Borla Performance Industries, Inc. v. Universal Tool and Engineering, Inc.

CourtCourt of Appeals of Tennessee
DecidedMay 26, 2015
DocketE2014-00192-COA-R3-CV
StatusPublished

This text of Borla Performance Industries, Inc. v. Universal Tool and Engineering, Inc. (Borla Performance Industries, Inc. v. Universal Tool and Engineering, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Borla Performance Industries, Inc. v. Universal Tool and Engineering, Inc., (Tenn. Ct. App. 2015).

Opinion

IN THE COURT OF APPEALS OF TENNESSEE AT KNOXVILLE November 20, 2014 Session

BORLA PERFORMANCE INDUSTRIES, INC. v. UNIVERSAL TOOL AND ENGINEERING, INC.

Appeal from the Circuit Court for Washington County No. 27603 Thomas J. Seeley, Judge

No. E2014-00192-COA-R3-CV-FILED-MAY 26, 2015

Borla Performance Industries, Inc. (Borla) entered into two contracts with Universal Tool and Engineering, Inc. (UTE), by the terms of which UTE was to repair and refurbish six of Borla‟s pipe bending machines, which machines are used in Borla‟s business of designing and manufacturing automobile exhaust systems. Borla later sued UTE for breach of contract, negligent misrepresentation, and violation of the Tennessee Consumer Protection Act (TCPA). Borla alleged that as a result of UTE‟s failure to timely repair and deliver the machines, which are also known as “benders,” Borla incurred lost profits in the amount of $486,166. After a four-day bench trial, the court dismissed Borla‟s negligent misrepresentation and TCPA claims; the court did grant Borla a judgment for $11,839.98 on its breach of contract claim. The trial court held that Borla failed to prove that it incurred lost profits as a result of a breach of contract by UTE. Borla appeals the trial court‟s judgment denying its claims for lost profits. Borla also appeals the court‟s judgment dismissing the TCPA claim. UTE appeals the judgment against it for breach of contract. We affirm.

Tenn. R. App. P. 3 Appeal as of Right; Judgment of the Circuit Court Affirmed; Case Remanded

CHARLES D. SUSANO, JR., C.J., delivered the opinion of the court, in which JOHN W. MCCLARTY and THOMAS R. FRIERSON, II, JJ., joined.

Mark S. Dessauer, Kingsport, Tennessee, for the appellant, Borla Performance Industries, Inc.

1 Arthur M. Fowler and Arthur M. Fowler, III, Johnson City, Tennessee, for the appellee, Universal Tool and Engineering, Inc.

OPINION

I.

In 2006, Borla decided to relocate its Michigan and California facilities to a new plant in Johnson City. In manufacturing vehicle exhaust systems, Borla uses pipe bending machines. The benders are roughly 20 feet long, four to five feet wide, four feet tall, and weigh about 8,000 pounds. In October of 2007, UTE sent its sales representative, Bill Swartz, to Borla‟s California plant to evaluate three benders. On October 27, 2007, Swartz sent an estimate to Borla for the cost of repairing and refurbishing these benders. Borla issued a purchase order on May 2, 2008 for upgrading the three benders, describing the work as follows:

Upgrade Tube Bending Machine: Replace all existing or missing original controller[s] with new UTE Windows XP based controllers. Dismantle and Replace Electrical components using existing electrical panels where feasible. Add new servo[]s to carriage. Convert chain drive to rack and pinion. Add new remote operator ped[e]stal and console. Add new safety mats (01 per machine). Paint (brush and roll) each machine to match original colors. Black oxide tool holders.

The purchase order also stated “estimated completion 3-4 weeks” and listed the “date required” as May 30, 2008. The price for the repair work on the three benders was set at $115,000. Borla shipped the three benders (the California benders) to UTE‟s plant in Johnson City, and they arrived on April 17, 2008.

At an earlier time, in January of 2008, Borla entered into another contract with UTE to service three benders that were located in Michigan. One of these benders was determined to be in such poor condition that it was not economically feasible to salvage it, so UTE was ultimately required to do work on only two of the Michigan benders (the Michigan benders). Borla shipped the Michigan benders to UTE‟s Johnson City plant in January 2008. A purchase order for the work was issued on January 16, 2008, and revised on March 12, 2008. The revised purchase order states: “Borla Owned Machinery to be Evaluated and serviced for minor repairs. All Machinery to be cleaned[,] stripped[,] and re-painted.” Regarding one of the two Michigan benders, the purchase order further specifies that work “Includes Touch Screen and Clips, repair and replace exposed wiring 2 and frayed hoses, and Labor. This machine to be Delivered to Tennessee Borla Facility in 2 weeks.” The “date required” on the purchase orders was listed as “TO BE DETERMINED.” (Capitalization in original.)

