Bonvillain Builders, LLC v. Gentile

29 So. 3d 625, 2009 WL 3530867
CourtLouisiana Court of Appeal
DecidedOctober 30, 2009
Docket2008 CA 1994, 2008 CA 1995
StatusPublished
Cited by8 cases

This text of 29 So. 3d 625 (Bonvillain Builders, LLC v. Gentile) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bonvillain Builders, LLC v. Gentile, 29 So. 3d 625, 2009 WL 3530867 (La. Ct. App. 2009).

Opinions

GAIDRY, J.

| .¿The owners of a professional medical office appeal a judgment against them and in favor of the contractors who constructed the office. The contractors answer the appeal, seeking damages, attorney fees, costs, and interest. For the following reasons, we affirm the judgment in part and reverse it in part, and deny the answer to the appeal.

FACTS AND PROCEDURAL HISTORY

Charon E. Gentile, M.D. is a physician practicing in Houma, Louisiana, and the sole member of a limited liability company, La Donna, L.L.C. La Donna, L.L.C. owned a municipal lot in Houma. (For convenience, we refer hereafter to Dr. Gentile and La Donna, L.L.C. jointly as “Dr. Gentile.”) Dr. Gentile obtained three bids from contractors for the construction of a medical office on the lot. She ultimately chose that submitted jointly by Bonvillain Builders, L.L.C. and Bonvillain Construction Company, Inc. (the Bonvillains).1 The total contract price was $323,819.00. The final plans for the Bonvillains’ proposal were dated October 7, 2003. The parties executed the contract on November 25, 2003, but by its terms it was effective as of its date, November 12, 2003.

The Bonvillains retained a drafting service to prepare the office floor plans and an engineering firm to prepare the structural project plans needed for the approval of the fire marshall. The latter plans bore the notation, “For Fire Marshall Approval Only.” The Bonvillains submitted the plans to the Terrebonne Parish Planning Commission of the Terrebonne Parish Consolidated Government (the parish), and a building permit was approved. However, in January 2004, before the foundation concrete was poured, the |aparish issued a cease-and-desist order, advising the Bon-villains that the construction plans did not conform to the parish building code requirement relating to drainage systems for commercial buildings. The Bonvillains again consulted their engineering firm to prepare the drainage study, which cost $5,490.00 and was completed sometime pri- or to April 13, 2004.

The drainage system’s total completed cost, including that of the drainage study, amounted to $47,422.02. Although Dr. Gentile was informed of the need for a drainage system, its final cost was not disclosed to her until the construction project was nearly complete. A dispute arose as to who was responsible for that cost, as well as certain unfinished “punch list” and other items.

On August 30, 2004, a notice of termination of work, verifying the “substantial completion” of the office pursuant to La. R.S. 9:4822(E), was executed by Bonvillain Builders, L.L.C. and La Donna, L.L.C. On October 26, 2004, the Bonvillains filed a statement of their contractor’s privilege relating to the alleged unpaid balance due in the mortgage records of Terrebonne Parish.

On April 29, 2005, the Bonvillains instituted this litigation against Dr. Gentile, filing a “Petition to Rescind Sale and for [628]*628Damages.” They alleged an unpaid balance due of $32,381.90 under the contract, representing the final 10% payment of the original contract price. They further alleged that they “abided by Terrebonne Parish codes, procedures, and governmental regulations, which required a drainage system which was not [originally] contemplated,” and that the parties “agreed upon the additional drainage system project and its costs to comply with appropriate Terrebonne Parish codes and regulations,” as well as a change order to that effect. (Emphasis added.) They claimed a net balance due for that additional cost, after a |4 credit attributable to changes in other items, in the amount of $45,813.55. Additionally, the Bonvillains alleged that Dr. Gentile “acted with artifice and misrepresentation” in failing to perform her obligations, and thus was liable to them for damages, attorney fees, and costs. They also alleged entitlement to “rental value of the property” from the time Dr. Gentile took occupancy. Finally, they sought rescission of the contract.

