Blake Construction Co. v. United States
618 F.2d 124, 221 Ct. Cl. 990, 218 Ct. Cl. 163
Procedural entryThis page is a short order in Blake Construction Co. v. United States. Read the opinion of the Court — 597 F.2d 1357 →
Opinion
On October 26, 1979 the court entered judgment for plaintiff in the amount of $642,684.07 based on a stipula[991]*991tion of the parties regarding Counts I, II, III and VIII, and in all other respects the petition was dismissed.
Free access — add to your briefcase to read the full text and ask questions with AI
Blake Construction Co. v. United States, 618 F.2d 124, 221 Ct. Cl. 990, 218 Ct. Cl. 163 (cc 1979).
618 F.2d 124 (Blake Construction Co. v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.