Brawner Builders v. State Highway Admin.

258 A.3d 217, 476 Md. 15
CourtCourt of Appeals of Maryland
DecidedAugust 25, 2021
Docket58/20
StatusPublished
Cited by6 cases

This text of 258 A.3d 217 (Brawner Builders v. State Highway Admin.) is published on Counsel Stack Legal Research, covering Court of Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brawner Builders v. State Highway Admin., 258 A.3d 217, 476 Md. 15 (Md. 2021).

Opinion

Brawner Builders, Inc., et al. v. Maryland State Highway Administration, No. 58, September Term, 2020, Opinion by Booth, J.

STATE FINANCE AND PROCUREMENT—PROCUREMENT CONTRACTS— FORMATION

The Court of Appeals held that certifying a supplier as a pre-approved source of materials for future projects did not constitute a procurement contract, as that term is defined in the State Finance and Procurement Article (“SF”) § 11-101. SF § 11-101(n) defines procurement as the process of buying or otherwise obtaining goods or services. Relying on this definition, the Court of Appeals reasoned that certifying a supplier as a pre- approved supplier of materials for future projects, without more, is not a procurement contract because the State is neither buying nor obtaining goods or services from the certified supplier.

STATE FINANCE AND PROCUREMENT—PROCUREMENT CONTRACTS— DISPUTE RESOLUTION—NOTICE OF CLAIM—TIMELINESS

SF § 15-219 provides that a contractor must file written notice of a claim against a procurement agency within 30 days after the basis for the claim is known or should have been known, and the support for the claim itself must be filed within 90 days after submission of the notice of claim. The Court of Appeals held that the Maryland State Board of Contract Appeals did not err in concluding a subcontractor failed to timely file a procurement contract claim even though such determination was made at the summary disposition stage because the undisputed facts showed notice of claim was not filed by the contractor within 30 days after the basis for the claim was known or should have been known. Circuit Court for Baltimore City Case No.: 24-C-19-003208 Argued: June 4, 2021

IN THE COURT OF APPEALS

OF MARYLAND

No. 58

September Term, 2020

BRAWNER BUILDERS, INC., et al.

v.

MARYLAND STATE HIGHWAY ADMINISTRATION

Barbera, C.J. McDonald Booth Biran Rodowsky, Lawrence F. (Senior Judge, Specially Assigned) Harrell, Jr. Glenn T. (Senior Judge, Specially Assigned) Raker, Irma S. (Senior Judge, Specially Assigned),

JJ.

Opinion by Booth, J. Pursuant to Maryland Uniform Electronic Legal Materials Act (§§ 10-1601 et seq. of the State Government Article) this document is authentic.

2021-08-25 13:55-04:00

Filed: August 25, 2021 Suzanne C. Johnson, Clerk In this case, we must determine whether a material supplier’s status as a “pre-

approved supplier” of concrete panels on construction projects administered by the

Maryland State Highway Administration (“SHA”) constituted a “procurement contract”

with the State under the State Finance and Procurement Article. The supplier, who was a

subcontractor on a State construction project, contends that its status as a pre-approved

supplier of products by SHA constituted a procurement contract with the State, thereby

entitling the subcontractor to file a direct contract claim against SHA under the

procurement statute.

The dispute arises out of a contract between SHA and Brawner Builders, Inc.

(“Brawner”) entered on November 19, 2012, for the construction of noise barriers along a

section of I-95 in Howard County. To secure the necessary materials for the project,

Brawner subcontracted with Faddis Concrete Products, Inc. (“Faddis”), a pre-certified

noise barrier manufacturer, to obtain noise wall panels for the project. Unfortunately,

things did not proceed as planned. Shortly after Faddis began manufacturing noise wall

panels for Brawner’s use in connection with the project, SHA learned that the noise panels

produced by Faddis contained construction aggregate of a non-conforming coarseness from

an unapproved source. Following an investigation, SHA suspended approval of Faddis-

manufactured noise panels for a minimum of 180 days.