Dr. Gentile filed a peremptory exception, raising objections that the petition failed to state a cause of action or a right of action of the Bonvillains to seek rescission, as no contract of sale was alleged. Although the disposition of the exception is not evident from the record, on September 30, 2005, the scheduled date of hearing, the Bonvillains filed a supplemental and amending petition, clarifying that the contract was a construction contract and reiterating their demand that the contract should be rescinded or dissolved.

On March 2, 2007, Dr. Gentile answered the petition, admitting the existence and nature of the contract, but denying that she agreed to any change order relating to the drainage system. She also affirmatively alleged the Bonvillains’ failure to complete their work, as well as various defects or omissions in construction that constituted breaches of the warranty of workmanlike performance.

On April 10, 2007, Dr. Gentile instituted a separate legal action for damages against the Bonvillains, alleging that there were numerous defects in her office, all attributable to defective construction and unfinished work by the Bonvillains. The Bon-villains answered the suit, denying liability. On Dr. Gentile’s motion, her action was consolidated for trial with the earlier action instituted by the Bonvillains.

15This matter was tried on the merits on May 29, 2007. Prior to trial, the Bonvil-lains stipulated to entry of judgment requiring them to pay for reconstruction of entrance and exit driveways based upon the bid amount of a subcontractor.2 At the conclusion of the trial, the trial court issued its ruling and oral reasons for judgment, finding in favor of the Bonvillains on the issue of Dr. Gentile’s liability for the cost of the drainage system. The trial court’s judgment was signed on June 13, 2007. Both parties filed motions for new trial, which were denied by judgment signed on October 5, 2007. This appeal followed.

ASSIGNMENTS OF ERROR

Dr. Gentile contends that the trial court committed error in its interpretation of the construction contract by not enforcing the contract according to its terms, which required the Bonvillains’ work to meet the requirements of prevailing construction codes, thereby obligating the Bonvillains to bear the additional cost of the drainage system.

In their answer to the appeal, the Bon-villains contend that the trial court erred [629]*629in failing to award them nonpecuniary damages, attorney fees, and costs, and they also seek attorney fees and expenses associated with defending Dr. Gentile’s appeal and then- answer to that appeal.

STANDARD OF REVIEW

Whether a contract is ambiguous or not is a question of law. Borden, Inc. v. Gulf States Utilities Co., 543 So.2d 924, 928 (La.App. 1st Cir.), unit denied, 545 So.2d 1041 (La.1989). Where factual findings are pertinent to the interpretation of a contract, those factual findings are not to be disturbed unless manifest error is shown. Id. However, when appellate review is not premised upon any factual findings made at the trial level, but is, instead, [ (¡based upon an independent review and examination of the contract on its face, the manifest error rule does not apply. In such cases, appellate review of questions of law is simply whether the trial court was legally correct or legally incorrect. Id. This determination of a legal question is made de novo. See Bennett v. Ragon, 04-0706, p. 5 (La.App.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State of Louisiana v. Brian Moser
Louisiana Court of Appeal, 2020
Jeanes v. McBride
W.D. Louisiana, 2019
Driver Pipeline Co. v. Cadeville Gas Storage, LLC
150 So. 3d 492 (Louisiana Court of Appeal, 2014)
Renaudin v. Citigroup Global Markets Inc.
652 F.3d 88 (First Circuit, 2011)
Mangerchine v. Reaves
63 So. 3d 1049 (Louisiana Court of Appeal, 2011)
Red River Parish Port Commission v. Headwaters Resources Inc.
698 F. Supp. 2d 684 (W.D. Louisiana, 2010)
Bonvillain Builders, LLC v. Gentile
29 So. 3d 625 (Louisiana Court of Appeal, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
29 So. 3d 625, 2009 WL 3530867, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bonvillain-builders-llc-v-gentile-lactapp-2009.