Boyland v. Southern Structures, Inc.

615 S.E.2d 919, 172 N.C. App. 108, 2005 N.C. App. LEXIS 1434
CourtCourt of Appeals of North Carolina
DecidedAugust 2, 2005
DocketCOA04-1235
StatusPublished
Cited by5 cases

This text of 615 S.E.2d 919 (Boyland v. Southern Structures, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Boyland v. Southern Structures, Inc., 615 S.E.2d 919, 172 N.C. App. 108, 2005 N.C. App. LEXIS 1434 (N.C. Ct. App. 2005).

Opinions

TIMMONS-GOODSON, Judge.

Employment Security Commission of North Carolina (“ESC” or “the Commission”) appeals an order of the trial court wherein the trial court held that Brad Boyland (“petitioner”) was qualified to [110]*110receive unemployment benefits. For the reasons stated herein, we affirm the order of the trial court.

The factual and procedural history of this case is as follows: Petitioner was employed by Southern Structures, Inc. (“employer”) as a construction job superintendent from February 2000 until he was discharged in May 2002. On 16 June 2002, petitioner filed a claim with ESC for unemployment insurance benefits. Upon review of the claim, the ESC adjudicator concluded that petitioner was qualified for benefits.

Employer appealed the ruling to an ESC appeals referee. The referee conducted an evidentiary hearing, made findings of fact and entered the following conclusion of law: “It is concluded from the competent evidence in the record that the claimant’s job performance did not meet the reasonable expectations of the employer. As such, the claimant was discharged for substantial fault on his part connected with the work.” The referee held that “[claimant is disqualified for unemployment benefits for a period of nine weeks beginning June 16, 2002 and ending August 17, 2002.”

Petitioner appealed the referee’s decision to the Commission. Upon review of the case, the Commission concluded “that the facts found by the Appeals Referee are supported by competent and credible evidence contained in the record.” The Commission further concluded that “the Appeals Referee properly and correctly applied the Employment Security Law (G.S. §96-1 et seq.) to the facts as found, and the resultant decision was in accordance with law and fact.” The Commission affirmed the referee’s decision.

Petitioner then filed a petition for judicial review with the superior court, arguing that the evidence did not support the findings of fact, and the findings did not support the conclusion of law that petitioner was discharged for substantial fault. Upon review of the matter, the superior court found as a fact that the Commission failed to find whether petitioner violated an explicit policy and whether petitioner was warned regarding his conduct. The superior court concluded the findings of the Commission were not sufficient to support its conclusions of law that petitioner was discharged for substantial fault. The superior court remanded the matter to ESC for “another evidentiary hearing and the issuance of a new decision.”

A second evidentiary hearing was conducted by the appeals referee and additional testimony was admitted into evidence. Upon con[111]*111sideration of this new evidence, the referee made the following pertinent findings of fact:

4. The claimant was discharged from this job for poor job performance.
5. The claimant was hired to train as a construction job superintendent under Ms. Faw and the then superintendent. When the superintendent left in April or May 2001, Ms. Faw left the claimant as the superintendent and continued the training.
6. The employer does not have an employee handbook nor does she have a list of company rules and regulations.
7. On or about October 30, 2001, Ms. Faw gave the claimant his evaluation. Some of the problems with his performance were his attitude towards some of the employees especially when it came to clean up that the claimant did not think was part of his job although everyone was responsible for handling it. She counseled him that he needed to be more observant and organized on the job site. He was to oversee the subcontractors and make sure deliveries were correct. She advised him that taking notes, or better notes, during meetings would help him in his observations and organization and would be something he could refer back to as the project progressed to make sure the work as being properly performed. It was also discussed that punch list items needed to be taken care of sooner, that the credit card was to only be used for business purposes, and that paperwork of what he did each day needed to be kept and turned in on a weekly basis to track what he had done each day.
8. In December 2001, Ms. Faw hired Mr. Rhoades as the project manager because she had not seen an improvement in the claimant’s job performance. Ms. Faw told the claimant that he would be working under not only her supervision but also that of Mr. Rhoades.
9. The claimant did not timely follow instructions of Mr. Rhoades. One specific instance related to covering a floor. Ms. Faw had told the claimant in the past that she liked the work he did in covering the floors and that she preferred that he did it rather than another employee. Mr. Rhoades gave the claimant instructions to cover a certain floor at least twice but it was not until Ms. Faw instructed him to do it that he did it.
[112]*11210. The claimant was sent to a trade show in Atlanta. He was instructed to get information on how to create a daily log of work performed by a superintendent. The claimant got information and beginning February 2001, claimant was instructed to keep a daily log of the work he performed, the amount of time spent, and what was being done at each job site. The claimant was instructed to turn the daily logs in every two weeks with his time sheet. He was given a palm pilot to keep his notes along with a keyboard.
11. Claimant was able to keep detailed daily log notes and was able to turn them in every two weeks for the period of February 2, 2001 through March 14, 2001. Ms. Faw was pleased with the notes.
12. Claimant stopped keeping notes for the period of March 15, 2001 through August 5, 2001.
13. Claimant started to keep notes again beginning August 6, 2001 but failed to turn them in every two weeks as required. Ms. Faw asked him several time[s] to turn them in and even suggested that claimant give Ms. Summey his palm pilot and she would print the notes out. Claimant did not do this. Even Ms. Summey asked claimant for his daily logs but he failed to turn them in when requested. Claimaint[] failed to follow the employer’s directive because he unreasonably thought that Ms. Faw and Ms. Summey were joking about the need for him to turn them in.
14. The claimant was out sick one time and did not notify Ms. Faw or Ms. Summey that he was going home sick. He was told in the future that he needed to call if he was going to be absent. Claimant was out again due to the flu and failed to call despite having been warned.

The referee made the following conclusion: “It is concluded from the competent evidence in the record that the claimant’s job performance did not meet the reasonable expectations of the employer. As such, the claimant was discharged for substantial fault on his part connected with the work.” The referee’s decision disqualified petitioner for unemployment benefits for nine weeks.

Once again, petitioner appealed the referee’s decision to the Commission. Upon review of the case, the Commission ruled in pertinent part as follows:

[113]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Johnson v. NASH COMMUNITY COLLEGE
673 S.E.2d 800 (Court of Appeals of North Carolina, 2009)
Carolina Power & Light Co. v. Employment Security Commission
665 S.E.2d 141 (Court of Appeals of North Carolina, 2008)
Boyland v. Southern Structures, Inc.
615 S.E.2d 919 (Court of Appeals of North Carolina, 2005)
Trotter v. State
455 S.E.2d 121 (Court of Appeals of Georgia, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
615 S.E.2d 919, 172 N.C. App. 108, 2005 N.C. App. LEXIS 1434, Counsel Stack Legal Research, https://law.counselstack.com/opinion/boyland-v-southern-structures-inc-ncctapp-2005.