Brantley County Development Partners, LLC v. Brantley County, Georgia

District Court, S.D. Georgia·Decided September 2, 2021·No. 5:19-cv-00109·Unknown

Opinion

In the United States District Court for the Southern District of Georgia Waycross Division

BRANTLEY COUNTY DEVELOPMENT PARTNERS, LLC,

Plaintiff, CV 5:19-109 v.

BRANTLEY COUNTY, GEORGIA by and through its Chairman and Members of the Brantley County Board of Commissioners; CHRIS “SKIPPER” HARRIS, RANDY DAVIDSON, BRIAN HENDRIX, JESSE MOBLEY, and RAY GRIFFIN, all in their individual and official capacities as Commissioners,

Defendants.

ORDER Presently before the Court is Defendants’ Renewed Motion to Dismiss. Dkt. No. 48. Plaintiff has filed a Response in opposition to Defendants' Motion, dkt. no. 52, to which Defendants have filed a Reply, dkt. no. 55. For the reasons below, Defendants’ Motion to Dismiss is GRANTED in part and DENIED in part. BACKGROUND Plaintiff Brantley County Development Partners, LLC (“Plaintiff”) is a limited liability company registered to do business under the laws of the State of Georgia. Dkt. No. 1 ¶ 1. On December 22, 2014, Plaintiff purchased 2,839 acres of land (the “Property”) to pursue the construction and operation of a solid waste handling facility in Brantley County (the “County”). Id.

¶ 9. Under the provisions of Georgia’s Comprehensive Solid Waste Management Act (the “CSWMA”), O.C.G.A. §§ 12-8-20 et seq., any person seeking to operate a solid waste handling facility must obtain a solid waste handling permit by application to the Georgia Environmental Protection Division (the “EPD”). In order to proceed through the EPD’s permitting process, the applicant must submit certain letters from the local governing authority certifying that the proposed site complies with local land use ordinances and is consistent with the local solid waste management plan (the “SWMP”). O.C.G.A. § 12-8-24(g). Moreover, pursuant to the rules of the Georgia Department of Natural Resources, written verification of local zoning compliance must be “reaffirmed by the governmental

authority prior to permit issuance.” Ga. Comp. R. & Regs. 391-3- 4-.05(1)(a). Before closing on the Property, Plaintiff sought and obtained written verification (the “2014 Verification Letters”) from County Manager Carl Rowland (“Rowland”) certifying that Plaintiff’s proposed solid waste handling facility (the “Proposed Facility”) was consistent with the County’s SWMP and local land use plan. Dkt. No. 1-2 at 3. At that time, the County did not have any zoning ordinances in effect at all. Id. at 2. On February 5, 2015, at a regularly scheduled meeting, the Brantley County Commission, through its Board of Commissioners (“Defendants”),1 took official action to authorize Plaintiff’s

Proposed Facility. Dkt. No. 1-4 at 4. The minutes and regular agenda show Plaintiff requested Defendants ratify and confirm the prior certification that the Proposed Facility and related activities were “consistent with [the] local land use plan and [the] Solid Waste Management Plan.” Id. Consequently, Defendants authorized the Chairman of the Board of Commissioners, Charlie Summerlin, to execute two letters (“the 2015 Verification Letters”): [T]he first letter acknowledging that the solid waste handling facilities proposed by [Plaintiff] . . . is consistent with the approved Solid Waste Management Plan adopted by Brantley County and the cities of Hoboken and Nahunta on June 26, 2006, and our most recent 2011 Five Year Short Term Work Program 2010-2019; and, the second letter acknowledging that the facilities proposed by [Plaintiff] is consistent with Brantley County’s Local Land Use Plan.

Id. The minutes acknowledge that Defendants knew these letters were necessary for Plaintiff to obtain permits from the EPD in order to conduct solid waste material activities. Id. On February 6, 2015, Chairman Summerlin signed and issued the 2015 Verification Letters to Claudia Moeller, an EPD program

1 Plaintiff is suing the individual commissioners of Brantley County both in their individual and official capacities. Dkt. No. 1 at 1. Defendants include Commissioners Chris “Skipper” Harris, Randy Davidson, Brian Hendrix, Jesse Mobley, and Ray Griffin. Id. manager, verifying Plaintiff’s Proposed Facility was consistent with the County’s SWMP and local land and zoning regulations. Dkt. No. 1-5 at 3. These letters reiterated that “Brantley County at

the present time does not have a zoning ordinance.” Id. at 2. On September 8, 2016, Defendants voted to adopt a new land- use ordinance for Brantley County (the “2016 Zoning Ordinance”). Dkt. No. 1-7. Plaintiff alleges it received assurances from Defendants that the 2016 Zoning Ordinance would not apply to its Proposed Facility. Dkt. No. 1 ¶ 18. Moreover, at the time the 2016 Zoning Ordinance was adopted, the ordinance did not include a map identifying the various zoning classifications, and no motion was made to approve any official zoning map. Id. ¶ 19. On December 29, 2016, Plaintiff filed a permit application with the EPD for the Proposed Facility. Dkt. No. 1-11. The EPD accepted the application along with Plaintiff’s filing fee for processing. Dkt. No. 1 ¶ 28.

