Blasland, Bouck & Lee, Inc. v. City of North Miami

96 F. Supp. 2d 1375, 51 ERC (BNA) 1603, 2000 U.S. Dist. LEXIS 6991, 2000 WL 553889
CourtDistrict Court, S.D. Florida
DecidedApril 27, 2000
Docket97-1484CIV
StatusPublished
Cited by1 cases

This text of 96 F. Supp. 2d 1375 (Blasland, Bouck & Lee, Inc. v. City of North Miami) is published on Counsel Stack Legal Research, covering District Court, S.D. Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Blasland, Bouck & Lee, Inc. v. City of North Miami, 96 F. Supp. 2d 1375, 51 ERC (BNA) 1603, 2000 U.S. Dist. LEXIS 6991, 2000 WL 553889 (S.D. Fla. 2000).

Opinion

MEMORANDUM OPINION ON CERCLA CLAIMS

HURLEY, District Judge.

THIS CAUSE is before the court upon the parties’ respective claims under the Comprehensive Environmental Response, Compensation, and Liability Act (“CERCLA”), 42 U.S.C. §§ 9601-75. The parties joined their CERCLA claims with several state law claims based on the same facts; the state law claims were heard by a jury while the CERCLA claims were submitted- to the court. 1 The seven-member jury returned a unanimous verdict on the state law claims, finding each party liable in part to the other. After the jury verdict, the court heard additional evidence relating solely to the CERCLA claims and now issues the following findings of fact and conclusions of law relevant to those claims.

I.FINDINGS OF FACT

1. Plaintiff/counter-defendant, Blasland, Bouck & Lee, Inc. (“BB & L”), is an environmental engineering firm.

2. Defendant/counter-plaintiff, the City of North Miami (the “City”), is a municipal corporation and the owner of a 350-acre parcel of property in north Miami known as the Munisport landfill (“Munisport”).

3. In an ill-conceived effort to upgrade the property for eventual use as a recreational area, the City permitted Munisport to be operated as a landfill from 1974 to 1980.

4. On September 8, 1983, the Environmental Protection Agency (“EPA”) placed Munisport on the National Priorities List of uncontrolled hazardous release sites due to the decomposition of waste into ammonia. The ammonia was leaching into the underlying groundwater and then migrating toward a mangrove preserve.

5. On July 26, 1990, the EPA issued its Record of Decision (“ROD”) pursuant to which it promulgated a comprehensive cleanup plan for the landfill.

6. On September 24, 1991,’ the City entered into a consent decree with the EPA, obligating the City to clean up Munisport and reimburse the EPA for its costs. The Consent Decree was approved by the court on March 20, 1992. See United States v. City of North Miami, Case No. 91-2834-Civ-Marcus (S.D.Fla.).

7. By written contract dated July 14, 1992, the City hired BB & L to assist it in implementing the cleanup plan for Munis-port. BB & L was primarily responsible for conducting hydrogeologic studies of the aquifer and using those studies to design a leachate collection system. The parties considered this work to be “in-scope work,” and it was to be performed for a fixed price ($1.4 million), as set forth, in the contract.

8. The contract also contemplated that additional work might be necessary and could be authorized with the parties’ mutual consent. The parties subsequently agreed to certain additional work and characterized it as “out-of-scope work.” The out-of-scope work was billed on a time-and-coSt basis at BB & L’s then-current hourly rates:

9. Contained within the contract was a provision known as the “pay-when-paid” clause, which stated:

City shall only be responsible for expeditiously processing (within five (5) days of receipt of invoice) payment of such invoices' of BB & L through the D.E.R. [Florida Department of Environmental Regulation], and BB & L recognizes that City’s obligation of payment of compensation is specifically contingent upon City’s receipt of funding from the *1378 D.E.R. for payment of such fees, costs, and expenses of BB & L.

See Pl.’s Ex. 11 at 2.

10. As required by the pay-when-paid clause, the City submitted BB & L’s invoices in a timely manner to the State.

11. The State paid the majority of BB & L’s invoices but refused to pay some, citing insufficient documentation. These unpaid invoices make up part of BB & L’s alleged damages.

12. Between July 1992 and June 1995, BB & L performed a variety of work at Munisport, including aquifer pump tests, computer modeling, and surface and groundwater sampling. In addition, BB & L breached a causeway (permitting tidal flow into a mangrove area), realigned a dike, and negotiated with the State concerning the City’s landfill closure permit application. BB & L was not paid for all of the work it performed.

13. One pump test (pump test # 3) BB & L conducted had particular significance. That test yielded a three-gallon-per-minute extraction rate. The extraction rate was substantially lower than both BB & L’s expectations and the rates from other pump tests. Despite this seemingly ano-malistic result, BB & L insisted upon using the three-gallon-per-minute rate as the basis for its design of the leachate collection system.

14. The three-gallon-per-minute rate was inaccurate and resulted from BB & L’s failure to comply with procedures and standards governing environmental engineers.

15. On June 1, 1995, prior to the completion of the project, the City terminated the contract with BB & L.

16. At the time of its termination, BB & L had not been paid for work valued at $486,083.51. Of that figure, $375,283.51 represented out-of-scope work, specifically work done on: (a) the causeway breach; (b) the dike realignment; and (c) the City’s landfill closure application. Unpaid in-scope work included: $75,000 for field data acquisition, $31,000 withheld by the State as retainage for the landfill closure permit application work, and $4,800.00 for surface water sampling.

17. The City never received from the State the amounts alleged in Finding of Fact 16 for field data acquisition, landfill closure permit application work, and surface water sampling.

18. The work for which BB & L had not been paid is unrelated to the work forming the basis of the City’s counterclaim for professional malpractice and, in particular, is unrelated to pump test # 3.

19. The City replaced BB & L with another environmental engineering firm, Se-cor International.

20. On May 7, 1997, BB & L sued the City, alleging a cost recovery claim under CERCLA, 42 U.S.C. § 9607 (Count I of the complaint), three state common law claims, and one state statutory claim.

21. The City counterclaimed against BB & L alleging a contribution claim under CERCLA, 42 U.S.C. § 9613 (Count III of the amended counterclaim), and two state common law claims.

Based on the foregoing, the court reaches the following:

II. CONCLUSIONS OF LAW

1. The court has jurisdiction over the parties’ CERCLA claims pursuant to 42 U.S.C. § 9613

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ashtabula River Corp. Group II v. Conrail, Inc.
549 F. Supp. 2d 981 (N.D. Ohio, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
96 F. Supp. 2d 1375, 51 ERC (BNA) 1603, 2000 U.S. Dist. LEXIS 6991, 2000 WL 553889, Counsel Stack Legal Research, https://law.counselstack.com/opinion/blasland-bouck-lee-inc-v-city-of-north-miami-flsd-2000.