Morton Buildings, Inc. v. Redeeming Word of Life Church, Inc.

744 So. 2d 5, 97 La.App. 1 Cir. 2251, 1998 La. App. LEXIS 3466, 1998 WL 781872
CourtLouisiana Court of Appeal
DecidedNovember 6, 1998
DocketNo. 97 CA 2251
StatusPublished
Cited by5 cases

This text of 744 So. 2d 5 (Morton Buildings, Inc. v. Redeeming Word of Life Church, Inc.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Morton Buildings, Inc. v. Redeeming Word of Life Church, Inc., 744 So. 2d 5, 97 La.App. 1 Cir. 2251, 1998 La. App. LEXIS 3466, 1998 WL 781872 (La. Ct. App. 1998).

Opinions

| ¡WHIPPLE, Judge.

In this dispute arising from design and construction contracts, defendants/plaintiffs-in-reconvention, Redeeming Word of Life Church, Inc. (“Redeeming Word”) and Reverend David Diamond, appeal from the judgment of the trial court, which ordered Redeeming Word to pay plaintiff, Morton Buildings, Inc., all moneys due under the contracts and dismissed Redeeming Word’s reconventional demand, which was based on alleged breach of contract. For the following reasons, we reverse.

FACTS AND PROCEDURAL HISTORY

On July 9, 1994, Reverend Diamond, pastor of Redeeming Word, entered into a design contract with Morton Buildings, Inc. (“Morton Buildings”) on behalf of the church, whereby Morton Buildings was to supply plans and specifications for the construction of a gymnasium and educational building. Thereafter, on September 6, 1994, the parties entered into a construction contract, whereby Morton Buildings agreed to construct the building for a price of $184,906.00.

Bryan Smyda, a sales representative for Morton Buildings, handled all of the contract negotiations with Reverend Diamond, and he also oversaw execution of the contracts in question on behalf of Morton Buildings. Smyda was the only Morton Buildings employee with whom Reverend Diamond dealt. In the contract negotiations stage, Reverend Diamond first indicated to Smyda that he wanted Morton Buildings to assume all responsibility for the construction project. However, Redeeming Word was unable to afford such an all-encompassing project. Thus, after further discussion, the parties agreed that Morton Buildings would construct the building, but would not perform any interi- or finishes. Redeeming Word agreed that it would provide its own subcontractors to perform the interior work, such as electrical work, plumbing, flooring and painting. The | ¡¡specific obligations of the parties in this respect were delineated in the construction contract.

Although not specifically listed in the contract as a responsibility of Morton Buildings, Smyda, as representative for Morton Buildings, agreed that he would assume responsibility for submitting the plans to the state fire marshal’s office for approval and for obtaining the building permit from the City of Baton Rouge/Parish of East Baton Rouge (“City/Parish”). Thus, when Morton Buildings completed the plans, Smyda in fact submitted the plans to the state fire marshal’s office. He later received a letter from that office, listing changes in the plans that would be required to bring the plans into compliance with the State Fire Marshal’s Act. Because of the changes necessitated by the fire marshal’s office, Morton Buildings and Redeeming Word executed a change order, whereby the necessary changes would be included in the construction contract at an additional charge to Redeeming Word of $5,195.00. Thereafter, the plans were approved by the fire marshal.

Regarding the obtaining of the building permit, Carl Jeansonne, a professional engineer with Baton Rouge Land Surveying, was hired by Redeeming Word to prepare a proposed certificate of elevation to be submitted with the permit application.1 The parties had contemplated constructing [8]*8the gymnasium at the same elevation as the church’s existing building on the property. However, when Jeansonne submitted his proposed certifícate of elevation to Smyda, Smyda became aware that there was a problem with the elevation. In the proposed elevation certificate, the elevation of the structure as reported by Jean-sonne to be [4necessary to comply with the building code was over two feet higher than the elevation initially contemplated by the parties.2

Although the construction contract specifically provided that site preparation was the responsibility of Morton Buildings, Smyda did not interpret this portion of the contract as obligating Morton Buildings to elevate the site by an additional two feet. Thus, when he related the problem with the elevation of the site to Reverend Diamond, he told Diamond that compliance with this elevation requirement would cost Redeeming Word $7,000.00 to $8,000.00 over the initial contract price for additional site preparation work. Reverend Diamond responded that this additional charge was not what the parties had agreed to and that Redeeming Word' did not have the money to pay this additional sum. Thus, Reverend Diamond indicated that he could not pay the additional charge.

Smyda then spoke with Jeansonne to determine if there was anything that could be done to remedy the situation to the mutual satisfaction of the parties. Jean-sonne told Smyda that the Parish had a variance procedure, whereby an individual could apply for a variance which, if granted, would allow the construction of a building at a lower elevation than the elevation required by the building code. Smyda, in turn, explained the procedure to Reverend Diamond, and he and Diamond agreed to apply for a variance requesting that they be allowed to construct the gymnasium at the lower elevation.

Smyda agreed that he would personally handle the procedure for applying for the variance for the construction project. In that regard, he obtained the application and filled it out. Smyda then submitted both the application for the building permit and the application for a variance in early October 1994. On | ¡November 2, 1994, the building permit was issued to Smyda, as the contact person listed on the permit application. Upon receipt of the building permit, Smyda assumed that the variance had been granted. Thus, Morton Buddings began construction of the gymnasium two or three days after issuance of the permit.

In January of 1995, when construction of the building was approximately 90% complete, the Department of Public Works for the City/Parish denied the application for flood variance for construction of the gymnasium. Inasmuch as the variance was not granted, the gymnasium, which was constructed at the lower elevation sought in the variance, ■ was not constructed in compliance with the building code. As such, Redeeming Word is unable to obtain a certificate of permanent occupancy until the building is brought into compliance with the code.3

Because the gymnasium could not be permanently occupied at the elevation at which it had been constructed and was thus totally useless to the church, Reverend Diamond, on behalf of Redeeming Word, took the position that the contract had not been completed. Thus, on behalf of Redeeming Word, he refused to make the final payment of $18,056.60 on the [9]*9construction contract. Redeeming Word also did not pay the final $2,000.00 installment due on the design services contract or the $5,195.00 due on the change order.

Subsequently, Morton Buildings filed suit against Redeeming Word, seeking payment on the contracts.4 Redeeming Word reconvened against Morton Buildings, alleging breach of the construction contract and seeking return of the contract price and damages.

| ^Following a bench trial, the trial court found that construction of the building was substantially complete, thus entitling Morton Buildings to payment on the contracts. Additionally, with regard to the reconven-tional demand, the trial court concluded that while Morton Buildings had undertaken to help Redeeming Word secure the building permit and flood variance, Morton Buildings had no duty to guarantee that the variance would be granted. Thus, the trial court found that Redeeming Word had failed to prove a breach of a contractual obligation by Morton Buildings.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

James Alan Siders v. Jane Zickler
Court of Appeals of Mississippi, 2021
Jeanes v. McBride
W.D. Louisiana, 2019
Bonvillain Builders, LLC v. Gentile
29 So. 3d 625 (Louisiana Court of Appeal, 2009)
MORTON BLDG. v. Redeeming Word of Life Ch.
835 So. 2d 685 (Louisiana Court of Appeal, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
744 So. 2d 5, 97 La.App. 1 Cir. 2251, 1998 La. App. LEXIS 3466, 1998 WL 781872, Counsel Stack Legal Research, https://law.counselstack.com/opinion/morton-buildings-inc-v-redeeming-word-of-life-church-inc-lactapp-1998.