Bourlas Constr., Inc. v. Paxos
This text of 2014 Ohio 289 (Bourlas Constr., Inc. v. Paxos) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
[Cite as Bourlas Constr., Inc. v. Paxos, 2014-Ohio-289.]
COURT OF APPEALS STARK COUNTY, OHIO FIFTH APPELLATE DISTRICT
BOURLAS CONSTRUCTION, INC. JUDGES: Hon. W. Scott Gwin, P.J. Plaintiff-Appellee Hon. William B. Hoffman, J. Hon. Patricia A. Delaney, J. -vs- Case No. 2013CA00076 MICHAEL PAXOS, ET AL.
Defendants-Appellants OPINION
CHARACTER OF PROCEEDING: Appeals from the Stark County Court of Common Pleas, Case No. 2013CV00350
JUDGMENT: Affirmed
DATE OF JUDGMENT ENTRY: January 27, 2014
APPEARANCES:
For Plaintiff-Appellee For Defendants-Appellants
GARY A. CORROTO MARIO GAITANOS EDMOND J. MACK 437 Market Avenue North MARIA C. KLUTINOTY EDWARDS Canton, Ohio 44702 Tzangas, Plakas, Mannos, Ltd. 220 Market Avenue South Eighth Floor Canton, Ohio 44702 Stark County, Case No. 2013CA00076 2
Hoffman, J.
{¶1} Defendants-appellants Michael Paxos, et al. (hereinafter “Paxoses”)
appeal the April 9, 2013 Order entered by the Stark County Court of Common Pleas,
which granted plaintiff-appellee Bourlas Construction, Inc.’s (hereinafter “Bourlas”)
Motion for Order Compelling Arbitration and Staying Action.
STATEMENT OF THE FACTS AND CASE
{¶2} On June 15, 2006, Bourlas and Michael and Maria Paxos executed a
contract for the construction of an addition to their home at 1625 Slate Run Circle,
Northeast, North Canton, Ohio (“the Contract”). The Contract price was $412,533.
{¶3} After construction began in July, 2006, the Paxoses requested Bourlas
make additional changes to the construction to be performed and the materials to be
used. Bourlas agreed and completed the requested changes. The Contract included a
provision relative to changes and additions thereto, which reads:
All changes or additions to the plans and specifications made after
the signing of this agreement shall be submitted from the owner to the
contractor and shall be approved in writing by the contractor, and both the
work and price therefore shall be approved in writing by the contractor and
owner before the work is done, or the materials are purchased. These are
called “change orders.” All change orders will be paid for in full by the
owner before the work will be done.
{¶4} The Contract specifically provided any change order would thereafter
“become part of this contract.” However, the parties never executed any written change
orders. All change orders were verbally requested and verbally approved. Stark County, Case No. 2013CA00076 3
{¶5} Bourlas completed the construction in early 2009. The Paxoses paid
Bourlas the entire Contract amount of $412,533, as well as $150,000, for additional
work. Approximately three years later, Bourlas advised the Paxoses they owed an
additional $450,000+ for the work performed pursuant to the change orders. The
Paxoses refused to pay the additional charges.
{¶6} Bourlas filed a complaint against the Paxoses, seeking declaratory
judgment, or, in the alternative, breach of contract, unjust enrichment/quantum meruit,
and breach of implied contract. Bourlas also filed a Motion for Order Compelling
Arbitration and Staying the Action. After the trial court granted them leave to plead, the
Paxoses filed an answer and counterclaim as well as a memorandum in opposition to
Bourlas’ motion to compel arbitration.
{¶7} Via order filed April 9, 2013, the trial court granted Bourlas’ motion to
compel arbitration, finding Bourlas’ claims were arbitratable pursuant to the terms of the
Contract.
{¶8} It is from this judgment entry, the Paxoses appeal, raising the following as
error:
{¶9} “I. THE TRIAL COURT ERRED IN ORDERING THE PARTIES TO
ARBITRATE A DISPUTE ARISING FROM A VERBAL AGREEMENT.”
I
{¶10} Arbitration is a matter of contract. Benjamin v. Pipoly, 155 Ohio App.3d
171, 2003–Ohio–5666, at ¶ 31–34. (Citations omitted.) In interpreting an arbitration
clause, courts must apply the fundamental principles of Ohio contract law. Id. If the
language of the contract is clear and unambiguous, the court's interpretation is a matter Stark County, Case No. 2013CA00076 4
of law. State ex rel. Parsons v. Fleming (1994), 68 Ohio St.3d 509, 511, 628 N.E.2d
1377.
{¶11} The Contract expressly required all disputes arising between the parties
be submitted to binding arbitration and reads as follows:
ARBITRATION. In the event that any dispute arise between the
parties to the meaning or in interpretations of any provisions of this
agreement and the exhibits attached, or if any disputes arise as to the
proper performance of any part of the work in the structure of the structure
and the parties are unable between themselves to resolve in such a
dispute, it is mutually agreed upon that the parties will submit said
disputes for arbitration. Any such arbitration shall be conducted with each
of the parties’ arbitrators. Any arbitrator appointed should be either a
registered architect or a competent structure contractor. A decision of any
two of the three arbitrators shall be conclusive on each issue that might be
submitted to arbitration.
{¶12} We find the arbitration clause at issue herein is clear and unambiguous.
However, the issue remains as to whether the trial court correctly found Bourlas' claims
concerning the verbal “change orders” were subject to the arbitration provision.
{¶13} The Paxos maintain Bourlas’ claims are not subject to the arbitration
clause because the parties did not contractually agree to arbitrate claims arising from
their verbal agreement. We disagree.
{¶14} We find the parties, through their course of conduct, mutually altered the
Contract by not requiring the change orders to be in writing, rather the change orders Stark County, Case No. 2013CA00076 5
could be verbally made and approved. Accordingly, we find the parties waived the
written change order provision. Although the parties waived this requirement, such
waiver did not waive the arbitration provision requiring “any dispute” be submitted to
arbitration. We find the change orders were not new individual contracts as argued by
the Paxoses but rather were “changes” to the contract. All of the change order work
flowed from the original Contract; therefore, any dispute relative thereto is subject to the
arbitration provision.
{¶15} Bourlas cites to this Court’s decision in Memmer Constr., Inc. v. Craig, 5th
Dist. App. No. 2002CA00144, 2002-Ohio-7008, for the proposition provisions of a
contract relative to change orders may be waived by the parties due to their course of
dealing. While we agree the parties herein, like the parties in Memmer, waived the
written change order provision of the Contract due to their course of dealing, we note
the parties in Memmer were not disputing the applicability of an arbitration provision. In
fact, the appellants in Memmer were appealing judgment following a bench trial.
{¶16} The Paxoses’ sole assignment of error is overruled.
{¶17} The judgment of the Stark County Court of Common Pleas is affirmed.
By: Hoffman, J.
Gwin, P.J. and
Delaney, J. concur
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
2014 Ohio 289, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bourlas-constr-inc-v-paxos-ohioctapp-2014.