lawrence F.

(Senior Judge, Specially Assigned)

Harrell, Jr. Glenn T.

(Senior Judge, Specially Assigned)

Raker, Irma S.

(Senior Judge, Specially Assigned),

JJ.

Opinion by Booth, J.

Pursuant to Maryland Uniform Electronic Legal Materials Act (§§ 10-1601 et seq. of the State Government Article) this document is authentic.

2021-08-25 13:55-04:00

Filed: August 25, 2021

Suzanne C. Johnson, Clerk

In this case, we must determine whether a material supplier’s status as a “pre-

approved supplier” of concrete panels on construction projects administered by the Maryland State Highway Administration (“SHA”) constituted a “procurement contract” with the State under the State Finance and Procurement Article. The supplier, who was a subcontractor on a State construction project, contends that its status as a pre-approved supplier of products by SHA constituted a procurement contract with the State, thereby entitling the subcontractor to file a direct contract claim against SHA under the procurement statute.

The dispute arises out of a contract between SHA and Brawner Builders, Inc.

(“Brawner”) entered on November 19, 2012, for the construction of noise barriers along a section of I-95 in Howard County. To secure the necessary materials for the project, Brawner subcontracted with Faddis Concrete Products, Inc. (“Faddis”), a pre-certified noise barrier manufacturer, to obtain noise wall panels for the project. Unfortunately, things did not proceed as planned. Shortly after Faddis began manufacturing noise wall panels for Brawner’s use in connection with the project, SHA learned that the noise panels produced by Faddis contained construction aggregate of a non-conforming coarseness from an unapproved source. Following an investigation, SHA suspended approval of Faddis- manufactured noise panels for a minimum of 180 days.

Displeased with SHA’s decision, Faddis sent letters to SHA and SHA’s legal counsel alleging, in general terms, harm due to SHA’s decision to suspend approval of Faddis-produced noise panels. In addition to sending letters to SHA, Faddis also sent a letter to Brawner. This letter, which apparently recognized that the Maryland State Board

of Contract Appeals (“MSBCA”) will not hear procurement contract claims filed by subcontractors unless they pass through the prime contractor, requested that Brawner pass Faddis’s contract claims through to SHA, which Brawner ultimately declined to do.

Approximately four years later, Faddis and Brawner sent a joint letter to SHA demanding that SHA render decisions on Faddis’s claims, which they asserted were properly submitted to SHA. SHA did not respond to this letter. Interpreting SHA’s silence as a denial of all claims, the parties filed an appeal with the MSBCA. SHA timely moved for summary disposition, which the MSBCA granted. In so doing, the MSBCA agreed with SHA that Faddis had no procurement contract with SHA and therefore had no standing to file a procurement claim unless such claim timely passed through Brawner. The MSBCA reasoned that, because Brawner did not timely file Faddis’s claim, dismissal was appropriate.

Faddis and Brawner timely filed a petition for judicial review in the Circuit Court for Baltimore City. The circuit court reversed the MSBCA’s decision, concluding that, as a matter of law, SHA’s certification of Faddis as a pre-approved supplier of noise barriers constituted a procurement contract, thereby conferring upon Faddis standing to file a direct claim against SHA. The circuit court also found error in the MSBCA’s conclusion that Faddis failed to timely file a notice of claim with SHA. According to the circuit court, it was inappropriate for the MSBCA to make factual determinations with respect to notice without a full hearing on the merits.

An appeal to the Court of Special Appeals followed. In a reported decision, the intermediate appellate court reversed the circuit court’s decision. Md. State Highway

Admin. v. Brawner Builders, Inc., 248 Md. App. 646 (2020). In so holding, the court agreed with the MSBCA’s conclusion that Faddis lacked standing to file a direct claim against SHA because SHA’s certification of Faddis as a pre-approved supplier of noise barriers, without more, did not constitute a procurement contract. Similarly, the court agreed with the MSBCA’s conclusion that Brawner failed to timely file notice of claim on Faddis’s behalf.

For the reasons more fully set forth herein, we affirm the decision of the MSBCA.

We agree with the MSBCA that SHA’s certification of Faddis’s manufacturing plan as a pre-approved supplier of concrete panels on SHA construction projects does not fall within the definition of a “procurement contract” under the State Finance and Procurement Article. Consequently, Faddis, as Brawner’s subcontractor, did not have standing to bring direct contract claims against SHA. We also determine that, as a matter of law, Brawner’s submission of a notice of a claim on Faddis’s behalf was not timely.

I.

Factual and Procedural Background A. SHA Highway Noise Policy and Manufacturer Certifications When Congress enacted the Federal-Aid Highway Act of 1970, Congress compelled the Federal Highway Administration (the “FHWA”) to, among other things, adopt highway noise abatement standards and conditioned approval of federal highway projects on adherence to such standards. See Federal-Aid Highway Act of 1970, Pub. L. No. 91-605, § 136 (codified, as amended, at 23 U.S.C. § 109(i)). Consistent with this directive, the FHWA not only promulgated regulations establishing noise abatement standards, see

Free access — add to your briefcase to read the full text and ask questions with AI

Brawner Builders v. State Highway Admin., 258 A.3d 217, 476 Md. 15 (Md. 2021).

258 A.3d 217 (Brawner Builders v. State Highway Admin.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Bd. of Education v. Sturm
Court of Appeals of Maryland, 2026
State v. Young
Court of Appeals of Maryland, 2026
State of Md. Comptroller v. Badlia Bros.
Court of Appeals of Maryland, 2025
Matter of the Petition of Md. Bio Energy
Court of Special Appeals of Maryland, 2024
Williams v. Morgan State Univ.
300 A.3d 54 (Court of Appeals of Maryland, 2023)
Montgomery Park v. Dept. of Gen. Services
290 A.3d 586 (Court of Appeals of Maryland, 2023)
Romeka v. RadAmerica II
Court of Special Appeals of Maryland, 2022