Brandywine Village Associates and L&R Partnership v. East Brandywine Twp. Board of Supervisors and Carlino East Brandywine, L.P.

CourtCommonwealth Court of Pennsylvania
DecidedJanuary 5, 2018
Docket164 C.D. 2017
StatusUnpublished

This text of Brandywine Village Associates and L&R Partnership v. East Brandywine Twp. Board of Supervisors and Carlino East Brandywine, L.P. (Brandywine Village Associates and L&R Partnership v. East Brandywine Twp. Board of Supervisors and Carlino East Brandywine, L.P.) is published on Counsel Stack Legal Research, covering Commonwealth Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brandywine Village Associates and L&R Partnership v. East Brandywine Twp. Board of Supervisors and Carlino East Brandywine, L.P., (Pa. Ct. App. 2018).

Opinion

IN THE COMMONWEALTH COURT OF PENNSYLVANIA

Brandywine Village Associates : and L&R Partnership, : Appellants : : v. : No. 164 C.D. 2017 : Argued: December 7, 2017 East Brandywine Township : Board of Supervisors : and Carlino East Brandywine, L.P. :

BEFORE: HONORABLE ROBERT SIMPSON, Judge HONORABLE ANNE E. COVEY, Judge HONORABLE DAN PELLEGRINI, Senior Judge

OPINION NOT REPORTED

MEMORANDUM OPINION BY SENIOR JUDGE PELLEGRINI FILED: January 5, 2018

In this confusing case, Brandywine Village Associates (BVA) and L&R Partnership (L&R) (collectively, Objectors) appeal the order of the Court of Common Pleas of Chester County (trial court) involving a decision by the Board of Supervisors (Board) of East Brandywine Township (Township) denying a preliminary plan filed by Carlino East Brandywine, L.P. (Developer) for the construction of a mixed-use development on a 10-acre parcel that it owns in the Township. I. A. The Developer is the equitable owner of an undeveloped tract of land located at 1279 Horseshoe Pike in East Brandywine Township, Chester County, Pennsylvania, containing approximately 10.118 acres (Property). The Property was originally part of a 21-acre parcel. BVA owns the remaining 11 acres, which contain a shopping center adjacent to the east side of the Property.

Prior to the Developer’s acquisition of the Property, BVA had certain rights to use the 10-acre parcel under a Cross Easement Agreement entered into with the Developer’s predecessor-in-title. Because the entire 21 acres did not have access to any public sewer, the Cross Easement Agreement provided that BVA would build, at its expense, a sewer plant for the use of both parties on the 10-acre parcel. The Cross Easement Agreement also granted BVA an easement to the 10- acre parcel for stormwater management as well as an access easement to use the 10-acre parcel as a main entrance to BVA’s shopping center.1 L&R, the general partner of BVA, is the owner of an undeveloped parcel of land adjacent to the north side of the Property.

1 Under the Cross Easement Agreement, the predecessor-in-interest granted BVA a sewer system easement to install an on-site septic sewer system, including a drainage area and reserve drainage area. It also provided an access easement to allow construction of a roadway through the Property to BVA property. The Cross Easement Agreement specified that the access drive could be modified, but that it must not “interfere with the flow of traffic . . . or with surface water drainage.” (Reproduced Record (R.R.) at 47a.) The Cross Easement Agreement further provided a highway improvement easement, dedicating land within the ultimate right-of-way along Route 322 to public use, and a stormwater basin and drainage easement, which included a reserve effluent disposal area.

2 Since 2011, the Developer has submitted land-development plans to build a 51,525 square foot supermarket with a 9,250 square foot expansion area, a 4,600 square foot attached retail building, and a pad site for a 4,088 square foot bank on the Property. From the beginning, the Township insisted that the Developer provide and pay for the construction of a road (Connector Road) connecting the Property with Horseshoe Pike (Route 322) on which it fronts and North Guthriesville Road.

Because the Connector Road was to cross over L&R’s adjoining property, in 2014, the Township and the Developer entered into a Memorandum of Understanding (MOU). Under this MOU, the Developer, in lieu of paying a significant portion of the Township’s transportation impact fee of $1,795,000, was obligated to design, permit and construct at its expense the Connector Road and dedicate it to the Township. The MOU also provided that the Township would condemn necessary portions of L&R’s adjoining property as well as BVA’s easements on the Property granted under the Cross Easement Agreement.

