Blake Construction Co. v. United States

585 F.2d 998, 25 Cont. Cas. Fed. 82,753, 218 Ct. Cl. 163, 1978 U.S. Ct. Cl. LEXIS 292
United States Court of Claims·Decided October 18, 1978·No. No. 757-71·Published·Cited by 1 cases

Opinion

Skelton, Senior Judge,

delivered the opinion of the court:

Blake Construction Company, Inc. (Blake or plaintiff), a corporation, sues the United States (Government or defendant) for the recovery of money owing to it by the Government under a building construction contract. The Government claims the right of set-off for amounts it paid to adjacent property owners for damages to their buildings during construction of the Government building by Blake. We hold for the Government.

The facts in this case show that on or about January 24, 1964, Blake entered into contract No. GS-03B-14060 (Project No. 49912) as an independent contractor with the General Services Administration (GSA) as the agent of the United States, to demolish a building known as the Wilkins Building, which was owned by the Government, and to excavate a basement on the site of the Wilkins Building and construct thereon a nine-story building to house the United States Court of Claims and the United States Court of Customs and Patent Appeals (Court Building). The Wilkins Building was located at 1512 "H” Street, N.W., in Washington, D.C. Its demolition, together with the basement excavation and the construction of the court building, were all included in the one contract as one composite project to be performed by Blake. The contract had detailed written specifications, including the following pertinent provisions, among others:

67-4 EXCAVATION
j. Adjacent Buildings, pavements, utilities and grades shall be protected during excavation work.
67-06 SHORING AND UNDERPINNING
a. Contractor, at his expense, shall provide and install all shoring, lagging, bulkheading, sheet piling, un[168]*168derpinning and other protective facilities or measures as may be required to adequately contain all banks and sides of excavations, and to protect at all times adjacent structures, facilities and utilities. Such work shall include adequate bracing and underpinning to prevent any settlement and to comply with all applicable building and safety codes, and to protect life, limb and property.
b. Contractor shall submit to the Architect for review, proposed designs for the shoring and underpinning complete with calculations prepared by a Registered Civil or Structural Engineer and bearing his seal prior to starting the work. The Architect or the Government does not in any way assume responsibility for the designs due to the above submission or general approval. Contractor shall assume the entire responsibility for all shoring and underpinning and shall make good at his expense any damage caused by or due to improper supports, underpinning, or failure of shoring in any manner or respect.
c. Shoring or underpinning is required, but not limited to, the areas indicated on drawings. Should additional shoring or underpinning be required, the contractor shall provide the additional shoring or underpinning at no additional cost to the Government.
d. Prior to commencement of the excavations, the Contractor and Government shall jointly survey the condition of the adjoining properties, including photographs and records of any prior settlement or cracking of walls, partitions, floors, etc., that may become the subject of possible damage claims. Such damage as noted shall be suitably marked on the structure, and the official list of existing damage shall be signed by all parties making the survey.
e. Prior to excavation, the Contractor shall establish a series of points, within and around the existing adjacent buildings, such points being suitable for taking levels and acting as bench marks. The datum sued to establish the elevations for these bench marks shall be sufficiently distant from the excavation so as not to be affected by any settlement resulting from the excavation operations. Elevations on these points shall be taken prior to commencement of excavation and the results noted in permanent form. These points shall be checked once weekly by a person properly qualified to perform level work. Copies of all reading and established elevations shall be submitted to the Architect without delay after levels have been taken. Any settlement noted as a result of these levels shall be reported immediately to the [169]*169Architect. Any cracks, sags, or damage of any nature to the adjoining properties not noted in the original survey, shall be reported to the Architect.
f. All shoring, sheet piling, etc. considered to be temporary, shall be removed before backfilling is completed, but not until permanent supports are in position and approval of the Architect has been obtained.
$ ‡ ‡ ‡ $
12. PERMITS AND RESPONSIBILITIES
The Contractor shall, without additional expense to the Government, be responsible for obtaining any necessary licenses and permits, and for complying with any applicable Federal, State, and municipal laws, codes, and regulations, in connection with the prosecution of the work. He shall be similarly responsible for all damages to persons or property that occur as a result of his fault or negligence. He shall take property safety and health precautions to protect the work, the workers, the public, and the property of others. * * *
% sjs jj: %

Blake entered into a contract on or about February 10, 1964, with Morauer and Hartzell, Inc. (M & H), as an independent sub-contractor, under which the latter agreed to perform all excavation, filling, back filling and grading for the construction of the court building that Blake was required to perform as prime contractor under its contract with GSA.

Blake entered into a contract with Eastern Foundation Company, Inc. (Eastern), as an independent sub-contractor, on or about June 2, 1964, whereby Eastern agreed to furnish all the labor, materials and services in connection with the sheeting, shoring and underpinning that Blake was required to furnish as the prime contractor.

The Wilkins Building, which occupied the part of the court building site on "H” Street, N.W., where the court building was to be constructed, was a nine-story building located immediately west of and adjacent to a five-story building at 1510 "H” Street, N.W. The two buildings had a common party wall. The building at 1510 "H” Street was owned by the American Vocational Association, Inc. (AVA), and it had a common party wall with a building located immediately to the east at 1508 "H” Street, N.W., owned by Riggs National Bank (Riggs).

[170]*170Blake began performance of the contract soon after it was signed on January 24, 1964, and between that date and February 27, 1964, it had razed the Wilkins Building and M & H had begun the excavation work for the basement of the court building (as shown by paragraph 41 of Blake’s petition.)

Other pertinent facts are shown by the Stipulation of Facts filed herein by the parties as follows:

"7. * * * The United States was the owner of the Wilkins Building at the time it was demolished. The Wilkins Building, prior to its demolition, was situated directly to the west of a building known as 1510 "H” Street N.W., which it adjoined by a party wall and directly upon a portion of the contract site upon which Blake contracted to construct the Court Building.

Free access — add to your briefcase to read the full text and ask questions with AI

Blake Construction Co. v. United States, 585 F.2d 998, 25 Cont. Cas. Fed. 82,753, 218 Ct. Cl. 163, 1978 U.S. Ct. Cl. LEXIS 292 (cc 1978).

585 F.2d 998 (Blake Construction Co. v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related