Blue Ocean Preservation Society v. Watkins

767 F. Supp. 1518, 22 Envtl. L. Rep. (Envtl. Law Inst.) 20259, 33 ERC (BNA) 1640, 1991 U.S. Dist. LEXIS 8863, 1991 WL 114121
District Court, D. Hawaii·Decided June 25, 1991·No. Civ. 90-00407 DAE·Published·Cited by 7 cases

Opinion

ORDER GRANTING PLAINTIFFS’ MOTION FOR SUMMARY JUDGMENT AND A PERMANENT INJUNCTION AND DENYING DEFENDANTS’ COUNTER MOTION TO DISMISS THE CASE AS MOOT

DAVID A. EZRA, District Judge.

I. Introduction

This lawsuit seeks to compel preparation of a federal Environmental Impact Statement (“EIS”) for the Hawaii Geothermal Energy Project (the “Project”) and to enjoin any further federal participation in the Project until the EIS is completed. Last January on plaintiffs’ and defendants’ (or the “government” ’s) motions for summary judgment, the court ruled that the remain *1520 ing phases of the project constitute “major federal action” within the meaning of the National Environmental Policy Act (“NEPA”). 42 U.S.C. § 4332(2)(C). Responding to the government’s contention that the matter was not yet ripe, the court also ruled that there remained issues of fact (1) as to the Department of Energy’s (“DOE” ’s) level of commitment to the Project, and (2) as to DOE’s role in implementation of the Project.

In the wake of that decision, DOE attempted to “reprogram” the $5 million Congress had already appropriated to the Project, but Congress rebuffed the attempt, and directed that at least some of the money be used toward an EIS. Plaintiffs have now brought a new summary judgment motion, arguing that given Congress’ reaction to the reprogramming effort, the case is now ripe, and submitting substantial evidence of the Project’s potential impact on the environment.

The government, rather than address plaintiffs’ arguments for summary judgment on the merits, has simply moved for dismissal, arguing that the entire case is moot.

II. Background

A complete statement of background facts is set forth in the court’s Order Denying Defendant United States’ Motion for Summary Judgment and Granting Plaintiffs’ Motion for Partial Summary Judgment, filed January 8, 1991 (“January 8 Order”), published at 754 F.Supp. 1450 (D.Hawaii 1991). A brief summary of those facts follows, supplemented by the developments of the last six months.

A. The Project

The Project is a cooperative venture of both the State of Hawaii and the federal government to facilitate the development of geothermal power as an alternative energy source in Hawaii. It involves four distinct stages or phases leading to the private development of a 500 megawatt geothermal power plant on the slopes of the Kilauea crater, an active volcano on the Island of Hawaii. The first two phases, involving (1) the building of a small plant for research and testing, and (2) research regarding the feasibility of transporting the power generated to other islands via underwater cable, have already been completed, and any attempt to obtain an EIS for those phases was deemed moot. January 8 Order, 754 F.Supp. at 1459. Phase III, entitled the Geothermal Resource Verification and Characterization Program, is now in progress, and involves the drilling of twenty-five (25) commercial-scale exploration wells throughout the Kilauea East Rift Zone in order to “verify” the geothermal resource. This verification will clear the way for Phase IV, the construction of the full 500 megawatt project.

Phase III is proceeding with funds appropriated by the Hawaii state legislature. So far, at least two slim-bore scientific observation holes (“SOHs”) have been drilled, and four more are called for. It is anticipated that federal funds will be utilized to drill the 25 full-scale holes in areas “proven” by the SOH drilling.

Phase IV will involve the construction of up to twenty (20) separate geothermal power plants of about 25 megawatts apiece. Each of these will employ eight to ten working wells. The separate plants will necessarily be connected by a network of roads, plumbing, and power lines throughout the subzone areas. It will also involve the laying of overland and underwater cable to carry the power generated to the islands of Maui and Oahu.

B. Federal Funding of the Project

As discussed by the court in its January 8 Order, 754 F.Supp. at 1453, Congress has thus far contributed $34.7 million, over 80% of the total funding, to Phases I and II of the Project, and had recently appropriated an additional $5 million toward Phase III. 1 *1521 This $5 million was the first of three such appropriations anticipated from Congress over the next three years. 754 F.Supp. at 1455.

At the hearing on December 17, 1990, counsel for the government suggested that the $5 million appropriation did not bind DOE to use the money for the Project, and that DOE had not yet decided whether to continue its support of the Project. Unable to determine the validity of this claim on the evidence before it, the court determined that issues of fact remained as to (1) DOE’s level of commitment to the implementation of Phase III, and (2) DOE’s role with respect to the $5 million appropriation. 754 F.Supp. at 1465-66.

1. DOE’s Reprogramming Request

After this court ruled that the government’s participation in the Project constituted “major federal action” based largely on the $5 million appropriation, DOE sought to “reprogram” the money, and have it applied to another project. When DOE announced its intention to seek reprogramming at a pretrial conference on February 12,1991, the court granted a continuance with the concurrence of all parties of the February trial date in order to permit DOE and Congress to settle the status of the funding.

Plaintiffs conducted some discovery on this reprogramming process, and obtained a single document from DOE: an internal memorandum dated December 1, 1986, detailing DOE’s reprogramming procedure (the “Memo”, Plaintiff’s Exhibit 4). The Memo explicitly acknowledges that an agency is expressly forbidden from spending a Congressional appropriation for purposes other than those for which they were appropriated. 31 U.S.C. § 1301(a).

The Memo goes on to explain, however, that reprogramming may be sought by first clearing the request with the Office of Management and Budget, and then submitting it to the appropriate Congressional committees. Memo at 2. Until Congress acts on the request, the funds are placed into a special DOE reserve account. Memo at 5. If the request for reprogramming is not approved, the funds must be used for the purposes stated in the original appropriation. Memo at 2.

There does not appear to be any other statutory or regulatory guideline governing the reprogramming procedure. DOE was simply pursuing its own prescribed method for obtaining Congressional approval to deviate from the terms of the original appropriation.

2. The Congressional Reaction to the Reprogramming Request

U.S. Senator Daniel K.

Free access — add to your briefcase to read the full text and ask questions with AI

Blue Ocean Preservation Society v. Watkins, 767 F. Supp. 1518, 22 Envtl. L. Rep. (Envtl. Law Inst.) 20259, 33 ERC (BNA) 1640, 1991 U.S. Dist. LEXIS 8863, 1991 WL 114121 (D. Haw. 1991).

767 F. Supp. 1518 (Blue Ocean Preservation Society v. Watkins) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Los Alamos Study Group v. United States Department of Energy
794 F. Supp. 2d 1216 (D. New Mexico, 2011)
Pit River Tribe v. Bureau of Land Management
306 F. Supp. 2d 929 (E.D. California, 2004)
Fund for Animals v. Jones
151 F. Supp. 2d 1 (District of Columbia, 2001)
Don't Ruin Our Park v. Stone
802 F. Supp. 1239 (M.D. Pennsylvania, 1992)