Beginning in 2017, a noticeable shift occurred in Defendants’ stance toward the siting and construction of a solid waste handling facility on Plaintiff’s Property. On January 3, 2017, Defendants imposed a 180-day moratorium on any landfills in Brantley County. Dkt. No. 1-12. That same day, Defendants also moved to send a written objection to the EPD regarding Plaintiff’s Proposed Facility. Dkt. No. 1-14 at 2. The January 3, 2017 Board minutes show that Defendants moved to instruct all county officials to “immediately cease and desist any communications or efforts with [Plaintiff] or any other individual or entity where the intent is to establish or facilitate a landfill or solid waste handling facility.” Id. at 3.

On January 6, 2017, County Attorney Deen Strickland, on behalf of Defendants, sent a letter to the EPD stating that Defendants were unanimously opposed to Plaintiff’s Proposed Facility and advising the EPD that Defendants had passed a moratorium on the proposed location. Dkt. No. 1-16 at 2. On January 19, 2017, Defendants took official action to hire outside counsel for the purpose of “stopping the landfill” on Plaintiff’s Property. Dkt. No. 1 ¶ 35. On June 15, 2017, Defendants convened and took action to down- zone Plaintiff’s Property from Heavy Industrial to Light Industrial (the “2017 Rezoning Decision”). Id. ¶ 42. Under the Light Industrial zoning classification, landfills are forbidden on

Plaintiff’s Property. Id. ¶ 45. Plaintiff contends Defendants’ entire rezoning process failed to follow proper procedures and no notice was given. Id. That same day, Defendants also allegedly adopted a new zoning ordinance (the “2017 Zoning Ordinance”) along with an official zoning map. Id. ¶ 43. Finally, at the same meeting, Defendants also adopted an amended Solid Waste Management Plan (the “2017 SWMP”). Dkt. No. 45 ¶ 151. The 2017 SWMP, as amended, prevents solid waste facilities from importing any waste from outside the County. Id. ¶¶ 151, 154. Specifically, any waste disposal facility must “limit use of such sites to disposal of waste generated from only within the County.” Id. ¶ 154.

On June 19, 2019, Plaintiff demanded Defendants provide the necessary written verification of local zoning compliance (the “Reaffirmation Letters”) for its EPD permit. Id. ¶ 58; see also Ga. Comp. R. & Regs. 391-3-4-.05(1)(a). Specifically, Plaintiff requested that Defendants confirm Plaintiff’s Property is not subject to the 2017 Rezoning Decision, the 2017 SWMP, or any zoning ordinances at all. Dkt. No. 1-26 at 3.

Free access — add to your briefcase to read the full text and ask questions with AI

Brantley County Development Partners, LLC v. Brantley County, Georgia, (S.D. Ga. 2021).

Brantley County Development Partners, LLC v. Brantley County, Georgia (Brantley County Development Partners, LLC v. Brantley County, Georgia) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Domer L. Ishler v. Internal Revenue
237 F. App'x 394 (Eleventh Circuit, 2007)
Watson Construction Co. v. City of Gainesville
244 F. App'x 274 (Eleventh Circuit, 2007)
Rogers v. Miller
57 F.3d 986 (Eleventh Circuit, 1995)
Corn v. City of Lauderdale Lakes
95 F.3d 1066 (Eleventh Circuit, 1996)
Villas of Lake Jackson, Ltd. v. Leon County
121 F.3d 610 (Eleventh Circuit, 1997)
Hipp v. Liberty National Life Insurance
252 F.3d 1208 (Eleventh Circuit, 2001)
75 Acres, LLC v. Miami-Dade County
338 F.3d 1288 (Eleventh Circuit, 2003)
Greenbriar Village, L.L.C. v. Mountain Brook, City
345 F.3d 1258 (Eleventh Circuit, 2003)
Joseph G. Givens v. AL Dept. of Corrections
381 F.3d 1064 (Eleventh Circuit, 2004)
Crown Media, LLC v. Gwinnett County, GA
380 F.3d 1317 (Eleventh Circuit, 2004)
Earle B. Lewis v. Clarence Brown
409 F.3d 1271 (Eleventh Circuit, 2005)
Alfred L. Bochese v. Town of Ponce Inlet
405 F.3d 964 (Eleventh Circuit, 2005)
Center for Biological Diversity v. Sam Hamilton
453 F.3d 1331 (Eleventh Circuit, 2006)
Harris v. Mexican Specialty Foods, Inc.
564 F.3d 1301 (Eleventh Circuit, 2009)
Sinaltrainal v. Coca-Cola Company
578 F.3d 1252 (Eleventh Circuit, 2009)
Pennsylvania Coal Co. v. Mahon
260 U.S. 393 (Supreme Court, 1922)
Brandenburg v. Ohio
395 U.S. 444 (Supreme Court, 1969)