Boyce v. Expanded Metal Fire Proofing Co.

136 Ill. App. 352, 1907 Ill. App. LEXIS 629
CourtAppellate Court of Illinois
DecidedOctober 4, 1907
DocketGen. No. 13,262
StatusPublished
Cited by3 cases

This text of 136 Ill. App. 352 (Boyce v. Expanded Metal Fire Proofing Co.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Boyce v. Expanded Metal Fire Proofing Co., 136 Ill. App. 352, 1907 Ill. App. LEXIS 629 (Ill. Ct. App. 1907).

Opinion

Mr. Justice Smith

delivered the opinion of the court.

By the written contract entered into on June 18, 1902, between appellant and appellee, the latter was to place in the machine room and beater room of appellant’s mill building an expanded metal and concrete floor to carry a load of 250 pounds per square foot, the floor to have a finished surface of sand and cement one and one quarter inches thick, trowelled to a smooth surface and graded to gutters as shown on plans. The roof of the beater room and machine building as shown by the plans was to be composed of cinder concrete, and to be four inches thick and broomed with stand and cement ready for tar and gravel roof. The cinder concrete was to be one part cement, two parts sand and five parts cinders. The floors of the building were to be composed of one part cement, two parts sand and five parts gravel. The top dressing was to be composed of one part cement and two parts sand. All beams and girders in the building were to be covered with concrete, and soffits were to be lathed with metal lath and left ready to plaster. The drawings and specifications referred to are made a part of the contract.

The work provided for in the contract was to be completed within thirty days after the roof iron was put in place in the machine room. Appellant agreed to pay for the work and materials the sum of $8,600.

It is urged as a ground of reversal that it is a well-settled rule in this jurisdiction in order to recover under the common counts upon a special contract the plaintiff must have fully performed the contract on his part, and unless upon the trial such appears to be the fact a recovery cannot be had; and that the evidence on the part of appellee fails to show performance on its part.

The ground of this contention was laid in the record by an objection by appellant to the contract when it was offered in evidence by appellee; and also by a motion on the part of appellant to exclude the contract, architect’s certificate and all the evidence offered in behalf of appellee, except that portion relative to the rental value of the engine of appellee used by appellant.

Under the evidence relating to the manner of securing the certificate of Ambursen, the architect, the certificate was properly excluded by the court. This left appellee’s case to rest entirely upon the evidence offered by appellee tending to show that it had substantially performed its part of the contract, and that Ambursen, the architect, had been discharged by appellant before the work was commenced under the contract, and had nothing whatever to do with the work during its progress.

By the terms of the contract appellee was bound to procure the certificate of the architect to the performance of the work as provided in the contract, and the amount due to it, or show a good excuse- for not procuring it, before it could recover under the common counts. This was the evidence of completion and of the amount due agreed upon by the parties, and was a substantial provision of the contract.

It is insisted by appellee that the evidence shows that the architect’s certificate was waived by the parties, and that after the certificate was excluded as evidence, appellee’s case was allowed to go to the jury, and a recovery under the common counts was allowed by the trial court upon that theory.

In our opinion this contention of appellee is sustained by the evidence and the law. The evidence shows without controversy that the architect named in the contract had been discharged, as above stated, before the work under the contract between the parties was commenced. The architect named did not direct the work or have anything to do with it. He went to Watertown, Hew York, when his connection with appellant was severed, and remained there during all the time the work was in progress. Appellant made several payments to appellee as the work progressed, without requiring any architect’s certificate. These facts with others shown by the record were sufficient evidence to warrant the jury in finding that the provisions of the contract regarding the payments on architect’s certificates and the procuring of the certificates by appellee were waived by the parties who participated in acts done in disregard of those provisions. Upon this evidence a recovery can be had under the common counts, without an averment in the declaration of the waiver, if the evidence also shows that the contract was performed and nothing remained to be done but to pay the amount due. Evans v. Howell, 211 Ill., 85, 92, and cases there cited. See also C. & E. I. R. R. Co. v. Moran, 187 Ill., 316; German Fire Ins. Co. v. Grunert, 112 id., 68; Continental Life Ins. Co. v. Rogers, 119 id., 474; City of Elgin v. Joslyn, 36 Ill. App., 301. A provision of a contract once waived is no longer a part of the contract. It is gone forever. It is therefore unnecessary to perform it, or aver it, or prove it. Continental Life Ins. Co. v. Rogers, supra.

We do not find anything said in Hart v. Carsley Mfg. Co., 221 Ill., 444, which conflicts with or overrules the above cases. In that case it is held that an excuse for nonperformance, and performance, are quite different things; and an averment of performance gives no notice of an excuse for not performing, and is therefore not good pleading where an excuse for not performing is relied upon.

Appellant assigns error upon the giving of the following instruction at the request'*'' flee:

“If you believe from the e after the first of January, It dent of the plaintiff, presente< fendant, an account of the exfc claimed that the plaintiff had mill building and that the made no objection thereto and J you are instructed that the pla’ amount stated in said.bill for e

3 in this case that shortly V. W. Eamsey, the presiVilliam D. Boyce, the deterials which said Eamsey ished for said defendant’s lant, William D. Boyce, ised to pay the same, then is entitled to recover the

One objection made to thi ceeds upon the theory of an acc

struction is that it prod stated. This, we think, is a misapprehension of the instruction. The instruction proceeds upon an express promise to pay.

Another objection urged to the instruction is that at the time appellant agreed -to pay the bill he did not know that the roof sagged, or of the cracks in the floors. This objection is not relevant because the instruction relates to the extra work done which had no connection with the roofs or floors.

The court gave to the jury, at the instance of appellee, the following instruction:

“You are instructed that if you believe from the evidence that the plaintiff and defendant entered into a contract offered in evidence in this case, and that there has been no material departure from the terms of the contract and plans, or omissions in essential points, and that the plaintiff has honestly and faithfully performed the contract in all its material and substantial particulars, then the plaintiff will not be held to have forfeited its right to remuneration by reason of mere technical, inadvertent and unimportant omissions or defects.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Halvorson v. Blue Mountain Prune Growers Cooperative
217 P.2d 254 (Oregon Supreme Court, 1950)
Halvorson v. Blue Mt. Prune Growers Co-Op.
217 P.2d 254 (Oregon Supreme Court, 1949)

Cite This Page — Counsel Stack

Bluebook (online)
136 Ill. App. 352, 1907 Ill. App. LEXIS 629, Counsel Stack Legal Research, https://law.counselstack.com/opinion/boyce-v-expanded-metal-fire-proofing-co-illappct-1907.