BP Exploration Libya Limited v. ExxonMobil Libya L

689 F.3d 481, 2012 WL 3065317, 2012 U.S. App. LEXIS 15706
CourtCourt of Appeals for the Fifth Circuit
DecidedJuly 30, 2012
Docket11-20547
StatusPublished
Cited by35 cases

This text of 689 F.3d 481 (BP Exploration Libya Limited v. ExxonMobil Libya L) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
BP Exploration Libya Limited v. ExxonMobil Libya L, 689 F.3d 481, 2012 WL 3065317, 2012 U.S. App. LEXIS 15706 (5th Cir. 2012).

Opinion

E. GRADY JOLLY, Circuit Judge:

BP Exploration Libya Limited (“BP”), ExxonMobil Libya Limited (“Exxon”), and Noble North Africa Limited (“Noble”) are entangled in a disagreement over the appointment of arbitrators to hear and decide their dispute related to the alleged breach of an assignment agreement. The case arises from an underlying dispute impheating the interests of these three parties, under an agreement to arbitrate that seems designed for a two-party dispute. Notwithstanding that the parties agreed to arbitrate before three arbitrators, the district court, in an effort to fit the arbitration agreement to the dispute at hand, ordered the parties to proceed to arbitration before five arbitrators: three party-appointed arbitrators, who then would choose two neutral arbitrators. If the party-appointed arbitrators could not agree, the district court ordered the parties to petition the Secretary-General of the Permanent Court at The Hague (the “PCA”) for appointment of the two neutral arbitrators. Now on appeal, we hold that there was a lapse in the naming of arbitrators in the parties’ agreement, that the district court was authorized to exercise appointment power under 9 U.S.C. § 5, and that the district court erred in deviating from the parties’ express agreement to arbitrate before a three-member panel. Accordingly, we AFFIRM in part, VACATE the district court’s judgment, and REMAND for further proceedings, not inconsistent with this opinion.

I.

A.

On March 31, 2009, Noble and Exxon entered into and executed a Drilling Services Agreement (“Drilling Agreement”). Noble agreed to provide offshore drilling contractor services to Exxon, specifically the use of Noble’s semi-submersible drilling rig, the Noble Homer Ferrington (the “Rig”), to drill certain deepwater oil wells for Exxon in the waters off of Libya. On March 3, 2010, Exxon and BP entered into *484 an Assignment Agreement, wherein Exxon agreed to assign, and BP agreed to assume, the Drilling Agreement for the time necessary for BP to drill two deepwater oil wells in those Libyan waters. The Assignment Agreement required Noble, who consented to the assignment, to maintain the Rig according to the safety and operational standards provided in the Drilling Agreement. Under the terms of the Assignment Agreement, BP agreed to take possession of the Rig and assume Exxon’s obligations no later than June 1, 2010.

In anticipation of acceptance, BP conducted an inspection of the Rig in late April 2010. BP found several problems that implicated the Drilling Agreement’s safety and operational requirements. BP orally and in writing informed Exxon of its concerns and requested that Exxon address the problems to BP’s satisfaction before BP accepted assignment of the Rig and Drilling Agreement. Noble also was informed of the problems in a detailed report. Although Exxon initially agreed with BP that the Rig was “not ready to perform in accordance with the drilling contract and with good oilfield practices,” it eventually took the position, after Noble had received certain parts for the Rig, that the Rig was assigned to BP effective June 30, 2010.

BP conducted additional inspections of the Rig that summer, but remained unsatisfied with the Rig’s condition and so informed Exxon after the final inspection in late July. Exxon responded on August 2, informing BP that it should continue working with Noble to resolve the issues, consistent with the Rig’s assignment to BP as of June 30, 2010. That same day, Exxon informed Noble by letter that BP was responsible for paying Noble for its services from June 30, 2010 until the end of the Assignment Period. In response, BP informed Exxon that Noble should not send invoices to BP because assignment of the Rig had yet to occur, and until BP was satisfied that the Rig complied with the Drilling Agreement’s requirements, BP disclaimed any contractual relationship with Noble. By subsequent letter dated August 16, 2010, BP informed Exxon and Noble that, because the two parties had materially breached the Assignment Agreement, it was exercising its right to terminate the agreement. BP’s letter, moreover, disclaimed any obligation to pay either party under the agreement.

The Drilling Agreement and Assignment Agreement contain arbitration provisions that govern any disputes arising out of the respective agreements. But the Assignment Agreement’s arbitration provision, found in Section 33, contemplated two different arbitration scenarios: arbitration over a dispute between Exxon and BP; and arbitration over any dispute to which Noble was a party. Specifically, in the Assignment Agreement, the parties agreed:

Any difference arising out of or in connection with the terms of the Assignment Agreement (regardless of the nature of the question or dispute) shall as far as possible be settled amicably. Failing an amicable settlement within (3) three months of the written notification by one party to the other of a difference, or such longer period as the parties may agree, any dispute or difference arising out of [sic] relating to this Assignment Agreement shall be referred to arbitration before three (3) arbitrators in accordance with the International Arbitration Rules of the American Arbitration Association. Each Party shall appoint one (1) arbitrator. The two (2) arbitrators so appointed shall appoint the third arbitrator, who shall chair the arbitral tribunal ....
*485 For avoidance of doubt, the parties agree that the dispute resolution mechanism in this section 3[3] shall apply only to disputes between [Exxon] and [BP] and that any disputes to which [Noble] is a party shall be governed by the language contained in Sections 18.1 and 18.2 of the [Drilling] Agreement which are incorporated by reference herein and made a part hereof for such purpose as though set out in full herein.

Section 18.1 of the Drilling Agreement simply provides that the “General Maritime Law of the United States” shall govern the validity of the Drilling Agreement and all matters pertaining thereto. We are concerned, for purposes of this appeal, with Section 18.2 of the Drilling Agreement, which states in relevant part: “Any dispute arising out of, or in connection with, this contract shall be finally settled by arbitration under the rules of the Arbitration and Conciliation Act 1990, by three (3) arbitrators appointed in accordance with such rules ____” Thus, for any dispute to which Noble was a party arising out of the Assignment Agreement, BP and Exxon and Noble agreed to arbitrate before three arbitrators appointed in accordance with the rules of the Arbitration and Conciliation Act 1990 (“ACA”).

Incorporated as part of the Laws of the Federation of Nigeria, the ACA is based on the 1985 UNCITRAL 1 Model Law on International Commercial Arbitration, and the 1976 UNCITRAL Arbitration Rules (“1976 UNCITRAL Rules”). The ACA consists of four Parts and three Schedules. Part I relates to arbitration, in general; Part II relates to conciliation; Part III contains additional provisions relating to international commercial arbitration and conciliation; and Part IV contains miscellaneous provisions.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
689 F.3d 481, 2012 WL 3065317, 2012 U.S. App. LEXIS 15706, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bp-exploration-libya-limited-v-exxonmobil-libya-l-ca5-2012.