Board of Governors of the University of North Carolina v. United States

33 Cont. Cas. Fed. 74,379, 10 Cl. Ct. 27, 32 Educ. L. Rep. 625, 1986 U.S. Claims LEXIS 877
CourtUnited States Court of Claims
DecidedMay 6, 1986
DocketNo. 88-85C
StatusPublished
Cited by3 cases

This text of 33 Cont. Cas. Fed. 74,379 (Board of Governors of the University of North Carolina v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Board of Governors of the University of North Carolina v. United States, 33 Cont. Cas. Fed. 74,379, 10 Cl. Ct. 27, 32 Educ. L. Rep. 625, 1986 U.S. Claims LEXIS 877 (cc 1986).

Opinion

OPINION

YANNELLO, Judge.

The facts relevant to defendant’s pending Motion to Dismiss are not in dispute and may be briefly stated.

The University of North Carolina (UNC) entered into a contract with the Agency for International Development (AID) in 1971. The contract provided for reimbursement of UNC’s costs, including overhead. The amount of reimbursement was initially based on stated provisional rates, with adjustments based on subsequently-known actual costs to be arrived at later.

For the period July 1, 1971, to June 30, 1974, UNC billed AID and was reimbursed an amount equal to 33.16 percent of salaries for on-eampus work and 18.04 percent of salaries for off-campus work. On January 23, 1974, the parties entered into a contract amendment establishing final overhead rates for that time period at 48.13 and 36.17 percent, respectively, for on-campus and off-campus work.

The rates established in the 1974 contract amendment also formed the basis for provisional rates for periods on and after July 1, 1974. UNC billed and was reimbursed at these rates through February 14,

1975.

In February 1975, UNC and AID executed a novation agreement transferring future rights to a third party, and on May 26, 1977, pursuant to a negotiated agreement, the final overhead rates for the period July 1, 1974, to June 30, 1975, (previously billed and reimbursed at provisional rates established in the 1974 contract amendment as discussed above) were established as 54.8 and 40.6 percent, respectively, for on-campus and off-campus work.

By letter dated March 9, 1979, UNC advised the contracting officer (CO) that “[f]or some inexplicable reason,” UNC had never billed AID for $274,858.09, representing two items:

(1) $238,946.65, representing the difference between the provisional and final rates for the 1971 to 1974 period; and
(2) $35,911.44, representing the difference between the provisional and final rates for July 1, 1974 to June 30, 1975.

Plaintiff was asked to submit a voucher for these amounts, and did so on January 6, 1981.

The claim was certified on December 27, 1983, and the CO issued his decision denying the claim on February 16, 1984. The instant suit was filed on February 13,1985.

There is no question in this case that the suit was initiated within 12 months of the receipt by UNC of the CO’s decision under [29]*29the provisions of 41 U.S.C. § 609(a)(1) and (3). Rather, defendant’s motion is based on the grounds that this court lacks jurisdiction because the statute of limitations contained in 28 U.S.C. § 2501 allegedly expired before the instant suit was filed (and, indeed, before the contractor elected, through certification of its claim to the CO, to proceed under the Contracts Disputes Act of 1978 (CDA), 41 U.S.C. §§ 601 et seq., and avail itself of the provisions of that Act).

Discussion

The critical time periods here may be summarized as follows: With respect to the first item of the claim, the billing periods were from July 1, 1971, to June 30, 1974, and the amendment to the contract establishing the final rates was executed on January 23, 1974. With respect to the second item of the claim, the billing periods were from July 1, 1974, to February 14, 1975, and the novation agreement establishing the final rates was entered into on May 26, 1977.

Defendant urges that, even taking the latest possible date of accrual of this claim, May 26, 1977, UNC’s claim here, initiated in 1985, is time-barred.1 The statute of limitations relied upon, 28 U.S.C. § 2501, provides that claims over which this court has jurisdiction must be brought within six years of the date they accrue. Such claims are, primarily, claims under the Tucker Act, 28 U.S.C. § 1491, including claims arising under a contract.

Generally stated, such Tucker Act contract claims would have included the instant suit—a suit for breach of contract for failure of the government to pay cost reimbursements as required by the contract. UNC could have initiated such suit in this court, in the first instance, between 1977 and 1983.2

However, on March 1, 1979, the provisions of the CDA became effective. The CDA applied to all contracts, as defined in that Act, which were entered into thereafter; it also allowed the contractor who had claims arising under contracts entered into before that date, which were either pending before the CO at the time of the [30]*30Act or initiated thereafter, to elect to proceed under the CDA. In proceeding under that statute, all disputes and all claims (whether breach of contract claims or claims for redress “under” the contract) were subject to a singular treatment: all must be submitted to the CO.

Thus, the CDA provided that, for a claim such as UNC’s, presentment must first be made to the CO (as contrasted with a Tucker Act breach of contract claim which could be presented directly to this court.) However, the CDA provided no limitations period in which claims must be presented (or certified) to the CO. (It did provide a limitations period in which suits contesting the CO’s decision could be brought in this court, but, as noted at the outset, that provision is not in issue here.)3 The contractor here elected to proceed under the CDA when, in December 1983, it certified its claim to the CO.4

Defendant argues that UNC’s attempt to elect to proceed under the CDA should not be countenanced, since, at the time it certified its claim (in December 1983), the general six-year statute of limitations had already expired with respect to the cause of action accruing, at the latest, in May 1977. In this context, the defendant’s linkage of the presentment of claims under the CDA and the general statute of limitations is without foundation. The CDA provides no limitations period for the presentment (and proper certification) of claims. The general statute of limitations, 28 U.S.C. § 2501, applies only to suits over which this court has jurisdiction. Under the CDA, this court has no jurisdiction until a decision has been issued by the CO (or he fails to timely issue such a decision, which is not in issue here), following the proper presentment of the claim to him.

Thus, we can find no basis for applying the general six-year statute of limitations with respect to suits over which this court has jurisdiction as the limitations period for the presentment of a claim to the CO under the CDA—which provides no limitations period for such presentment.

Moreover, defendant argues that the enactment of the CDA—with its absence of limitations periods in which to elect to proceed under the Act and to present certified claims to the CO—cannot be used as a vehicle to resurrect claims which would otherwise be extinguished by the general six-year statute of limitations.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sucesion J. Serralles, Inc. v. United States
46 Fed. Cl. 773 (Federal Claims, 2000)
Pathman Construction Co. v. United States
33 Cont. Cas. Fed. 74,394 (Court of Claims, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
33 Cont. Cas. Fed. 74,379, 10 Cl. Ct. 27, 32 Educ. L. Rep. 625, 1986 U.S. Claims LEXIS 877, Counsel Stack Legal Research, https://law.counselstack.com/opinion/board-of-governors-of-the-university-of-north-carolina-v-united-states-cc-1986.