Bos v. Dolajak

534 P.2d 1258, 167 Mont. 1, 1975 Mont. LEXIS 519
CourtMontana Supreme Court
DecidedMay 5, 1975
Docket12787
StatusPublished
Cited by26 cases

This text of 534 P.2d 1258 (Bos v. Dolajak) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bos v. Dolajak, 534 P.2d 1258, 167 Mont. 1, 1975 Mont. LEXIS 519 (Mo. 1975).

Opinion

MR. CHIEF JUSTICE JAMES T. HARRISON

delivered: the Opinion of the Court.

This is an appeal from a judgment entered following a jury-verdict rendered in the district' court of Gallatin County.

*3 From the record it appears that plaintiffs Gary Bos and 'Steven Bos, contracted with defendants, Mike Dolajak and Dolajak Manufacturing Co., Inc., residents of North Dakota, for the construction of a metal silo on plaintiffs’ dairy farm near Bozeman. Plaintiffs purchased the silo secondhand from the manufacturer, who had repossessed it in California shortly after it had been installed there. The silo was dismantled and shipped to Montana where defendants agreed to erect it for the sum of $6,500 for labor, all materials to be furnished by plaintiffs.

Defendants constructed a concrete base and on June 12, 1972, Mike Dolajak arrived at the Bos ranch to personally supervise the erection of the main portion of the silo by his ■corporation. The general construction procedure consisted of placing the top of the silo and two rings on the base ring and then jacking this portion up and adding additional rings until the silo was completed. In this case Dolajak utilized eight inside jacks although the construction manual specifically required the use of twelve jacks during the erection procedure in a 36 foot diameter silo. The silo was suspended in the air ■on cables hanging down from each jack and due to its unstable nature was required to be lowered and bolted to the base ring in the event of bad weather and at night. During the erection of the silo one of the jacks broke leaving seven jacks remaining to hold the approximately 20,000 pound weight of the silo. Dolajak’s men had also allowed the silo to twist so that it could not be readily lowered and affixed to the base ring. Dolajak at no time made any effort to stabilize the silo by use of guy wires or any other device.

An expert witness for plaintiffs stated guy wires were always utilized as a standard construction procedure and that he would not allow his men to work on a job without guy wires. Also, standard construction procedures required that one insure the stiffeners were at all times in a line; that all jacks *4 were working; and, that weather conditions be closely monitored.

On the afternoon of June 16, 1972, when the silo was approximately 60 feet in the air and within a few hours of completion, a windstorm developed throwing the silo off its-foundation and virtually destroying it.

After the silo was blown down, Dolajak returned to North. Dakota and made no attempt or offer to assist in removal, of the silo or to make specific arrangements for the erection of a second silo. As a result, the entire decision as to the-action to be taken was thrust upon the shoulders of the Bosbrothers, both as to removal of the old silo and any salvage, as well as re-erection of the silo. "With their limited knowledge-of construction procedures, plaintiffs undertook to remove-the damaged silo and to salvage whatever items they could. They estimated approximately 1200 man hours were required, to complete the salvage and removal operation. Plaintiffs were-then required to determine what additional materials would, be required for erection of the silo and to secure these items. No other used silos were available at the time and to purchase-a new silo, exclusive of the cost of erection, would have cost-$40,000.

Plaintiffs purchased the materials necessary for repairs and reconstruction of the silo. They presented proof of alleged damages in these amounts: Costs of replacing the downed silo-—$15,342.61; losses resulting from inability to use the silo- • — $9,932; a total of $25,274.61. Against these alleged damages-was an offset of $2,900, alleged to be the value of the concrete-base which was not damaged. Plaintiffs claim the evidence clearly shows damages of $22,374.61.

Defendants admit to damages in the maximum total of $8,-695.60, arrived at by taking the value of the silo before it was damaged, and subtracting the salvage value.

The jury awarded $17,626.75. Defendants’ motion for new trial was denied and defendants appeal.

*5 Defendants contend the trial court erred in instructing the jury on the general measure of damages in tort and contract actions; that the damages awarded are excessive under the law and the court’s instructions; and that the verdict is contrary to the law and the evidence.

