Board of Education v. W. Harley Miller, Inc.

236 S.E.2d 439, 160 W. Va. 473
CourtWest Virginia Supreme Court
DecidedJuly 26, 1977
DocketCC899
StatusPublished
Cited by76 cases

This text of 236 S.E.2d 439 (Board of Education v. W. Harley Miller, Inc.) is published on Counsel Stack Legal Research, covering West Virginia Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Board of Education v. W. Harley Miller, Inc., 236 S.E.2d 439, 160 W. Va. 473 (W. Va. 1977).

Opinions

Neely, Justice:

The Court granted this appeal for the purpose of settling the law of arbitration in this State. The exact issues before us were raised and discussed in the majority opinion by Justice Haden and the concurring opinion by this writer when the case first appeared before us two years ago. See, Board of Ed., etc. v. W. Harley Miller, Inc., _ W. Va. _, 221 S.E.2d 882 (1975). The basic issue before us now is to what extent and in what manner a court should enforce an arbitration award, which is rendered without fraud pursuant to a standard arbitration provision in a commercial contract.

This appeal is a certified question which asks whether the circuit court has jurisdiction to enforce an arbitration award upon a motion for summary judgment by the party prevailing at arbitration. The Circuit Court of Berkeley County held that it did not have such jurisdiction, and we reverse.

The factual context in which the issues were presented involves a dispute between the Berkeley County Board of Education (Board), as owner, and W. Harley Miller, Inc. (Miller), as contractor, over Miller’s excavation and removal of rock from the North Berkeley High [475]*475School construction site. Miller claimed the Board owed him a substantial sum of money above the agreed contract price for this work. The Board resisted Miller’s claim by asserting Miller did not follow the contract’s procedures for computing the volume of rock in place. To settle the dispute Miller demanded arbitration pursuant to a standard arbitration provision contained in the construction contract with the Board. That contract provision is:

“All claims, disputes and other matters in question arising out of, or relating to this Contract or the breach thereof, ... shall be decided by arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association then obtaining unless the parties mutually agree otherwise. This agreement to arbitrate shall be specifically enforceable under the prevailing arbitration law. The award rendered by the arbitrators shall be final and judgment may be entered upon it in accordance with applicable law in any court having jurisdiction thereof.”

The Board responded to Miller’s demand for arbitration by filing a declaratory judgment action in the Circuit Court of Berkeley County and by seeking a preliminary injunction restraining Miller from proceeding to arbitration. The preliminary injunction issued against Miller, pending the outcome of the declaratory judgment action. Following the Circuit Court’s denial of Miller’s motion to dissolve the preliminary injunction, Miller appealed the injunction order to this Court where we reversed the circuit court and remanded the case with instructions to dissolve the preliminary injunction and to abate the action so that the parties could proceed to arbitration, Board of Ed., etc. v. W. Harley Miller, supra.

The dispute was then submitted to a duly selected panel of arbitrators, who rendered their award for $323,291.52 in favor of Miller in November 1976. After receiving the award, Miller filed a Petition to Enforce Award of Arbitrators in the abated declaratory judg[476]*476ment action. On motion of the parties, Miller’s petition was taken as a motion for summary judgment and the Board’s answer to the petition was taken as an affidavit in opposition to the summary judgment motion. The circuit court then refused to grant the motion for summary judgment, on the ground it lacked jurisdiction, and the circuit court certified the jurisdictional question to this Court.

I.

The Court has read a large number of conflicting cases on arbitration in this State,1 the mother Commonwealth of Virginia, and other jurisdictions. Arbitration, apparently, has an enormous potential both for good and for evil. As the concurring opinion recognized in the first Board v. Miller case, supra, litigation is a poor way to resolve controversies. It is expensive, time consuming, and tends to engender ill will which jeopardizes continuing business relationships. Consequently, where both parties are concerned with speedy, economical, conflict resolution, and harmonious business relations, they will often prefer arbitration to litigation, and incorporate this preference in their contracts. This writer in his concurring opinion in the first Miller case, supra, tended to emphasize the advantages of arbitration without giving sufficient attention to its disadvantages. Board v. Miller, supra, 221 S.E.2d at 886.

[477]*477Many of the disadvantages of arbitration are detailed in the factual contexts of earlier West Virginia cases which denied enforcement of arbitration agreements. While the results in these prior West Virginia cases may be correct, the legal reasoning is confusing and gives no clear answer to the problem at hand.

