Bowen-McLaughlin-York Co. v. United States

33 Cont. Cas. Fed. 74,492, 10 Cl. Ct. 223, 1986 U.S. Claims LEXIS 855
CourtUnited States Court of Claims
DecidedJune 20, 1986
DocketNo. 71-82C
StatusPublished
Cited by3 cases

This text of 33 Cont. Cas. Fed. 74,492 (Bowen-McLaughlin-York Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bowen-McLaughlin-York Co. v. United States, 33 Cont. Cas. Fed. 74,492, 10 Cl. Ct. 223, 1986 U.S. Claims LEXIS 855 (cc 1986).

Opinion

OPINION

WIESE, Judge.

I.

This case involves a contract pricing dispute in which plaintiff Bowen-McLaughlin-York Company (“BMY”) seeks reformation of a fixed-price contract that it entered into with the United States Army Tank-Automotive Command (“TACOM”). The contract involved production of M88A1 tracked recovery vehicles and dieselization conversion kits for the M88 vehicle; the contract amount was $146 million. At issue are certain escalation costs on purchased materials which were omitted from the final agreed-upon contract price by oversight on BMY’s part. The amount in question, exclusive of contractor-added markups, is approximately $700,000. BMY argues its entitlement to reformation of the contract price on alternative theories of unilateral and mutual mistake.

The case had been previously before the court on the parties’ cross-motions for summary judgment directed to the unilateral mistake argument. These motions were denied by order dated November 29, 1985, and the case subsequently went to trial on March 18 through March 21, 1986 to hear evidence on both mistake theories. On the basis of the evidence disclosed at trial, the court has made findings of fact which appear in the appendix to this opinion. From those facts, we conclude that plaintiff is not entitled to prevail as a matter of law. The reasons which dictate this result are given below; for purposes of the discussion we assume a familiarity with the facts as given in the appendix.

II.

A.

Mistake, as that word is used in the law of contracts, refers to a belief that is not in accord with existing facts. Restatement (Second) of Contracts § 151 (1981). Such a belief, even when not shared by the other party to a contract, may under certain circumstances be recognized as a basis for rescission of an agreement or for its reformation. The Restatement, § 153, states the rule applicable to cases where relief for unilateral mistake may be allowed:

Where a mistake of one party at the time a contract was made as to a basic assumption on which he made the contract has a material effect on the agreed exchange of performances that is adverse to him, the contract is voidable by him if he does not bear the risk of the mistake under the rule stated in § 154, and
(a) the effect of the mistake is such that enforcement of the contract would be unconscionable, or
(b) the other party had reason to know of the mistake or his fault caused the mistake.

With respect to the foregoing, the court previously ruled in its order of November 29, 1985 that the pricing error involved here qualified as a material mistake as to a basic assumption, the risk of which the contract had not expressly allocated to either party. Left for trial and later decision was the issue we now confront: whether the individuals who negotiated the contract on behalf of the Government had reason to know that BMY had unintentionally omitted escalation costs on certain purchased ordnance parts (components of the M88A1 vehicle) at the time that it agreed to the fixed price.

“Reason to know” is the Restatement’s analytically more precise term for “constructive knowledge”. The Restatement explains that “[a] person has reason to know a fact, present or future, if he has information from which a person of ordinary intelligence would infer that the fact in question does or will exist.” Restatement (Second) of Contracts § 19 comment b (1981). The comment continues on to say that “reason to know” is to be used “both where the actor has a duty to another and where he would not be acting adequately in the protection of his own interests were he [225]*225not acting with reference to the facts which he has reason to know.” Id.

As applied in the context of Government contracting, we deem the “duty” referred to as involving no more than the Government’s basic obligation to honestly and fairly evaluate a prospective contractor’s submission (the proposal or the bid) in accordance with the solicitation criteria and applicable procurement regulations. And, in discharging this duty to the contractor, the Government may be viewed as simultaneously acting in the protection of its own interests. Thus, in the typical procurement context, it fits the situation to say that even though the Government may be ignorant in fact of mistakes in the contractor’s submission, still it will be charged with the knowledge thereof if, under like circumstances, a person of ordinary intelligence1 would have been led to infer the existence of the mistake or its reasonable possibility.

In the present case, the Government did undertake a review of BMY’s cost and price submissions. In fact, it went well beyond that: the Government twice had occasion to examine the underlying data, once by the Defense Contract Audit Agency (“DCAA”) and later by TACOM. In the course of these reviews the Government confronted the purchase orders which showed that BMY was acquiring certain parts pursuant to contracts whose prices were subject to escalation.

Indeed, it is clear that TACOM personnel not only had access to but, more importantly, possession of a number of documents whose texts bore reference to this fact. These documents included copies of: (i) a BMY memorandum of negotiations with Berwick Forge and Fabricating Company (one of the two suppliers whose escalation costs BMY failed to identify) which noted the parties’ agreement to an order price of “$14,117.56 per set plus an Economic Price Adjustment, Code 10”,2 (ii) the June 1977 “Procurement Plan for Award of 140 Sets of Castings to Buckeye Steel Castings Company” (the other supplier whose prices were subject to escalation) which identified the pricing provision of the purchase order to be issued as a “Firm Fixed Price w/Economic Adjustment Clause (Material Only) Code 10 Metal and Metal Products”, and (iii) a DCAA audit report covering BMY’s interim pricing which contained footnotes identifying that certain ordnance parts were subject to price escalation.

Based on this evidence, it seems certain that the Government negotiators, at some point during the cost verification and price negotiation processes, at least scanned documents which, if carefully considered side-by-side, bespeak the mistake’s existence. When considered in context, however, this finding does not lead to a conclusion that the Government negotiators had reason to know that BMY had failed to include any allowance for price escalation in its final proposed material costs. Several reasons require this result.

In the context of this procurement, which involved BMY’s purchase of over 3,000 ordnance parts per vehicle, information concerning the possibility of price escalation on sixteen of those parts was not so significant in its own right as to have forged itself upon one’s memory. And this would be true even though those parts were being acquired under two purchases each of which represented a sizeable percentage of the total vehicle cost—roughly 18 percent in the case of the Buckeye order and approximately 7 percent in the case of the Berwick order. Moreover, the information [226]*226concerning escalation that appeared in the above-mentioned documents was not displayed in such fashion as to arrest a reader’s attention. Generally, the reference to escalation appeared as part of a single paragraph in a multi-page document.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
33 Cont. Cas. Fed. 74,492, 10 Cl. Ct. 223, 1986 U.S. Claims LEXIS 855, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bowen-mclaughlin-york-co-v-united-states-cc-1986.