BOC Group, Inc. v. Chevron Chemical Co., LLC

819 A.2d 431, 359 N.J. Super. 135, 50 U.C.C. Rep. Serv. 2d (West) 489, 2003 N.J. Super. LEXIS 119
CourtNew Jersey Superior Court Appellate Division
DecidedApril 3, 2003
StatusPublished
Cited by13 cases

This text of 819 A.2d 431 (BOC Group, Inc. v. Chevron Chemical Co., LLC) is published on Counsel Stack Legal Research, covering New Jersey Superior Court Appellate Division primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
BOC Group, Inc. v. Chevron Chemical Co., LLC, 819 A.2d 431, 359 N.J. Super. 135, 50 U.C.C. Rep. Serv. 2d (West) 489, 2003 N.J. Super. LEXIS 119 (N.J. Ct. App. 2003).

Opinion

819 A.2d 431 (2003)
359 N.J. Super. 135

BOC GROUP, INC., Plaintiff-Respondent,
v.
CHEVRON CHEMICAL COMPANY, LLC, Defendant-Appellant.

Superior Court of New Jersey, Appellate Division.

Argued February 19, 2003.
Decided April 3, 2003.

*433 Joseph P. La Sala argued the cause for appellant (McElroy, Deutsch & Mulvaney, Morristown, attorneys; Mr. La Sala, of counsel; Nancy McDonald and George A. Kelman, Roseland, on the brief).

*434 Michael L. Rosenberg, Trenton, argued the cause for appellant (Sterns & Weinroth, attorneys; Mr. Rosenberg, of counsel; Marshall D. Bilder and Christopher E. Torkelson, on the brief).

Before Judges SKILLMAN, CUFF and WINKELSTEIN.

*432 The opinion of the court was delivered by WINKELSTEIN, J.A.D.

Plaintiff contracted with defendant to deliver liquid nitrogen, primarily from its Michoud, Louisiana plant, to defendant's oil refinery production facility located in Belle Chase, Louisiana. Defendant uses liquid nitrogen to ensure the safe operation of its plant. Defendant claims that plaintiff repeatedly failed to timely deliver the liquid nitrogen, dropping the liquid nitrogen to dangerously low levels, compromising the safety of plant personnel. Although the contract provided that if plaintiff failed to deliver the liquid nitrogen as required defendant's sole remedy would be to purchase the product from another supplier and charge plaintiff for the additional expenses incurred, defendant did not do so, but instead terminated plaintiff's services.

Plaintiff sued defendant for breach of contract, and defendant counterclaimed. Each sought damages. The Law Division granted plaintiff's motion for partial summary judgment on liability, and defendant agreed to dismiss its counterclaim. After a damages trial before a jury, plaintiff was awarded a judgment in the amount of $1,200,000.

Defendant appealed, challenging the Law Division's denial of its motion to dismiss the complaint on the grounds of forum non conveniens; its grant of summary judgment on the issue of liability; and various evidentiary rulings at the damages trial. We conclude that defendant's arguments are without merit. Accordingly, we affirm.

I

Plaintiff is a Delaware corporation that produces liquid nitrogen. Its principal place of business is in Murray Hill, New Jersey, with a regional office in Houston, Texas. Defendant, also a Delaware corporation, has its principal place of business in San Francisco, California.

On October 1, 1991, the parties entered into a procurement contract, whereby plaintiff would supply defendant with "[a]ll [of defendant's] requirements" for bulk nitrogen. Plaintiff would deliver the nitrogen by tank trucks to Chevron's Oak Pointe Plant in Belle Chase. The contract, prepared and executed by defendant in California, was originally effective from October 1, 1991, to September 30, 1994, and was extended until August 31, 2000.

Defendant uses liquid nitrogen to "prevent fires and explosions within process equipment and systems and to assure instrumentation and control system reliability in critical process units." The nitrogen "protects plant personnel and the public from accidental toxic material discharges and prevents product contamination [from] oxygen ... which would reduce product quality and performance." More specifically, nitrogen is used to regulate the oxidation of petrochemicals (oil). Many petrochemicals at defendant's plants are maintained at high temperatures, and to keep them from quickly oxidizing, defendant keeps a nitrogen purge in the petrochemical tanks. If the nitrogen purge is not sustained, oxygen quickly enters the tank and whatever build-ups of petrochemicals which may have otherwise oxidized slowly, will oxidize quickly, resulting in an explosion. Defendant also uses nitrogen *435 "as a control substance for processes that produce nitrogen sulfide, ... a very deadly gas," which needs to be "managed very carefully."