The early cases draw directly on Vynior’s Case, 8 Co. 80a, 81b (1609), decided by Lord Coke. This case is the basic authority for the proposition that at common law a submission to arbitration may be revoked.2 Kill v. Hollister, 1 Wilson 129 (K. B. 1746), followed up on Vynior’s Case by explaining the rationale for the doctrine of revo-cability: arbitration agreements, it seemed, ousted courts of their jurisdiction. This rationale has persisted into modern common law arbitration cases, with perhaps one significant modification, the doctrine of condition precedent. Scott v. Avery, 5 H. L. Cas. 811 (1856) is the foremost English authority on this doctrine, holding that parties may agree that no cause of action arise upon their contract until after there has been arbitration of contractual disputes. The Commonwealth of Virginia, before West Virginia became a state, had incorporated the doctrine of Scott v. Avery as well as the underlying doctrine of revocability into her common law which then passed into our own law. See, Condon v. South Side R. Co., 55 Va. (14 Gratt.) 302 (1858).

Very little illumination with regard to the proper rule for arbitration and the underlying social policy support[478]*478ing that rule can be gleened from the prior West Virginia cases because they talk in terms of “jurisdiction,” “conditions precedent”, “implied conditions precedent”, and “revocability”. Most of the prior West Virginia cases indulge in what this writer would call a rule selection process, and contain little cogent functional analysis.

II.

The basic problem in all arbitration cases could probably best be explained not in terms of legal characterizations such as “conditions precedent,” “ousting courts of their jurisdiction,” or “revocability,” but rather by a hypothetical case in the tradition of the ancient fableist Aesop. Let us assume for a minute that for some reason all the rabbits and all the foxes decided to enter into a contract for mutual security, one provision of which were that any disputes arising out of the contract would be arbitrated by a panel of foxes. Somehow that shocks our consciences, and it doesn’t help the rabbits very much either.

Now, what happens if we have the same contract with the same arbitration provision, except that disputes will be arbitrated by a panel of wolves? Is there such a community of interest among foxes and wolves that the wolves cannot be impartial? Possibly.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Nationstar Mortgage v. Adam and Bethany West
785 S.E.2d 634 (West Virginia Supreme Court, 2016)
Ryan Cunningham v. Ronald F. LeGrand and Mountain Country Partners
785 S.E.2d 265 (West Virginia Supreme Court, 2016)
Wayne and Joyce Kirby v. Lion Enterprises, Inc.
West Virginia Supreme Court, 2014
Credit Acceptance Corp. v. Robert J. and Billye S. Front, etc.
745 S.E.2d 556 (West Virginia Supreme Court, 2013)
Brandy Pingley v. Perfection Plus Turbo-Dry
746 S.E.2d 544 (West Virginia Supreme Court, 2013)
Brown ex rel. Brown v. Genesis Healthcare Corp.
729 S.E.2d 217 (West Virginia Supreme Court, 2012)
State Ex Rel. Richmond American Homes of West Virginia, Inc. v. Sanders
717 S.E.2d 909 (West Virginia Supreme Court, 2011)
Brown Ex Rel. Brown v. Genesis Healthcare
724 S.E.2d 250 (West Virginia Supreme Court, 2011)
Ruckdeschel v. Falcon Drilling Co., LLC
693 S.E.2d 815 (West Virginia Supreme Court, 2010)
Schultz v. AT & T Wireless Services, Inc.
376 F. Supp. 2d 685 (N.D. West Virginia, 2005)
Walther v. Sovereign Bank
872 A.2d 735 (Court of Appeals of Maryland, 2005)
State ex rel. City Holding Co. v. Kaufman
609 S.E.2d 855 (West Virginia Supreme Court, 2004)
State Ex Rel. Wells v. Matish
600 S.E.2d 583 (West Virginia Supreme Court, 2004)
State Ex Rel. Dunlap v. Berger
567 S.E.2d 265 (West Virginia Supreme Court, 2002)
HAROLD ALLEN'S MOBILE HOME OUTLET, INC. v. Butler
825 So. 2d 779 (Supreme Court of Alabama, 2002)
Adkins v. Labor Ready, Inc.
185 F. Supp. 2d 628 (S.D. West Virginia, 2001)
State ex rel. Barden & Robeson Corp. v. Hill
539 S.E.2d 106 (West Virginia Supreme Court, 2000)
STATE EX REL. BARDEN AND ROBESON v. Hill
539 S.E.2d 106 (West Virginia Supreme Court, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
236 S.E.2d 439, 160 W. Va. 473, Counsel Stack Legal Research, https://law.counselstack.com/opinion/board-of-education-v-w-harley-miller-inc-wva-1977.