Brando Construction, Inc. v. Department of Transportation

487 N.E.2d 1132, 139 Ill. App. 3d 798, 94 Ill. Dec. 255, 1985 Ill. App. LEXIS 2893
CourtAppellate Court of Illinois
DecidedDecember 30, 1985
Docket84-2055
StatusPublished
Cited by8 cases

This text of 487 N.E.2d 1132 (Brando Construction, Inc. v. Department of Transportation) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brando Construction, Inc. v. Department of Transportation, 487 N.E.2d 1132, 139 Ill. App. 3d 798, 94 Ill. Dec. 255, 1985 Ill. App. LEXIS 2893 (Ill. Ct. App. 1985).

Opinion

JUSTICE CAMPBELL

delivered the opinion of the court:

Pursuant to Supreme Court Rules 304(a) and 307(a)(l) (87 Ill. 2d Rules 304(a), 307(a)(1), defendants, State of Illinois, Department of Transportation (IDOT), John D. Kramer and H.W. Monroney, appeal from an interlocutory order entered by the circuit court of Cook County granting preliminary injunctive and declaratory relief to plaintiff, Brando Construction, Inc. Intervener, Thos. M. Madden Construction Co. (Madden), appeals from the circuit court’s denial of its petition for intervention. Plaintiff, as low bidder on a State construction project, sought: (1) a preliminary injunction to enjoin defendants from awarding the project to Madden, second lowest bidder, and (2) specific performance of the alleged contract between IDOT and plaintiff on the grounds that it had complied with all applicable rules and regulations promulgated by IDOT with respect to the bidding procedure. Madden sought the right to intervene to protect its interests in the contract. The circuit court denied Madden’s petition for intervention and granted plaintiff’s motion for a preliminary injunction and declaratory relief.

The underlying dispute concerns a bid which plaintiff had submitted to IDOT in response to a general advertisement for bids on the construction work of a State highway project. On July 10, 1984, Richard Brooks, chief contract officer for IDOT, informed Randall Rathmann, plaintiff’s estimator and general superintendent of field operations, by telephone that plaintiff was low bidder on the project at issue. Brooks further informed Rathmann that he had five working days, i.e., until July 17, 1984, within which to mail to IDOT’s Springfield offices the necessary forms indicating compliance "with the DBE/ WBE utilization plan (the plan) which indicates the extent of participation in the proposed project by disadvantaged business enterprises (DBEs) or women-owned business enterprises (WBEs). Brooks told Rathmann that the paperwork had to be either hand-delivered to IDOT’s Springfield offices by 4:30 p.m. on July 17 or postmarked by July 17, 1984. Failure to timely comply would render the bid non-responsive.

On July 27, 1984, plaintiff received a letter from H.M. Monroney, Director of Highways for IDOT, which informed plaintiff that because it had not submitted its plan within the required time period, its bid was rejected as nonresponsive and it would not be allowed to rebid on the project in the event the project was readvertised. Rathmann immediately called IDOT’s Springfield office and spoke with Brooks, who informed Rathmann that the envelope was postmarked July 18, 1984. When Rathmann explained that he had personally mailed the plan before the last 5:30 p.m. mail pickup on July 17, 1984, Brooks told him to send a letter to IDOT detailing the circumstances.

On July 30, 1984, Rathman telephoned IDOT and spoke with Joseph Crowe, who advised Rathmann to come to Springfield as soon as possible and explain the situation in person. Several minutes after terminating the conversation, Crowe telephoned Rathmann and informed him that he had just learned that the project “had already gone to construction” and that Madden, as second low bidder, was suggested as the contractor to be awarded the project. Rathmann told Crowe that he and Vito Brandonisio, plaintiff’s president, would go to Springfield anyway. In the interim, plaintiff filed a complaint with the post office.

