Blue Mountain Construction Company, a Corporation v. H. C. Werner and Tauf Charneski

270 F.2d 305
CourtCourt of Appeals for the Ninth Circuit
DecidedSeptember 21, 1959
Docket16206
StatusPublished
Cited by29 cases

This text of 270 F.2d 305 (Blue Mountain Construction Company, a Corporation v. H. C. Werner and Tauf Charneski) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Blue Mountain Construction Company, a Corporation v. H. C. Werner and Tauf Charneski, 270 F.2d 305 (9th Cir. 1959).

Opinions

ORR, Circuit Judge.

On the 4th day of April, 1958, appellant filed in the United States District Court of Oregon a complaint seeking damages for alleged breaches of three sub-contracts entered into with appellees.

On April 28, 1958, defendants served and filed their answer. No affirmative relief was sought.

[306]*306On May 19, 1958, appellant moved for a dismissal of the action without prejudice under Rule 41(a) (2), F.R.Civ.P., 28 U.S.C.A.1 No supporting affidavit was presented and no reasons were given for the dismissal. Appellee objected to the dismissal on the ground that appellee had “undertaken at considerable expense to go through this thing and prepare ourselves for our answer and also to prepare ourselves for trial.”

The court denied the motion. Whether or not a dismissal will be granted is within the sound judicial discretion of the court. Ockert v. Union Barge Line Corp., 3 Cir., 1951, 190 F.2d 303; Rollison v. Washington National Ins. Co., 4 Cir., 1949, 176 F.2d 364. We think it follows that each case must be determined on its own particular facts. We find no abuse of discretion in the denial of this motion. There was no showing whatever in support of the motion. It was no more than a request. Counsel for appellants, other than the one making the first motion, evidently sensing the inadequacy of the showing made in support of said motion, on May 23, 1958 filed a second motion entitled “Motion for Reconsideration of and Renewing Plaintiff’s Motion for a Voluntary Dismissal Without Prejudice pursuant to Rule 41(a) (2).” This motion was supported by an affidavit setting forth the reasons why the dismissal was desired. In essence the supporting affidavit stated: that plaintiff’s attorney had erroneously concluded that the only forum available to appellants to obtain redress on its alleged causes of action was by an action in the United States District Court of Oregon, inasmuch as the appellees were residents of Oregon and could not be reached in a suit instituted in the state of Washington ; that thereafter appellant’s attorney determined that this theory was erroneous and further determined that his clients had a cause of action under the Miller Act, §§ 270a and 270b, 49 Stat. 793 (1935), 40 U.S.C.A. §§ 270a and 270b,2 and that under the terms of said act an action under it could only be brought in the district court having jurisdiction of the area in which the work was performed, in this case the Eastern District of Washington. Thus we have appellant squarely representing to the trial court that their purpose in requesting a dismissal in the Oregon District was to enable them to institute an action in the Eastern District of Washington.

The trial court had before it this picture upon which to act in exercising its discretion whether to dismiss. The dismissal was desired in order to permit [307]*307an action in the State of Washington because under appellant’s theory a suit under the Miller Act, which they wished to bring, could only be brought where the contract was to be performed. According to appellees this is a debatable question because, as they argue, the requirement of the Miller Act relates only to venue,3 citing Texas Construction Company v. United States, 5 Cir., 1956, 236 F.2d 138. That case does not depart from the established rule that a competent court could have jurisdiction of a case and try it where improper venue was laid only in the event the parties agreed. Of course the trial court here could not speculate as to whether the sureties would waive venue in the event they were made parties in the Oregon suit, nor did it try. However it nowhere appears that it was necessary to sue the sureties, no showing being made that the appellees are insolvent. Appellant’s complaint alleges three causes of action, two based on breach of contract and one for reformation of contract.

The first cause of action was for damages for failure to complete the concrete lining of a tunnel in time. The second cause of action was also for failure to complete the concrete lining of a tunnel in time. The third cause of action was for reformation so as to include certain provisions for the method of lining the tunnels and a time element.

The Miller Act provides that the requirement of the bond shall be for insuring payment of all persons “supplying labor and material.” (See note 2, supra). Appellees have argued that the causes of action alleged in the complaint in the Oregon Court could not have been brought under the Miller Act, hence the reasons given for dismissal had no validity. We expressly refrain from passing on this question. It is, we understand, before the District Court of Washington at this time. It should be noted, however, that the trial court in Oregon offered to dismiss the action there founded, as we have said, on breach of contract and for a reformation without prejudice if appellant would agree not to sue on said causes of action in Washington. What if any effect such an agreement would have had on the future right to litigate said causes of action in Oregon we are unable to say.

As against this lack of showing on the part of appellant, the trial court was justified in turning to the other side of the coin. The defendants have been brought into court in the State of their residence, a matter of great convenience to them. We understand that their witnesses reside in that jurisdiction. To require them to pull up stakes and move to another state would entail considerable additional expenses of hotel accommodations for the litigants and witnesses and the trial court could reasonably conclude that appellees’ lawyers would require additional fees and expenses to travel to a foreign state to try the case. It may be argued that appellees would have been subjected to these same expenses had appellant seen fit to sue in Washington in the first instance. That may be so, but we think that a court in exercising its discretion as to whether a dismissal for the express purpose of allowing a plaintiff to bring an action in a foreign state should be granted, is entitled to consider whether a plaintiff should be allowed to snatch from a defendant certain monetary advantages and conveniences which appellant has conferred by its voluntary act.

After the denial of their motion to dismiss, appellant informed the court that they refused to proceed further. Appellant took this position at its peril. If the trial court was in error in refusing to dismiss without prejudice appellant was on safe ground, but on the other hand, as we find there was no abuse of discretion then the subsequent action of the court in dismissing the action with [308]*308prejudice for want of prosecution was proper.

The trial court set the case for pretrial conference on July 21, 1958. The matter came on for pre-trial conference on said date. No appearance was made for or on behalf of appellant. In view of the information given the court that appellant would not proceed further, it justifiably concluded that there was a failure to prosecute and dismissed the action with prejudice under Rule 174 of the Oregon District Court and Rule 41(b) F.R.Civ.P.5

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Haynes v. Juarez
S.D. California, 2022
Ewing v. BF Advance, LLC
S.D. California, 2021
Young v. Target Corporation
S.D. California, 2021
Dalfio v. Tran
S.D. California, 2021
United States v. Gold Mountain Coffee, Ltd.
9 Ct. Int'l Trade 77 (Court of International Trade, 1985)
Gill v. Hall (In Re Hall)
15 B.R. 913 (Ninth Circuit, 1981)
Sams v. Beech Aircraft Corp.
625 F.2d 273 (Ninth Circuit, 1980)
Jackson v. Harris
84 F.R.D. 602 (N.D. Indiana, 1979)
Shellman v. United States Lines, Inc.
528 F.2d 675 (Ninth Circuit, 1975)

Cite This Page — Counsel Stack

Bluebook (online)
270 F.2d 305, Counsel Stack Legal Research, https://law.counselstack.com/opinion/blue-mountain-construction-company-a-corporation-v-h-c-werner-and-tauf-ca9-1959.