Defendants claim that in order to find damages in the amount set by the jury it had to make an award for consequential ■damages, such as the loss of milk production, corn spoilage, baling hay and rolling feed, and the jury did this because of the court’s instructions allowing it to consider general damages as a result of negligence and also breach of contract. They insist the court should have instructed the jury solely on the appropriate measure of damages for damage to, or destruction of, personal property.

The court gave these instructions, over defendants’ objection:

“You are instructed that for the breach of an obligation arising from contract the measure of damages is the amount which will compensate the party aggrieved for all the detriment proximately caused thereby, or which, in the ordinary course of things, would be likely to result therefrom.”

This instruction follows Montana’s statute, section 17-301, B.C.M.1947.

“Every person who suffers detriment from the negligent act or omission of another person may recover from him a compensation therefor in money which is called damages. In this case detriment is the loss or harm suffered. The measure of damages is the amount which will compensate for all the detriment proximately caused thereby hereinbefore defined, whether it could have been anticipated or not.”

This instruction follows Montana’s statute, section 17-401, B.C.M.1947.

Defendants offered two instructions on the measure of damages, one where the property could not be repaired and the other where it could. These were refused, but the court did *6 give an abbreviated version of one of these instructions, which read:

“You are instructed that the owner is not entitled to have property put back into better condition than before the damage. Nor is the owner entitled to be compensated for loss of use beyond the time reasonably required to complete the necessary repairs.
“The amount awarded, if any, may not exceed the value of the property just before it was damaged.”

While it is defendants contention that in Spackman v. Ralph M. Parsons Co., 147 Mont. 500, 506, 509, 510, 414 P.2d 918, 921, this Court clearly delineated the proper measure of damages for damage to personal property, this quotation is apt here:

“As for the issue of compensatory damages, the question is. always a difficult one. In tort actions, the wrongdoer is liable, in general, for any injury which is the natural and probable consequence of the wrong. These may include both the direct and indirect, but reasonably probable, results of the wrong.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

J & D Towing, LLC v. American Alternative Insurance Corp.
478 S.W.3d 649 (Texas Supreme Court, 2016)
Dewey v. Stringer
2014 MT 136 (Montana Supreme Court, 2014)
McEwen v. MCR, LLC
2012 MT 319 (Montana Supreme Court, 2012)
Sunburst School District No. 2 v. Texaco, Inc.
2007 MT 183 (Montana Supreme Court, 2007)
Reed v. University of North Dakota
1999 ND 25 (North Dakota Supreme Court, 1999)
Burk Ranches, Inc. v. State
790 P.2d 443 (Montana Supreme Court, 1990)
Kebschull v. Nott
714 P.2d 993 (Montana Supreme Court, 1986)
Nicholson v. United Pacific Insurance
710 P.2d 1342 (Montana Supreme Court, 1985)
Big Knob Volunteer Fire Co. v. Lowe & Moyer Garage, Inc.
487 A.2d 953 (Supreme Court of Pennsylvania, 1985)
Chandler v. Madsen
642 P.2d 1028 (Montana Supreme Court, 1982)
Stensvad v. MINERS & MERCHANTS BANK, ETC.
640 P.2d 1303 (Montana Supreme Court, 1982)
Cuddy v. United States
490 F. Supp. 390 (D. Montana, 1980)
Whitaker v. Farmhand, Inc.
567 P.2d 916 (Montana Supreme Court, 1977)
Smith v. Zepp
567 P.2d 923 (Montana Supreme Court, 1977)
Agrilease, Inc. v. Gray
566 P.2d 1114 (Montana Supreme Court, 1977)
Dolajak v. State Automobile & Casualty Underwriters
252 N.W.2d 180 (North Dakota Supreme Court, 1977)
Big Sky Livestock, Inc. v. Herzog
558 P.2d 1107 (Montana Supreme Court, 1976)
Johnson v. Jarrett
548 P.2d 144 (Montana Supreme Court, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
534 P.2d 1258, 167 Mont. 1, 1975 Mont. LEXIS 519, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bos-v-dolajak-mont-1975.