On July 31, 1984, Rathmann and Brandonisio met with Ronald Eckert of IDOT and explained to Eckert that they had mailed the Plan on July 17, 1984. Eckert told them to write down all the facts and mail it to him. Brandonisio mailed the necessary information on August 1, 1984. Six days later, Rathmann telephoned Ingvy Bloomquist, project engineer for IDOT, and was informed that a preconstruction meeting had been set up with Madden for August 13, 1984. The following day, August 8, 1984, plaintiff filed its verified complaint and motion for a temporary restraining order and/or preliminary injunction, requesting the court to: (1) enter a declaratory judgment order declaring that plaintiff is the low, responsive, responsible bidder on the project and that plaintiff’s mailing of the plan was timely and sufficiently complied with all bidding requirements; (2) enter orders temporary, preliminary, and permanent, without notice or bond, enjoining and/or restraining defendants from awarding the contract at issue to anyone other than plaintiff pending further order of the court; and (3) order defendants to specifically perform the contract at issue with plaintiff.

On August 9, 1984, the circuit court entered a temporary restraining order restraining defendants “from awarding a construction contract to anyone other than plaintiff with respect to” the project at issue, pending further order of the court. Shortly thereafter, Madden filed its emergency motion to intervene as a parly defendant. The circuit court denied Madden’s motion on the ground that it lacked standing to intervene. Defendants then filed their answer to plaintiff’s complaint. Subsequently, Madden filed an emergency motion for reconsideration of denial of intervention, amending his original petition to seek the same relief against defendants as sought by plaintiffs. The circuit court again denied Madden’s motion on the ground that Madden lacked standing because it had no vested right in the contract.

Thereafter, following a hearing on plaintiff’s motion for preliminary injunctive and declaratory relief, the circuit court found, inter alia, that plaintiff had timely mailed the plan and had sufficiently complied with all of IDOT’s necessary bidding requirements, and entered its order on August 20, 1984, which: (1) restrained and enjoined the State of Illinois and all defendants from awarding the contract at issue to Madden or anyone other than plaintiff; and (2) ordered the State of Illinois and all defendants to specifically perform the contact at issue with plaintiff. Subsequently, on August 23, 1984, the circuit court entered its amended order, nunc pro tunc as of August 20, 1984, which added the finding that because plaintiff’s bid was approximately $182,000 less than Madden’s, the interest of the Illinois taxpayers is furthered by the preliminary injunction. Defendants’ and Madden’s timely appeals followed.

All purchases and contacts entered into by any State agency, including IDOT, are subject to the provisions of the Illinois Purchasing Act (the Act) (Ill. Rev. Stat. 1983, ch. 127, par. 132.1 et seq.), which establishes the procedure for procuring competitive bids and authorizes each State agency to adopt “additional rules governing procurement practices and procedures for that agency.” (Ill. Rev. Stat., 1984 Supp., ch. 127, par. 132.5.) Acceptance or rejection of bids is discretionary with the State agency; and if, the agency rejects all bids, it may readvertise for new bids. Ill. Rev. Stat. 1983, ch. 127, par. 132.4.

On appeal, defendants first allege that plaintiff, as a disappointed bidder on a State contract, does not have standing to seek judicial review of the award of that contract to another bidder. While we are cognizant that this standing issue was raised by defendants at trial level only as to Madden and not as to plaintiff, because the parties on appeal have argued and briefed this issue and, in our view, the matter is of significant public importance, we elect to consider plaintiff’s contention. See Doran v. Cullerton (1972), 51 Ill.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of Carbondale v. Bower
773 N.E.2d 182 (Appellate Court of Illinois, 2002)
Keefe-Shea Joint Venture, Inc. v. City of Evanston
773 N.E.2d 1155 (Appellate Court of Illinois, 2002)
President Lincoln Hotel Venture v. Bank One
649 N.E.2d 432 (Appellate Court of Illinois, 1994)
Amtech System Corp. v. Illinois State Toll Highway Authority
637 N.E.2d 619 (Appellate Court of Illinois, 1994)
Nichols v. Board of Education
603 N.E.2d 799 (Appellate Court of Illinois, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
487 N.E.2d 1132, 139 Ill. App. 3d 798, 94 Ill. Dec. 255, 1985 Ill. App. LEXIS 2893, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brando-construction-inc-v-department-of-transportation-illappct-1985.