Bluegreen Vacations Unlimited, Inc. v. T. Park Central LLC

CourtDistrict Court, S.D. New York
DecidedJanuary 28, 2025
Docket1:24-cv-08009
StatusUnknown

This text of Bluegreen Vacations Unlimited, Inc. v. T. Park Central LLC (Bluegreen Vacations Unlimited, Inc. v. T. Park Central LLC) is published on Counsel Stack Legal Research, covering District Court, S.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bluegreen Vacations Unlimited, Inc. v. T. Park Central LLC, (S.D.N.Y. 2025).

Opinion

UNITED STATES DISTRICT COURT SOUTHERN DISTRICT OF NEW YORK ---------------------------------------------------------------------- X : BLUEGREEN VACATIONS UNLIMITED, INC., : : Petitioner, : : 24-CV-8009 (JMF) -v- : : MEMORANDUM OPINION T. PARK CENTRAL LLC et al., : AND ORDER : Respondents. : : ---------------------------------------------------------------------- X JESSE M. FURMAN, United States District Judge: This case arises from a contractual dispute over a complex real estate transaction between Petitioner Bluegreen Vacations Unlimited, Inc. (“Bluegreen” or “Petitioner”) and Respondents T. Park Central LLC, O. Park Central LLC and New York Urban Ownership Management, LLC (collectively, “Respondents”). Section 12.3 of the parties’ contract contains a mandatory arbitration clause, providing that any disputes arising out of the agreement are to be resolved by a three-member panel of arbitrators (the “Tribunal”). ECF No. 11-1 (“Interim Award”), at 12- 13. The provision further states that the Tribunal “shall have the authority to award only actual damages” and that “[n]o Party shall be in default until ten (10) days after the determination of such arbitration of the Dispute and such default shall be deemed cured if cured within such ten (10) day period.” Id. In 2021, Respondents initiated arbitration proceedings, asserting two contract claims and one claim for breach of the implied covenant of good faith and fair dealing. Following extensive arbitration proceedings, including a twenty-day evidentiary hearing, the Tribunal issued an eighty-one-page decision styled “Interim Award.” See id. The Tribunal found in Respondents’ favor on the two contract claims (and denied the implied covenant claim as duplicative). See id. at 79. But citing the cure provision in Section 12.3 of the parties’ agreement, the Tribunal expressly declined to reach the issue of remedy. See id. at 67-78 As the Tribunal explained: The decision whether to cure under § 12.3 is Bluegreen’s decision to make, and Bluegreen’s alone. Only in the event that Bluegreen fails to cure, or the Dispute is otherwise resolved by the Parties via a settlement, will it be necessary for the Tribunal to proceed to the remedy stage of this Arbitration. In the event that Bluegreen decides not to cure its breaches, the Tribunal will need to determine whether and, if so, to what extent, TMC is entitled to recover monetary damages for Bluegreen’s breaches. The Tribunal notes that the Parties vigorously disagree about TMC’s entitlement to general monetary damages and whether TMC has proven such damages. Id. at 68; see also id. at 70 (“tak[ing] no position at this time” on the parties’ disputes “with respect to whether [Respondents are] entitled to recover general monetary damages and, if so, the amount of such damages”). The Tribunal “direct[ed] the Parties to meet and confer . . . to determine whether and, if so, how Bluegreen will cure its breaches of the [contract], and to report back to the Tribunal concerning those efforts.” Id. at 76-78. More specifically, the Tribunal ordered the parties, following a meet-and-confer, to file letters addressing a handful of issues and scheduled “a status conference . . . for the purpose of determining what further proceedings, if any, are necessary before the Tribunal issues its Final Award.” Id. at 78. Apparently without waiting for that process to run its course, however, Bluegreen filed a petition in this Court (the “Petition”), seeking, pursuant to Section 10 of the Federal Arbitration Act (“FAA”), 9 U.S.C. § 10, to vacate the Interim Award. ECF No. 13 (“Am. Pet.”).1 Upon review of the parties’ submissions and the Interim Award itself, the Court concludes that the Petition must be dismissed because the Court lacks authority to review the

1 The record is silent with respect to what, if anything, has happened in the arbitration proceedings since the Tribunal’s ruling. The Court presumes that the proceedings have been stayed pending adjudication of the Petition in this case. Interim Award. “By its terms, the FAA gives courts the power to confirm only a final ‘award’ of an arbitral panel.” Major League Baseball Players Ass’n v. Arroyo, No. 24-CV-3029 (LJL), 2024 WL 3539575, at *3 (S.D.N.Y. July 24, 2024) (citing 9 U.S.C. § 9). “In order to be ‘final,’” the Second Circuit has explained, “an arbitration award must be intended by the arbitrators to be

their complete determination of all claims submitted to them. Generally, in order for a claim to be completely determined, the arbitrators must have decided not only the issue of liability of a party on the claim, but also the issue of damages.” Michaels v. Mariforum Shipping, S. A., 624 F.2d 411, 413-14 (2d Cir. 1980) (citation and footnote omitted). Put differently, “an arbitration award, to be final, must resolve all the issues submitted to arbitration, and . . . it must resolve them definitively enough so that the rights and obligations of the two parties, with respect to the issues submitted, do not stand in need of further adjudication.” Rocket Jewelry Box, Inc. v. Noble Gift Packaging, Inc., 157 F.3d 174, 176 (2d Cir. 1998) (emphasis omitted); accord Kerr- McGee Refin. Corp. v. M/T Triumph, 924 F.2d 467, 471 (2d Cir. 1991). The Second Circuit’s decision in Michaels is especially instructive here. It arose from a

two-year time charter party between a charterer and ship owner that was terminated early by the charterer, prompting arbitration proceedings. Michaels, 624 F.2d at 412. The arbitration panel issued an interim award resolving liability, but not damages, on five of the owner’s six counterclaims and deferring decision on the charterer’s six claims. Id. at 412-13. The charterer sought to vacate the interim award in federal court. The district court denied the petition on the merits, but on appeal, the Second Circuit held that the district court had erred in doing so because the award was not final and, thus, the court lacked power under the FAA, to review it. Indeed, the court of appeals did not even consider the issue to be a close one. “Since the interim award here did not decide any of Charterer’s claims,” the court explained, “it obviously was not a final determination of all issues submitted.” Id. at 414 (emphasis added); see also Metallgesellschaft A.G. v. M/V Capitan Constante, 790 F.2d 280, 283 (2d Cir. 1986) (“Clearly, the arbitrators’ award in [Michaels] was not intended to be, and was not, a final award.”). “Moreover,” the Michaels court continued, “with the exception of the one Owner counterclaim decided in

Charterer’s favor, which Charterer obviously does not attack, the award did not finally dispose of any of the claims submitted, since it left open the question of damages on the four counterclaims of Owner that it sustained and reserved decision on the fifth.” Michaels, 624 F.2d at 414. Applying these standards here, the Court is compelled to conclude that the Interim Award is not final because, like the interim award in Michaels, it “did not finally dispose of any of the claims submitted, since it left open the question of damages.” Id. Moreover, it is plain from the Interim Award’s terms that the Tribunal did not “intend[]” the ruling “to be their complete determination of all claims submitted to them.” Id. at 413.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
Bluegreen Vacations Unlimited, Inc. v. T. Park Central LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bluegreen-vacations-unlimited-inc-v-t-park-central-llc-nysd-2025.