The contract was a "requirement" contract—deliveries were based on how much liquid nitrogen defendant had in its tanks. As a result, plaintiff typically made deliveries seven days a week, and sometimes several times a day.

Under the contract's terms, defendant's exclusive remedy if plaintiff failed to timely deliver the nitrogen was "cover damages."

(B) CHEVRON'S EXCLUSIVE REMEDY FOR THE UNEXCUSED FAILURE ON THE PART OF SUPPLIER TO DELIVER PRODUCT TO CHEVRON WHEN REQUIRED HEREUNDER, WHETHER OR NOT SUCH FAILURE WAS CAUSED, IN WHOLE OR IN PART, BY ANY NEGLIGENCE, SHALL BE TO RECOVER FROM SUPPLIER THE DIFFERENCE BETWEEN THE COST TO PURCHASER OF ANY REASONABLE PURCHASE OF PRODUCT IN SUBSTITUTION FOR THE PRODUCT THAT [BOC] SO FAILED TO DELIVER AND THE LESSER PRICE OF SUCH QUANTITY OF PRODUCT HEREUNDER, REDUCED BY ANY EXPENSES SAVED BY CHEVRON.

When the nitrogen level fell below fifty percent of the total storage capacity, the operator of defendant's plant would inform plaintiff that the levels were depleting and check on the time for the next delivery. At a twenty-five percent level of nitrogen, defendant considered the situation "critical," and at a ten-percent level defendant could no longer maintain normal operation of the plant.

Defendant claims that from August 1997 through June 1998 plaintiff made twenty-one late deliveries. A representative of defendant stated that on "many more than two times," because of its dissipating nitrogen levels, defendant's personnel would have to call plaintiff to find out when the next delivery would arrive. Plaintiff would usually promise delivery within four hours; however, the delivery would typically not arrive for as long as twelve hours. On May 19, 1998, defendant's nitrogen supply became so low that it had to connect its own nitrogen cylinders to the hot oil surge tank to maintain operation.

That same month, Steven Earle, defendant's operations supervisor, decided to terminate the contract with plaintiff and find another liquid nitrogen supplier. He testified that he opted to terminate the contract rather than seek cover damages because he could not find alternate suppliers to deliver the required nitrogen. He claimed other suppliers were hesitant "to come in and infringe on an existing contract,..." He did not know, however, which suppliers interpreted the contract that way. Although he believed that Air Products, a company that delivered nitrogen to defendant's other plants, as well as other chemicals to defendant's Belle Chase plant, "would have been one of them," Dennis H. Boushie, an Air Products representative, testified otherwise. He said that in early 1998, when a representative of defendant told him of defendant's problems with low nitrogen inventory levels, he represented that Air Products "had the product" and could supply the product to defendant. Allen Jackson, defendant's purchasing manager, confirmed this conversation. Although no agreement materialized from the discussion, Air Products did cover defendant's liquid nitrogen supply on one occasion, in September 1998 during a hurricane.

Earle also acknowledged, however, that when he made his decision to terminate *436 the contract in May 1998 he was not aware of the exclusive remedy provision in the contract. In fact, he had not read the contract. When asked what he thought the parties "envisioned" when the contract was drawn concerning what Chevron would do if BOC failed to supply sufficient amounts of nitrogen, Earle did not know.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Shore Star Properties, LLC v. Kolbe & Kolbe Millwork Co., Inc.
New Jersey Superior Court App Division, 2025
Krivulka v. Lerner/krivulka
Court of Appeals of Arizona, 2024
Argabright v. Rheem Manufacturing Co.
258 F. Supp. 3d 470 (D. New Jersey, 2017)
Viking Yacht Co Inc v. Composites One LLC
385 F. App'x 195 (Third Circuit, 2010)
Asp v. TOSHIBA AMERICA CONSUMER PRODUCTS, LLC
616 F. Supp. 2d 721 (S.D. Ohio, 2008)
PETRI PAINT CO., INC. v. OMG Americas, Inc.
595 F. Supp. 2d 416 (D. New Jersey, 2008)
Jefferson Loan Co. v. Session
938 A.2d 169 (New Jersey Superior Court App Division, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
819 A.2d 431, 359 N.J. Super. 135, 50 U.C.C. Rep. Serv. 2d (West) 489, 2003 N.J. Super. LEXIS 119, Counsel Stack Legal Research, https://law.counselstack.com/opinion/boc-group-inc-v-chevron-chemical-co-llc-njsuperctappdiv-2003.