State Highway Admin v. Brawner Builders

242 A.3d 1188, 248 Md. App. 646
CourtCourt of Special Appeals of Maryland
DecidedDecember 18, 2020
Docket1643/19
StatusPublished
Cited by4 cases

This text of 242 A.3d 1188 (State Highway Admin v. Brawner Builders) is published on Counsel Stack Legal Research, covering Court of Special Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State Highway Admin v. Brawner Builders, 242 A.3d 1188, 248 Md. App. 646 (Md. Ct. App. 2020).

Opinion

Md. State Highway Administration v. Brawner, No. 1643, September Term 2019, Argument Date: 11/6/20

Procurement Law

A subcontractor is entitled to make a contract claim against a procurement agency only if there is a direct contract between the claimant and that agency. The subcontractor had a contract with a contractor to provide materials on a state highway project. Although the state agency had approved the materials the subcontractor would use in state highway noise barrier wall, that did not suffice to create a contract between the subcontractor and the agency. As such, the subcontractor did not have standing to present a claim against the agency. The mere approval of a company’s product as being acceptable for a project does not make that company a procurement contractor with standing to make a claim.

Timeliness

In construction contracts, a contractor must file written notice of a claim against a procurement agency within 30 days after the basis for the claim is known or should have been known and the support for the claim itself must be filed within 90 days after submission of the notice of the claim. The subcontractor alleged the contractor was obligated to pass through its complaints to the procurement agency. The court affirmed the decisions of the Maryland State Board of Contract Appeals to dismiss the claim as untimely because the contractor failed to file a written pass-through notice with the 30 days. Circuit Court for Baltimore City Case No. 24-C-19003208 REPORTED IN THE COURT OF SPECIAL APPEALS

OF MARYLAND

No. 1643

September Term, 2019

MARYLAND STATE HIGHWAY ADMINISTRATION

v.

BRAWNER BUIILDERS, INC.

Beachley, Gould, Wilner, Alan M. (Senior Judge, Specially Assigned),

JJ.

Opinion by Wilner, J.

Filed: December 18, 2020

Pursuant to Maryland Uniform Electronic Legal Materials Act (§§ 10-1601 et seq. of the State Government Article) this document is authentic.

Suzanne Johnson 2020-12-18 15:41-05:00

Suzanne C. Johnson, Clerk This case arises under the State procurement law. The State Highway

Administration (SHA) rejected claims filed by appellees Brawner Builders, Inc.

(Brawner) and Faddis Concrete Products, Inc. (Faddis) on the grounds that (1) Faddis had

no procurement contract with SHA and therefore had no standing to file a procurement

claim, and (2) the claims filed by Brawner and Faddis were untimely. In an appeal by

appellees, the Maryland State Board of Contract Appeals (MSBCA) agreed with SHA on

both of those issues and entered a Summary Decision affirming SHA’s rejection of the

claims.

In a judicial review action, however, the Circuit Court for Baltimore City had a

different view. It concluded, (1) as a matter of law, that Faddis did have a procurement

contract with SHA and was entitled to file a claim, and (2) that there was a genuine

dispute of material fact as to whether the claims were timely. It therefore vacated the

MSBCA summary decision and remanded the case for a hearing on the merits of the

claims. Before us is SHA’s appeal from that judgment. We shall reverse the Circuit

Court judgment and remand with instructions to affirm the MSBCA order.

BACKGROUND

The project that spawned this dispute was the construction of a 0.38-mile noise

barrier wall along a stretch of I-95 in Howard County. Noise abatement measures along

State highways are required both for Federal funding of highway construction projects

and by State law. As a result, in August 2011, SHA issued a Highway Noise Policy that set forth substantive requirements for precast concrete products and a procedure for SHA

certification of plants producing those products. Pre-approval of a plant by SHA was

required in order for a manufacturer to be eligible to bid on SHA highway projects.

Certification was good for one year, subject to renewal following an annual inspection of

the plant and subject also to the manufacturer continuing to operate the plant in

conformance with the SHA specifications through a Quality Control Plan. SHA charged

a cost reimbursement fee for the cost of inspection and certification. Pursuant to that

process, SHA, at some point, certified Faddis’s plant in Downingtown, Pennsylvania as

“Qualified for Sourcing on State Projects” and included that plant on its list of pre-

approved manufacturers of noise barrier systems.

The prime contract for the construction of the 0.38-mile section (Contract No.

H02485126) was entered into with Brawner on November 19, 2012. That contract, for

whatever reason, was not placed in evidence in the court proceeding and therefore is not

included in the record. In February 2013, Brawner and Faddis entered into a subcontract,

evidenced by a purchase order, for Faddis to furnish 40,910 noise wall panels and three

access doors. All materials and work were required to be in conformance with the

conditions and specifications pertaining to the prime contract. The purchase order was

contingent on SHA approval of Faddis as a supplier and made clear that Brawner was

obligated to pay for all products ordered, produced, and shipped regardless of any

payment to Brawner by SHA. There were to be no set-offs. Brawner reserved the right

2 to cancel the subcontract if Faddis was in breach of any of its obligations, including the

performance or delivery of non-conforming work or materials.

In September 2013, Faddis furnished SHA with a sample panel which, on

September 27, SHA approved for use on the project. Based on that approval, Faddis

began manufacturing the panels for Brawner to erect pursuant to its (Brawner’s) contract

with SHA.

SHA employed an outside agency to furnish inspectors to assure compliance with

the SHA standards, one of whom was Nick Patras. Mr. Patras was stationed at Faddis’s

Downingtown plant for the purpose of inspecting panels destined for the SHA project.

No panels were to be shipped without his approval. It appears, at least from SHA’s

perspective, that Mr. Patras was not doing his job properly, and he eventually was

dismissed. In March 2014, SHA’s Office of Materials and Technology concluded that

panels manufactured by Faddis after November 27, 2013 contained aggregate from an

unapproved source, which was a violation of the noise barrier standards, and, as a result,

the required strength of the panels could not be determined. Investigations led the

Assistant Division Chief for Field Operations (Christopher Gale) to conclude, among

other things, that, throughout the production of the panels, Faddis had (1) failed to

provide adequate documentation of the source material for the exposed aggregate panels,

(2) altered cylinder test data to reflect values higher than what the material actually

achieved, (3) used a mix design that did not meet SHA specifications, and (4) was

extremely uncooperative about making changes to meet specifications.

3 On May 2, 2014, SHA’s District Engineer, David Coyne, informed Brawner of

those conclusions and requested a response as to how Brawner intended to remedy the

problem. Faddis was not copied on that letter. Brawner’s project manager responded six

days later, on May 8, that the problem was not Brawner’s to remedy, that it involved

instead “a breakdown in the fabrication, inspection, and acceptance procedure at an SHA

pre-approved concrete precast facility.” The letter requested a temporary partial

shutdown of the project and advised that Brawner was reserving its rights to extended

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Matter of the Petition of Md. Bio Energy
Court of Special Appeals of Maryland, 2024
Brawner Builders v. State Highway Admin.
258 A.3d 217 (Court of Appeals of Maryland, 2021)
Small MS4 Coalition v. Dept. of Environment
250 Md. App. 388 (Court of Special Appeals of Maryland, 2021)

Cite This Page — Counsel Stack

Bluebook (online)
242 A.3d 1188, 248 Md. App. 646, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-highway-admin-v-brawner-builders-mdctspecapp-2020.