Displeased with SHA’s decision, Faddis sent letters to SHA and SHA’s legal

counsel alleging, in general terms, harm due to SHA’s decision to suspend approval of

Faddis-produced noise panels. In addition to sending letters to SHA, Faddis also sent a

letter to Brawner. This letter, which apparently recognized that the Maryland State Board of Contract Appeals (“MSBCA”) will not hear procurement contract claims filed by

subcontractors unless they pass through the prime contractor, requested that Brawner pass

Faddis’s contract claims through to SHA, which Brawner ultimately declined to do.

Approximately four years later, Faddis and Brawner sent a joint letter to SHA

demanding that SHA render decisions on Faddis’s claims, which they asserted were

properly submitted to SHA. SHA did not respond to this letter. Interpreting SHA’s silence

as a denial of all claims, the parties filed an appeal with the MSBCA. SHA timely moved

for summary disposition, which the MSBCA granted. In so doing, the MSBCA agreed

with SHA that Faddis had no procurement contract with SHA and therefore had no standing

to file a procurement claim unless such claim timely passed through Brawner. The

MSBCA reasoned that, because Brawner did not timely file Faddis’s claim, dismissal was

appropriate.

Faddis and Brawner timely filed a petition for judicial review in the Circuit Court

for Baltimore City. The circuit court reversed the MSBCA’s decision, concluding that, as

a matter of law, SHA’s certification of Faddis as a pre-approved supplier of noise barriers

constituted a procurement contract, thereby conferring upon Faddis standing to file a direct

claim against SHA. The circuit court also found error in the MSBCA’s conclusion that

Faddis failed to timely file a notice of claim with SHA. According to the circuit court, it

was inappropriate for the MSBCA to make factual determinations with respect to notice

without a full hearing on the merits.

An appeal to the Court of Special Appeals followed. In a reported decision, the

intermediate appellate court reversed the circuit court’s decision. Md. State Highway

2 Admin. v. Brawner Builders, Inc., 248 Md. App. 646 (2020). In so holding, the court agreed

with the MSBCA’s conclusion that Faddis lacked standing to file a direct claim against

SHA because SHA’s certification of Faddis as a pre-approved supplier of noise barriers,

without more, did not constitute a procurement contract. Similarly, the court agreed with

the MSBCA’s conclusion that Brawner failed to timely file notice of claim on Faddis’s

behalf.

For the reasons more fully set forth herein, we affirm the decision of the MSBCA.

We agree with the MSBCA that SHA’s certification of Faddis’s manufacturing plan as a

pre-approved supplier of concrete panels on SHA construction projects does not fall within

the definition of a “procurement contract” under the State Finance and Procurement

Article. Consequently, Faddis, as Brawner’s subcontractor, did not have standing to bring

direct contract claims against SHA. We also determine that, as a matter of law, Brawner’s

submission of a notice of a claim on Faddis’s behalf was not timely.

I.

Factual and Procedural Background

A. SHA Highway Noise Policy and Manufacturer Certifications

When Congress enacted the Federal-Aid Highway Act of 1970, Congress compelled

the Federal Highway Administration (the “FHWA”) to, among other things, adopt highway

noise abatement standards and conditioned approval of federal highway projects on

adherence to such standards. See Federal-Aid Highway Act of 1970, Pub. L. No. 91-605,

§ 136 (codified, as amended, at 23 U.S.C. §

Related

State of Md. Comptroller v. Badlia Bros.
Court of Appeals of Maryland, 2025
Matter of the Petition of Md. Bio Energy
Court of Special Appeals of Maryland, 2024
Williams v. Morgan State Univ.
300 A.3d 54 (Court of Appeals of Maryland, 2023)
Montgomery Park v. Dept. of Gen. Services
290 A.3d 586 (Court of Appeals of Maryland, 2023)
Romeka v. RadAmerica II
Court of Special Appeals of Maryland, 2022

Cite This Page — Counsel Stack

Bluebook (online)
258 A.3d 217, 476 Md. 15, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brawner-builders-v-state-highway-admin-md-2021.