B. While the Developer has submitted a few different versions of land development plans pertaining to the Property, the plan subject to this appeal is the plan filed December 9, 2014 (2014 Plan). The Developer argues that even though the Connector Road will eventually be dedicated to the Township as a public road, it is currently a driveway and the Developer identified it as such in the 2014 Plan. The 2014 Plan also included the area under the “driveway” as part of the Developer’s land area. The 2014 Plan did not identify the previously condemned

3 BVA easements on the Property. In January 2015, the Board conditionally approved the 2014 Plan. Objectors appealed to the trial court and the Developer intervened.

C. Among other things, Objectors alleged that the 2014 Plan contained many defects, including the following:

 It did not comply with the Township’s Zoning Ordinance (Zoning Ordinance) requirement of a minimum 10-acre area to build a mixed-use development in a Mixed Use (MU) zoning district.2

 It did not comply with Section 399-46.C of the Zoning Ordinance, requiring that “[n]o building shall be situated less than 85 feet from the front lot line” because the bank building, as designed on the 2014 Plan, is set back 50 feet from the Connector Road. (R.R. at 593a.) Developer argued that Connector Road was merely a private driveway until such time as it is dedicated to the Township, and therefore, the 85-foot setback requirement is inapplicable.

 Even though the Property was going to be connected to the public sewer system, the 2014 Plan violated Section 399-47.K3 of the Zoning Ordinance, providing that 2 Section 399-46.A of the Zoning Ordinance provides that “[a] minimum gross tract area of 10 acres shall be required for any use or combination of uses permitted in the MU District.” (R.R. at 593a.)

3 Section 399-47.K of the Zoning Ordinance provides:

Sewage facilities and water supply. The applicant’s proposals for sewage facilities and for water supply (both quality and quantity) in relation to the proposed uses shall be in compliance with the requirements of §§ 350-47 and 350-48, respectively, of Chapter (Footnote continued on next page…)

4 sewage facilities must be in compliance with the Township’s Land Development Ordinance (SALDO), Sections 350-47.B(2)4 & 350-48.5 BVA argued that this provision was incorporated into the Zoning Ordinance and could not be waived.

 It did not comply with Section 399-81.E6 of the Zoning Ordinance because Developer failed to provide safe and

(continued…)

350, Subdivision and Land Development. Any approval of an application for development within the MU District shall be contingent upon the requisite approvals and certifications from the Chester County Health Department and/or the Pennsylvania Department of Environmental Protection.

(R.R. at 594a.)

4 Section 350-47.B(2) of the SALDO provides in pertinent part:

All subdivisions and land developments shall be self-sustaining relative to the storage and disposal of treated sewage effluent. The applicant shall provide sufficient storage and land area on or off the subdivision or land development site to store and dispose of all treated sewage effluent which is generated by the uses on the site by means of conventional underground seepage beds or drip irrigation.

(R.R. at 616a.)

5 Section 350-48 of the SALDO pertains to water supply.

6 Section 399.81.E of the Zoning Ordinance provides that to minimize traffic congestion and encourage “orderly development of street highway frontage,” an applicant is responsible for providing:

[S]afe and efficient ingress and egress to and from public streets, without undue congestion or interference with normal traffic flow within the Township. The developer shall be responsible for the design, construction, and costs of any necessary traffic control (Footnote continued on next page…)

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Empire Coal Mining & Development, Inc. v. Department of Environmental Resources
623 A.2d 897 (Commonwealth Court of Pennsylvania, 1993)
In Re Cain
590 A.2d 291 (Supreme Court of Pennsylvania, 1991)
Maple Street A.M.E. Zion Church v. City of Williamsport
7 A.3d 319 (Commonwealth Court of Pennsylvania, 2010)
Callowhill Center Associates, LLC v. Zoning Board of Adjustment
2 A.3d 802 (Commonwealth Court of Pennsylvania, 2010)
Governor's Office v. Office of Open Records, Aplt.
98 A.3d 1223 (Supreme Court of Pennsylvania, 2014)
ACS Enterprises, Inc. v. Norristown Borough Zoning Hearing Board
659 A.2d 651 (Commonwealth Court of Pennsylvania, 1995)
In re Brandywine Realty Trust
857 A.2d 714 (Commonwealth Court of Pennsylvania, 2004)
Chruby v. Department of Corrections
4 A.3d 764 (Commonwealth Court of Pennsylvania, 2010)
Pilchesky v. Lackawanna County
88 A.3d 954 (Supreme Court of Pennsylvania, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
Brandywine Village Associates and L&R Partnership v. East Brandywine Twp. Board of Supervisors and Carlino East Brandywine, L.P., Counsel Stack Legal Research, https://law.counselstack.com/opinion/brandywine-village-associates-and-lr-partnership-v-east-brandywine-twp-pacommwct-2018.