UTE worked on the Michigan Benders and had them ready to ship to Borla‟s Tennessee plant on April 15, 2008. Borla picked up the Michigan benders on April 21, 2008. According to Borla, the Michigan benders were able to power up, but “they would not operate such that they could be used by Borla in production.” Borla hired James Garen to come to its Tennessee plant, get the Michigan benders in working order, and train Borla‟s workers to operate the benders. Garen performed that work in early June of 2008, and the Michigan benders were operational on June 9, 2008. Garen charged Borla $11,839.98 for his work.

On June 12, 2008, Borla visited the UTE plant to inspect the California benders. Borla requested UTE to do a full evaluation of the California benders and report back as to what was needed to get them fully operational. On June 17, Borla authorized UTE to do the additional work suggested by UTE. After this work was completed in July of 2008, the parties discovered that the three-inch cylinders on the California benders were not big enough to bend the pipe that Borla needed in order to make parts. Borla then authorized UTE to install four-inch cylinders. On October 28, 2008, one of the California benders was delivered to the Borla plant, inspected, and found acceptable by Borla.

Frustration mounted on both sides. UTE complained that Borla frequently took parts off the California benders, or “cannibalized” them, while they were at UTE‟s plant,1 in order to allow Borla‟s other benders to function. UTE alleged that Borla took the “servo valves” from the two remaining California benders, which were essential parts, and that Borla did not provide the tooling necessary to properly test the benders. Borla expressed frustration at the delays in repairing the benders and UTE‟s perceived inability to get them in functioning order. Borla paid only $75,000 of the $115,000 invoice for UTE‟s work on the California benders. UTE kept possession of the two remaining California benders for the next several years. Borla did not provide the servo valves allegedly necessary to make the benders work until it was ordered to do so by the trial court.

Borla filed its complaint on May 4, 2009. UTE answered and counterclaimed for breach of contract. A bench trial began on August 15, 2013, and ended on August 20, 2013. In support of its claim for lost profit damages, Borla presented the testimony of its chief financial officer, Allan Stoner. He explained that Borla‟s plan for smoothly 1 Apparently, the distance between UTE‟s facility and Borla‟s plant in Johnson City was only about ten miles. 3 transitioning its manufacturing facilities from California to Tennessee depended upon Borla having the Michigan benders operational and timely delivered to Borla‟s Johnson City plant so Borla could train its employees on the benders. Borla ceased production at its California plant around July 1, 2008. Stoner summarized Borla‟s claim as follows:

had we had those machines here earlier from Michigan, we would have been able to train in the controlled environment, and then those employees that were trained would have been able to provide the bending ‒ bent materials earlier providing additional capacity and – or if we had those three machines from California at all able to provide additional capacity, we would have been able to add an amount of product that we could have sold to our customers.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Audio Visual Artistry v. Stephen Tanzer
403 S.W.3d 789 (Court of Appeals of Tennessee, 2012)
Tucker v. Sierra Builders
180 S.W.3d 109 (Court of Appeals of Tennessee, 2005)
Waggoner Motors, Inc. v. Waverly Church of Christ
159 S.W.3d 42 (Court of Appeals of Tennessee, 2004)
Kristen Cox MORRISON v. Paul ALLEN Et Al.
338 S.W.3d 417 (Tennessee Supreme Court, 2011)
Baker v. Hooper
50 S.W.3d 463 (Court of Appeals of Tennessee, 2001)
Authentic Architectural Millworks, Inc. v. SCM Group USA, Inc.
586 S.E.2d 726 (Court of Appeals of Georgia, 2003)
Oakes v. Oakes
235 S.W.3d 152 (Court of Appeals of Tennessee, 2007)
McClain v. Kimbrough Const. Co., Inc.
806 S.W.2d 194 (Court of Appeals of Tennessee, 1990)
Cloud Nine, LLC v. Whaley
650 F. Supp. 2d 789 (E.D. Tennessee, 2009)
Tire Shredders, Inc. v. ERM-North Central, Inc.
15 S.W.3d 849 (Court of Appeals of Tennessee, 1999)
Smith v. Scott Lewis Chevrolet, Inc.
843 S.W.2d 9 (Court of Appeals of Tennessee, 1992)
Walgreen Co. v. Walton
64 S.W.2d 44 (Court of Appeals of Tennessee, 1932)

Cite This Page — Counsel Stack

Bluebook (online)
Borla Performance Industries, Inc. v. Universal Tool and Engineering, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/borla-performance-industries-inc-v-universal-tool--tennctapp-2015.